Combi-wall installation - CIPA Lumber

Fraser River Pile & Dredge (GP) Inc., on behalf of CIPA Lumber (the Applicant) proposes to conduct bank stabilization works to install a combination wall comprised of sheet-pile and steel pipe piles riverward of an existing compromised sheet pile wall at 797 Carlisle Road, Delta, BC. The project would consist of the following:
 

  • Install a combi-wall (i.e., comprised of a combination of sheet-piles and steel pipe piles) riverward of the existing compromised sheet pile wall.
  • Once the combi-wall is installed, fill material would be placed in the interstice of the proposed and existing (compromised) sheet pile wall and would extend landward, overtop of the existing wall, to the existing concrete slab supporting the building.
  • Potentially removing up to five recently installed steel pipe piles to facilitate installation of the new wall (as required).


The works will be conducted via a marine spud derrick equipped with a vibratory hammer for the sheet-piles and steep pipe piles and a clam-shell bucket for the placement of fill material overtop of the completed wall. Pile driving will be conducted during daytime hours, however nighttime works may be required to facilitate welding of the piles during low tides.


Latest update

Notice of Determination

Delta, B.C. – October 7 2025 – The Vancouver Fraser Port Authority has determined that the proposed Combi-wall installation - CIPA Lumber located at 797 Carlisle Road, Delta BC is not likely to cause significant adverse environmental effects.

Participate

Contacts

Project and Environmental Review
Vancouver Fraser Port Authority
100 The Pointe, 999 Canada Place
Vancouver, British Columbia V6C 3T4
Email: per@portvancouver.com


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Combi-wall installation - CIPA Lumber (British Columbia)
  • Nature of Activity

    • Ports and Harbours
    • Maintenance activities (fences, walls)
  • Assessment Status

    Completed
  • Start Date

    2025-07-28
  • Proponent

    CIPA Lumber
  • Authorities

    • Vancouver Fraser Port Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    89768