MFC Training Fuel Farm Replacement at the Greater Moncton Roméo LeBlanc International Airport

Canlink Aviation Inc. is proposing a project that will replace an aging 19,000 litre AvGas fuel tank with two 40,000 litre AvGas Fuel tanks at the Greater Moncton Roméo LeBlanc International Airport.  The proposed tank capacity will allow for the acceptance of larger fuel volumes and less frequent delivery transfers. The new tanks will be relocated to a more central location on the airport apron to improve access.


Latest update

September 9, 2025 - The Greater Moncton International Airport Authority would like to inform the public that this project was delayed in 2023 but is set to be completed in March 2026 with no changes to the scope of the project nor the environmental effects determination. 

.

Participate

Key documents

Key documents
Document number Document title File Date
2 Notice of Determination - February 12, 2024
1 Notice of Intent to Make a Determination - Start of Public Comment Period - December 28, 2023

Contacts

Greater Moncton International Airport Authority
Gemma Askeland, Manager, Terminal Operations
777 Aviation Avenue
Unit 12
Dieppe, New Brunswick E1A 7Z5
Telephone: 506-853-5245
Email: gaskeland@cyqm.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • 1719 Chamlain Street, Dieppe, NB (New Brunswick)
  • Nature of Activity

    • Airport and Airfields
  • Assessment Status

    Completed
  • Start Date

    2023-12-28
  • Proponent

    Canlink Aviation Inc.
  • Authorities

    • Greater Moncton International Airport Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    87190