Wharf Reconstruction and New Breakwater at Sainte-Marie-sur-Mer SCH, NB
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Improvements to the harbour will consist of reconstruction of a marginal wharf structure (#401), expansion of the existing containment cell (#771), and construction of a new breakwater structure.
The marginal wharf structure is located on the south side of the harbour basin and is a treated timber cribwork structure with a reinforced concrete deck measuring approximately 150 meters (m) in length and 9 m in width. The reconstruction will involve the entire structure, which will be demolished down to approximately 1.0 m above chart datum with the bottom of the timber cribwork remaining in place. The cribwork will be encapsulated by a new king pile structure (i.e., steel H piles and concrete panels) along the same alignment as the existing wharf but will be offset from the existing wharf face by approximately 1.0 m to facilitate construction. The H piles will be drilled and socketed in place along the existing wharf face and tied back near the top with steel tie rods and concrete anchor blocks. Pre-cast concrete panels will be lowered in place between the piles, the new marginal structure will be infilled, and a new cast-in-place concrete deck system will be installed over the top fill layer.
The marginal wharf reconstruction will also include a new 15 m-long section perpendicular to the shoreward end of existing structure (#401). This section will be of a similar king pile structure tied back to anchor blocks on the existing shoreline. A layer of rip rap will be placed all along the outside of the new walls for scour protection. The reconstructed marginal wharf and the new 15 m section will both be constructed to an elevation of 3.05 m above chart datum.
The project will also involve the construction of a new rubblemound breakwater on the south side of the entrance channel, extending from the earthen containment cell (#771) that contains sediments dredged from the harbour basin. The new breakwater will extend approximately 96 m beyond the marginal wharf (#401) to provide improved protection for the fishing fleet. The breakwater will consist of a core stone berm with outer layers of filter and armour stone. The design elevation of the breakwater is 5.5 m above chart datum for the crest on the seaward side slope. The inner crest of the breakwater will be designed to incorporate a travel road and a 20 m-long wharf structure at its end. The wharf will also be a king pile and concrete panel tied-back structure and designed as an operating platform for land-based dredging equipment. As part of the construction, the breakwater will be blended into the existing shore protection and allow for a 30 m-long expansion of containment cell to increase its capacity.
The work will be conducted using heavy equipment such as excavators, cranes, front-end loaders, and trucks working from existing structures and/or temporary work platforms. If temporary stockpiling of material is required, the stockpile area will be located at the Small Craft Harbour and coordinated with the Harbour Authority to avoid disruption of fishing activities. The project will include the addition of a navigational aid at the end of the new breakwater structure.
Construction activities are anticipated to commence in fall 2025 and be completed in 2027. Project commencement is, however, subject to DFO-SCH operational priorities and funding, as well as the completion of regulatory approval processes, therefore work may be delayed. The scope of the impact assessment (subject to the Impact Assessment Act) will, therefore, be based on the works being completed over a period of 18 months commencing within a period of 5 years following finalization of the assessment.
The Sainte-Marie-sur-Mer Small Craft Harbour is a core fishing harbour that was developed to serve the fishing industry in the area. The goal of the harbour improvements project is to upgrade dilapidated infrastructure, increase capacity within the containment cell to accommodate future dredge events, as well as improve protection and safety of fishers such that the harbour may continue to serve and protect the fishing community. As the existing and proposed structures are essential to the sustainability of the harbour, the only alternative to the project would be for it not to be completed and eventually abandon the harbour completely. Since this is not a viable alternative, DFO-SCH considered design alternatives. DFO-SCH selected the proposed design of reconstructing the marginal wharf and construction of the new rubblemound breakwater based on constructability, harbour protection, projected sedimentation, and capital costs.
Latest update
October 10, 2025 - The Federal Authorities have issued their Notice of Determination after evaluation of the project, Wharf Reconstruction and New Breakwater at Sainte-Marie-sur-Mer DFO-SCH and have determined that the project is not likely to cause significant adverse environmental effects and can therefore proceed.
This determination was based on a consideration of the following factors:
- Impacts on rights of Indigenous peoples;
- Community and Indigenous knowledge;
- Comments received from the public; and
- Technically and economically feasible mitigation measures.
Mitigation measures taken into account for this determination include:
- The project will comply with all applicable municipal, provincial, and federal acts and regulations.
- Vessels should be compliant with all Canada Shipping Act, 2001 requirements for inspection, which includes certification of the vessel and adequate training and appropriate certificate of competency for the operators.
- Ensure that vessels will have procedures in place to ensure safeguards against marine pollution: awareness training of all employees, means of retention of waste oil on board and discharge to shore based reception facilities, capacity of responding to and clean-up of accidental spill caused by vessels involved in the project.
- Contractor to coordinate with the local Harbour Authority prior to commencement of the work such that the schedule with the least possible conflicts will be implemented.
- Limit impacts on fish habitat components to those approved for the works, undertakings and activities.
- Ensure that machinery arrives on site in a clean condition and is maintained free of fluid leaks, invasive species and noxious weeds.
- Operate machinery in the dry in a manner that minimizes disturbance to the shoreline and beach area (i.e., minimize tracking of equipment by using the same pathway as much as possible).
- Machinery will be stationed on land most of the time and if travelling on the beach it will do so at low tide.
- Monitor and assess weather forecast on a daily basis to determine the risk of extreme weather. Avoid work during periods for which Environment and Climate Change Canada had issued rainfall, storm surge or other weather warning for the work area.
- All conditions set out by DFO-FFHPP in the Fisheries Act Authorization will be adhered to. Any harmful alteration, disruption, or destruction of fish habitat will be offset as per the details of the Fisheries Act authorization.
- A Sediment Control Plan will be developed and implemented to minimize sedimentation in the waterbody.
- Regularly inspect and maintain the erosion and sediment control measures and structures during all phases of the project.
- Ensure that all in-water activities, or associated in-water structures, do not interfere with fish passage.
- All rock/stone material (including re-used ballast from the deconstructed wharf) used in the construction of the breakwater should be clean and free from significant fines, organics, debris, staining and potential contaminants.
- Do not dispose of hazardous wastes (e.g., paints, batteries, cleaners, acids, etc.) including volatile materials (e.g., solvents, mineral spirits, aerosol cans, etc.) and petroleum products on the ground, near or into watercourses, storm or sanitary sewers or in waste landfill sites. Dispose of hazardous wastes in accordance with applicable federal and provincial, regulations, codes, standards and guidelines.
- Wash, refuel and service machinery and store fuel and other materials for the machinery in such a way as to prevent any deleterious substances from entering the water.
- Secure contents against free board spillage when excavating, loading and hauling material, including dredged material. Do not overload trucks when hauling material and avoid potential release of contents, and of any foreign matter onto highways, roads and access routes used for the work. Immediately clean any ground spills and soils to extent as directed by authority having jurisdiction.
- Dispose and recycle construction and demolition-related debris and waste materials in accordance with provincial waste management regulations.
- Mitigation measures will be implemented to ensure no contamination from creosote-contaminated material when temporarily stored on site and source-separated. In particular, creosote-contaminated material will be stored down-gradient from local water wells. Its storage will be temporary (less than a month) and material will be contained with a sufficiently durable tarp liner and covered by tarp to prevent leaching. Creosote-contaminated material will be disposed off at a facility licensed to accept this type of material.
- Store and handle hazardous materials in accordance with applicable federal and provincial regulations, codes, standards and guidelines. Store in location that will prevent spillage into the environment.
- An Emergency Response Plan will be developed and implemented immediately in the event of a sediment or spill release of a deleterious substance.
- Maintain on site appropriate emergency spill response equipment consisting of at least one 250-litre overpack spill kit for containment and clean-up of spills. In the event of a petroleum spill and release into the environment, stop work and immediately notify the Departmental Representative and the Canadian Coast Guard 24-Hour Environment Emergencies Report System (1-800-565-1633). Contain spill and perform clean-up in accordance with all regulations and procedures stipulated by authority having jurisdiction.
- If an oiled seabird is encountered, it will be handled according to Environment and Climate Change Canada (ECCC) – Canada Wildlife Service (CWS)’s guidelines.
- Minimize disturbance to all birds on site and adjacent areas during the entire course of the work.
- Large (>2 m high) stockpiles of sand and soil may be used by Bank Swallows to dig burrows for nesting. To prevent this either cover the stockpiles or maintain slopes of the pile such that they are less than 70°.
- A 50 m buffer will be maintained from bank swallow critical habitat, and 100 m buffer from active colonies, where possible. If the 100-m buffer cannot be maintained and construction is conducted between April 15 and August 31, a survey will be completed by a qualified biologist within 48 hours of the commencement of project activities to identify the presence of bank swallows and/or their critical habitat. For situations where project activities have begun and have not been completed prior to the breeding season (April 15 and August 31), then the initial survey will be completed the first week of the breeding bird season. Additional mitigation measures may be developed based on the results of the survey.
- A qualified biologist must conduct a Piping Plover survey at the beginning of the breeding season to confirm no Piping Plovers are nesting within 300 m from the project. If Piping Plovers are nesting within 300 m, conduct monitoring to confirm no disturbance by activities.
- Should nests or chicks of migratory birds or raptors be encountered during work, immediately stop work in that area and notify Departmental Representative for directives to be followed.
- Do not disturb nest site and neighbouring vegetation until nesting is completed.
- Minimize work immediately adjacent to such areas until nesting is completed.
- Protect these areas by following recommendations of Canadian Wildlife Service (CWS).
- Do not approach concentrations of seabirds, waterfowl and shorebirds when anchoring equipment, accessing wharves or ferrying supplies.
- Do not use beaches, dunes, coastal wetlands and other natural previously undisturbed areas of the site to conduct work unless specifically approved by the Departmental Representative.
- During nighttime work, position flood lights in opposite direction of nearby bird nesting habitat.
- A safety zone for cetaceans and/or species listed under Schedule 1 of the Species at Risk Act (e.g. North Atlantic Right Whale, White Sharks or Leatherback Turtles) must be established at the work site. The safety zone shall consist of a circle with a radius of at least 500 meters as measured from the center of the work site.
- Work equipment and machinery must be equipped with adequate muffling capacity to reduce noise on site to lowest possible level. Maintain mufflers in good operating condition at all times. Sounds such as whistle blasts and horns will be limited or replaced, to the extent possible, with radio communications.
- Dust suppression by the application of water must be employed, when required. Apply dust control measures to roads, parking lots and work areas. The Departmental Representative shall determine locations where water is to be applied, the amount of water to be applied, and the times at which it shall be applied. Waste oil or any other petroleum products must not to be used for dust control under any circumstances.
- Any intact sediments excavated during the project to be examined by a permitted monitoring archaeologist to identify potential heritage resources. Monitoring is only recommended for undisturbed postglacial Holocene sediments which coincide with the period of human occupation of the area – not for glacial till, bedrock, or previously disturbed sediments.
- All construction personnel will be responsible for reporting any unusual materials unearthing during construction activities to Construction Supervisor. If the find is believed to be an archaeological resource, the Construction Supervisor will immediately stop work in the vicinity of the find and notify his/her immediate supervisor and the Project Manager.
- Work in the area will be stopped immediately and the New Brunswick Department of Tourism, Culture and Heritage – Provincial Archaeological Services will be contacted at 506-453-3115.
- Work can only resume in the vicinity of the find when authorized by the Departmental Representative, after approval has been granted by the New Brunswick Department of Tourism, Culture and Heritage.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 3 | Notice of Determination | - | October 10, 2025 |
| 2 | End of Public Comment Period | - | June 14, 2025 |
| 1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | May 14, 2025 |
Contacts
Fisheries and Oceans Canada - Small Craft Harbours, Maritimes and Gulf RegionsChyann Kirby, Environmental Advisor
Gulf Fisheries Centre
343 University Avenue
Moncton, New Brunswick E1C 9B6
Telephone: 506-866-5164
Email: chyann.kirby@dfo-mpo.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Saint-Marie-sur-Mer SCH (Harbour Code 2640) is located in the community of Sainte-Marie-sur-Mer on the eastern side of Lamèque Island in Gloucester County, New Brunswick. (New Brunswick)
-
Nature of Activity
- Ports and Harbours
-
Assessment Status
Completed -
Start Date
2025-05-14 -
Proponent
Fisheries and Oceans Canada - Small Craft Harbours (DFO-SCH) -
Authorities
- Fisheries and Oceans Canada
- Transport Canada
-
Assessment Type
Project on federal lands -
Reference Number
89536
Nearby assessments
...within 200 kilometres-
Floating Wavebreaks Installation, Lameque NB
Lameque Small Craft Harbour -
Lameque Breakwater and Floating Wavebreak Installation
Lameque Small Craft Harbour, Gloucester County, New Brunswick. -
Addition of Armourstone Protection at Disposal Site DS2, Shippagan, Gloucester County, New Brunswick
Shippagan, Gloucester County, New Brunswick -
Removal of access road and sea wall, and restoration of dune and tidal wetland habitats at Shippagan Gully, Gloucester County, New Brunswick
Shippagan Gully, Gloucester County -
Shippagan DFO-SCH New Fuel Storage and Dispensory System Installation
The project is taking place at Shippagan Small Craft Harbour in the town of Shippagan, Gloucester County, New Brunswick. -
Shippagan Containment Cell and Basin Dredging
Shippagan Small Craft Harbour in the town of Shippagan, Gloucester County, New Brunswick. -
Addition of Armourstone Protection at the Petit-Shippagan Small Craft Harbour, Gloucester County, New Brunswick
Petit-Shippagan, Gloucester County, New Brunswick -
Rue du Havre Street Rehabilitation
Rue du Havre, Le Goulet -
Replacement of diesel fuel system at Pigeon Hill Harbour, NB
Pigeon Hill -
Miscou Fish Products Inc. Construction of Seafood Plant Addition
Miscou Small Craft Harbour -
Caraquet Wharf Removal and Breakwater and Rock Protection Installation
Caraquet Small Craft Harbour in the town of Caraquet, Gloucester County, New Brunswick. -
Installation of a Concrete Tank and Septic Pump-Out System at the Port of Caraquet, NB
Caraquet DFO-SCH -
Bush Cutting the Sides of 4.7 km of Cross Country Ski Trails
Kouchibouguac National Park of Canada -
Re-Surface Parking Lot at Detachment
Tracadie-Sheila -
Containment Cell Construction and Dredging, Val Comeau, NB
Val Comeau Small Craft Harbour -
Maintenance Dredging - Saint-Godefroi Fishing Harbour
Saint-Godefroi -
Maintenance Dredging - St-Godefroi Fishing Harbour
St-Godefroi Fishing Harbour -
Rehabilitation of boat unloading station #402 and launching ramp at Saint-Godefroi Harbour, Gaspésie
Havre de pêche de Saint-Godefroi -
Maintenance Dredging at Port-Daniel Est Fishing Harbour
Port-Daniel-Est -
Maintenance Dredging at Port-Daniel Est Fishing Harbour
Port Daniel Est Fishing Harbour -
Revitalization of the Newport Fishing Harbour - Gaspésie, Québec
Newport Fishing Harbour -
Wharf 403 Reconstruction - Newport Harbour - Gaspésie
Newport Harbour -
Reconstruction of the boat launching ramp - Paspebiac Fishing Harbour, Gaspe
Paspebiac Fishing Harbour -
Stonehaven Wharf Re-construction
Stonehaven Harbour is located on the Stonehaven Wharf Road, off of Route 11 in Stonehaven, Gloucester County, New Brunswick, on the southeast shore of Nepisiguit Bay. -
Reconstruction of breakwater structure 301 at the Miller Brook Fisheries and Oceans Canada Small Craft Harbour
Miller Brook DFO-SCH, Gloucester County -
Reconstruction of wharf structure 406 at the Miller Brook Fisheries and Oceans Canada Small Craft Harbour.
Miller Brook DFO-SCH, Gloucester County -
Securing the Cap-d'Espoir Lighthouse Site
Cap-d'Espoir Lighthouse -
Maintenance Dredging at Bonaventure Fishing Harbour
Bonaventure Harbour -
Esgenoopetitj First Nation Lift Station Upgrades
Esgenoopetitj First Nation -
Esgenoôpetitj Community and Cultural Centre
Esgenoôpetitj First Nation -
Harbour Repairs and Dredging, Burnt Church, NB
Harbour Repairs and Dredging -
Maintenance Dredging - L'Anse-à-Brillant Fishing Harbour
L'Anse-à-Brillant -
Chanel Dredging at Escuminac Small Craft Harbour
Escuminac -
Construction of a Containment Cell at the Escuminac Small Craft Harbour, New Brunswick
Escuminac Small Craft Harbour -
Escuminac Wharf Upgrades
Escuminac SCH is located off of Escuminac Point rd., in Northumberland County, New Brunswick. -
Fox Island South Range Replacement
Fox Island, North of Hardwick, NB -
Rehabilitation of Ruisseau-Leblanc Harbour, Gaspé Peninsula
Ruisseau-Leblanc Wharf -
Floating Wharf Installation at the Petit-Rocher Small Craft Harbour, Gloucester County, New Brunswick
Petit-Rocher, Gloucester County, New Brunswick -
Vanier Commercial Development Project
Bathurst -
Pabineau Water Exploration Study & Well Development
Pabineau First Nation -
Oak Point Range Easement Remediation
Oak Point, NB -
Wharf Repairs and Shoreline Protection, Pointe Sapin Harbour, N.B.
Pointe Sapin small craft harbour is located in Kent County, along the Northumberland Strait, on the eastern coast of New Brunswick directly adjacent to Highway 117. -
Turning Block Replacement, Pointe-Sapin, NB
Pointe-Sapin Small Craft Harbour -
Sand Trap Dredging, Pointe -Sapin Small Craft Harbour, New Brunswick
Pointe-Sapin Small Craft Harbour -
Slipway and Breakwater Reconstruction at Seacow Pond Small Craft Harbour, Prince Edward Island
Seacow Pond SCH (DFRP #02255) is located on the eastern coast of the northwest point of Prince Edward Island (PEI) on Highway 12, Tignish, Prince County, PEI. -
Skinner's Pond Copewall Installation
Skinners Pond SCH is located at 513 Stompin Tom Road in Skinners Pond, Prince County, on the western shores of PEI. -
Skinners Pond Small Craft Harbour Containment Cell Expansion
Skinners Pond Harbour is located at 513 Stompin Tom Road in Skinners Pond, Prince County -
Wood Pellet Warehouse
Port of Belledune -
Skinners Pond Small Craft Harbour Wharf Reconstruction
513 Stompin Tom Road, Skinners Pond, Prince County -
Routine Maintenance Dredging
Port of Belledune -
Terminal 3 Storm Sewer Upgrade
Port of Belledune -
Construction of a storage facility on Terminal 3 at the Port of Belledune
Belledune -
Elmtree Property Gold Mine
Dauversière -
Extension of the Breakwater at St-Georges-de-Malbay Harbour
St-Georges-de-Malbay Harbour -
Upgrades to Port of Belledune Tank Farm
Belledune -
Breakwater Construction at Tignish SCH, PEI
Tignish SCH is located in the town of Tignish, Prince County. The harbour is formed by the mouth of the Tignish River where it enters the Gulf of St. Lawrence. It is accessible by land via Tignish Run/Harbour Road and Founders Lane. -
Food counter service at the new visitor center located in the North sector
Forillon National Park -
Miminegash DFO-SCH South Breakwater Reconstruction
Miminegash SCH, Queens county -
Maintenance Dredging - L'Anse-à-Brillant Fishing Harbour
L'Anse-à-Brillant Fishing Harbour -
Well Installation at Loggiecroft Wharf
Kouchibouguac National Park of Canada -
Sewage Disposal System Replacement, Loggiecroft Wharf
Kouchibouguac National Park of Canada -
Paving of Loggiecroft Wharf, Loggiecroft Harbour Authority
Kouchibouguac National Park -
New Ice Shed and Storage Garage at Loggiecroft Wharf
Kouchibouguac National Park of Canada -
Loggiecroft DFO-SCH Shore Protection and Floating Dock Realignment
The project is taking place at Loggiecroft Small Craft Harbour (Kouchibouguac Park), Kent County, New Brunswick. -
Expansion of Saint Vincent de Paul Cemetery
Kouchibouguac National Park of Canada -
South Kouchibouguac Campground Entrance Kiosk Redesign and Road Realignment
Kouchibouguac National Park -
Rankin Trail Re-Opening and Expansion
Kouchibouguac National Park of Canada -
Gasgusi Street Extension
Gesgapegiag -
Construction of Lentug Street and reconstruction of Eagle Street
Gesgapegiag Community -
Phoco Tours Business Licence Application
Kouchibouguac National Park -
Changes to the Grande-Grave floating dock
Forillon National Park of Canada -
Access to heritage homes in the Grande Grave area PRO-1686
Forillon National Park of Canada -
Renovation of the Elias-Gavey house and related improvements
Forillon National Park of Canada -
Refurbishment of the Joseph-Gavey house - LOT 2 PRO-1686
Forillon National Park of Canada -
Alberton (Northport) Wharf Reconstruction (Structure 412)
Alberton (Northport) SCH -
Howards Cove Wharf Upgrades
50 Wharf Road, off Route 14 in Cape Wolfe, Prince County -
Acquisition and installation of propane heating in the oTENTiks of loop F at Petit-Gaspé campground
Forillon National Park of Canada -
Cap Saint Louis Wharf Repairs, 2026
Kouchibouguac National Park of Canada -
Protection of vegetation against spruce budworm at Petit Gaspé and oTENTik campgrounds
Forillon National Park -
Howards Cove SCH Breakwater Reconstruction
Howards Cove SCH is located at the end of Wharf rd in Howards Cove, Kings county, Prince Edward Island. -
Powerline Biofuel Removal - Reducing Wildfire Risks for Kouchibouguac National Park and Neighbouring Communities
Kouchibouguac National Park of Canada -
Establishment of a Micmac experiential site within Forillon Park in the Cap-Bon-Ami sector.
Forillon National Park of Canada -
Development of a picnic site on the Laurencelle
Forillon National Park of Canada -
Penouille Energy Trail
Forillon National Park of Canada -
Petroleum product storage cabinet at Cap-des-Rosiers harbour in Forillon National Park
Forillon National Park of Canada -
Notice of intention - Maintenance Dredging - Cap-des-Rosiers Fishing Harbour
Cap-des-Rosiers Fishing Harbour -
Natoaganeg - Subdivision Phase 2
Natoaganeg First Nation -
Construction of a service building in the parking lot of the Cap-des-Rosiers beach
Forillon National Park -
Construction of a service building in the parking lot of the Cap-des-Rosiers Beach
Forillon National Park -
L'no Minigog Shoreline Revetment
Indian Island First Nation -
Road Upgrade Project - Mi'kmaq Lane - Indian Island First Nation
Indian Island First Nation -
Basin Dredging, New Mills Small Craft Harbour, New Brunswick
New Mills -
Rock Protection Installation at Cap- Lumière Small Craft Harbour, Kent County, New Brunswick
Cap-Lumière, Kent County, New Brunswick -
Cap-Lumière DFO-SCH Containment Cell Construction
The Cap-Lumière DFO-SCH is located on the Northumberland Strait in the parish of Richibucto, Kent County, New Brunswick. -
Discovery and fishing cruise along the north coast of Forillon
Forillon National Park -
West Point Dredge Zone Expansion and New Ocean Disposal Site
West Point Harbour is accessible off the Harbour Road, a secondary road off Route 14 in the community of West Point, Prince County -
Metepenagiag Mountain Side Road Extension and New Residential Development
Metepenagiag First Nation -
Elsipogtog New Subdivision
Elsipogtog First Nation -
Elsipogtog First Nation Water Treatment Plant Manganese Upgrade
Elsipogtog First Nation -
Installation of a 15,000L diesel fuel tank at the Rivière-au-Renard Search and Rescue station.
Rivière-au-Renard Search and Rescue station -
Main Breakwater Repair at Rivière-au-Renard Harbour
Riviere-au-Renard Harbour -
Elsipogtog First Nation Wastewater Treatment Upgrades
Elsipogtog First Nation -
Elsipogtog First Nation - Water Tower Demolition
Elsipogtog First Nation -
Elsipogtog First Nation - Housing Recovery Phase 2
Elsipogtog First Nation -
Sediment rehabilitation and demolition of Miguasha wharf, Quebec
Miguasha wharf -
Migaju' House
Eel River Bar First Nation -
Eel River Bar - Child and Family Service Building
Eel River Bar First Nation -
Containment cell reconstruction and harbour dredging at Saint-Edouard-de-Kent Fisheries and Oceans Canada Small Craft Harbour, Kent County, New Brunswick
Saint-Edouard-de-Kent DFO-SCH, Kent County, New Brunswick -
Rock Installation at Saint-Edouard-de-Kent Harbour
Saint-Edouard-de-Kent -
Subdivision Infrastructure Development – Eel River Bar First Nation
Eel River Bar First Nation -
Tiny Home Subdivision
Eel River Bar First Nation -
Eel River Bar Osprey Truckstop Expansion
Eel River Bar First Nation -
Fisheries Maintenance and Repair Facility at Lennox Island
Lennox Island -
Dalhousie Pozzolan Project
Heron Bay -
Higgins Shore Wharf Replacement
Higgins Shore Small Craft Harbour is located at 241 Higgins Shore Road in Victoria West, Prince County, PEI on the shores of the Northumberland Strait. -
Lennox Island Wharf Construction
Lennox Island First Nation, Malpeque Bay -
Blackville Detachment Parking Lot Resurfacing and Expansion
Blackville Detachment -
Multi-Unit Construction Project - Buctouche First Nation
Buctouche First Nation -
Malpeque Small Craft Harbour Dredge and Disposal Zone Amendments
Project is located in the entrance channel to the Malpeque Cove Small Craft Harbour, which is located on the Malpeque Wharf Road. -
Replacement of diesel fuel system at Malpeque Cove Harbour, PE
Malpeque -
Reconstruction of wharf structure 404 and addition of armour stones at the Barre-de-Cocagne Fisheries and Oceans Canada Small Craft Harbour, Kent County, New Brunswick
Barre-de-Cocagne DFO-SCH, Kent County -
Construction of a Marginal Wharf at the Barre-de-Cocagne (Cormierville) Small Craft Harbour, New Brunswick
Barre-de-Cocagne (Cormierville) DFO-SCH -
Abrams Village SCH Wharf Reconstruction
Abrams Village DFO-SCH, Prince County, Prince Edward Island -
Abram's Village Wharf Removal and Armour Stone Replacement
8311 Route 11 in Abram's Village, Queens County -
Darnley Bridge Small Craft Harbour Basin Dredging
Darnley Small Craft Harbour -
New Floating Dock at French River Small Craft Harbour, Queens County, Prince Edward Island
French River Small Craft Harbour, located Park Corner, Queens County, Prince Edward Island. -
Lot development project in Listuguj
Listuguj -
Drinking Water Treatment Plant Upgrades
Listuguj -
Riverside Extension
Listuguj -
French River South Landing SCH Wharf Reconstruction
French River South Landing SCH is located at the junction of Paynter and Cannery road, in French River, Queens County, Prince Edward Island. -
Reconstruction of a Wharf and Shore Protection at the Cap-des-Caissie Small Craft Harbour, New Brunswick
Cap-des-Caissie DFO-SCH -
Mi'gmaw Language & Cultural Community Centre
Listuguj -
Cavendish Campground Post-Fiona Recovery and Reinstatement
Prince Edward Island National Park of Canada -
Paving & Walkway & Curb Work
29, chemin Schurman's Point, Summerside -
Cavendish Campground Staff Room Construction
Prince Edward Island National Park -
Acadian Forest Restoration
Prince Edward Island National Park -
Cavendish Grove Stream & Watershed Restoration
Detailed Impact Assessment, Prince Edward Island National Park -
Green Gables Golf Course - Replacement of Underpass Retaining Walls
Prince Edward Island National Park -
Lift Station Modification on Route 6 by the Resort Municipality of Stanley Bridge, Hope River, Bayview, Cavendish and North Rustico
Prince Edward Island National Park -
Launching Ramp Reconstruction at the Cap-Pelé DFO-SCH, New Brunswick
Cap-Pelé DFO-SCH -
Cap-Pelé DFO-SCH Containment Cell Construction
The Cap-Pelé DFO-SCH is located on the Northumberland Strait in the town of Cap-Acadie, Westmorland County, New Brunswick. -
Launching Ramp Reconstruction at the Cap-Pelé DFO-SCH, New Brunswick
Cap-Pelé DFO-SCH -
Boardwalk Construction, Les Aboiteaux Harbour, New Brunswick
Cap-Pelé -
Rock protection for erosion control at Les Aboiteaux Fisheries and Oceans Canada Small Craft Harbour, Kent, New Brunswick
Les Aboiteaux Small Craft Harbour, Kent County -
Berlin Wall Installation at the Les Aboiteaux SCH, New Brunswick
Dupuis Corner -
Shoreline Protection at the Robichaud Fisheries and Oceans Canada Small Craft Harbour, Westmorland County, New Brunswick
Robichaud Small Craft Harbour, Westmorland County -
North Rustico Wharf Replacement, Floating Dock Replacement and Shoreline Protection Repairs
52 Harbourview Drive in North Rustico, Queens County, PEI -
Installation of a septic tile field at North Rustico beach, Prince Edward Island National Park
Prince Edward Island National Park -
Entrance Breakwater and Shore Protection Reconstruction at the North Rustico Small Craft Harbour, Prince Edward Island
North Rustico -
North Rustico DFO-SCH Wharf Reconstruction
North Rustico SCH -
Petit-Cap Wharf Reconstruction - Phase 2
Petit-Cap Harbour is located at 55 Chemin du Quai Road, off of Route 950 in the community of Petit-Cap, Westmorland County, New Brunswick. -
Petit-Cap Wharf Re-construction
Petit-Cap Harbour is located at 55 Chemin du Quai Road, off of Route 950 in the community of Petit-Cap, Westmorland County, New Brunswick. -
Green Gables Golf Course Netting Installation
Prince Edward Island National Park -
Moncton 1 Site Development
Moncton -
Covehead DFO-SCH Wharf Upgrades
Covehead Small Craft Harbour (SCH) is located in Covehead, Queens County, Prince Edward Island, adjacent to the PEI National Park (Brackley-Dalvay region). -
Wharf Upgrades and Launching Ramp Reconstruction at the Covehead Small Craft Harbour, Prince Edward Island
Covehead -
Wharf Upgrades and Launching Ramp Reconstruction at the Covehead Small Craft Harbour, Prince Edward Island
Covehead -
Eliminating Bottlenecks and Enabling Growth at Greater Moncton Roméo LeBlanc International Airport
Greater Moncton Roméo Leblanc International Airport -
Managed Retreat of Stanhope Cape Parking Lot and Beach Access, Prince Edward Island National Park
Prince Edward Island National Park of Canada -
Runway End Safety Areas at the Greater Moncton Roméo LeBlanc International Airport
Greater Moncton Roméo LeBlanc International Airport -
Botsford Harbour Boat Ramp Replacement
Botsford -
Botsford DFO-SCH Shoreline Protection Upgrade
The Botsford (Murray Corner) DFO-Small Craft Harbour is located in Murray Corner, Westmorland County, New Brunswick. -
MFC Training Fuel Farm Replacement at the Greater Moncton Roméo LeBlanc International Airport
1719 Chamlain Street, Dieppe, NB -
Federal Express Canada Parking Lot Expansion
Greater Moncton Roméo LeBlanc International Airport -
MACC Warehouse facility at the Greater Moncton Roméo LeBlanc International Airport
Greater Moncton Roméo LeBlanc International Airport -
Ross Lane - Stanhope campground road extension, Prince Edward Island National Park
Prince Edward Island National Park of Canada -
Exterior Upgrades - Moncton District Office
Moncton, New Brunswick -
Stanhope Campground - Creation of pedestrian pathway
Prince Edward Island National Park -
Atlantic Science Enterprise Centre (ASEC), Moncton, New Brunswick.
The existing Gulf Fisheries Center and lands are located at 343 Université Avenue in the City of Moncton, New Brunswick -
Fuel Storage Tank Piping Modifications - Moncton Government of Canada Building
Dominion Public Building 1081 Main Street Moncton New Brunswick E1C 1H1 -
Gulf Shore Parkway East Road Renovations and Bank Stabilization
Prince Edward Island National Park -
Expansion of Cottage Accommodation Service Offer, Dalvay-by-the-Sea National Historic Site, PEINP
Dalvay-by-the-Sea National Historic Site of Canada -
Watts Road Boundary Corridor Access - Prince Edward Island National Park
Prince Edward Island National Park -
New Dredge and Disposal Sites at Tracadie Small Craft Harbor
Project is located in the entrance channel to Tracadie Bay. The Tracadie Small Craft Harbour is located at 467 Harbour Road in Grand Tracadie. -
Cape Tormentine DFO-SCH Wharf Structure 402 Reconstruction
The Cape Tormentine DFO-SCH is located on the Northumberland Strait in Cape Tormentine, Westmorland County, New Brunswick. -
Wharf reconstruction at Cape Tormentine
Cape Tormentine -
Upgrade Salisbury Small Arms Range
Salisbury Rifle Range -
Cavendish Campground New Loop Construction
Prince Edward Island National Park -
Centre Village Renewables Integration and Grid Security Project
Centre Village -
New Southeast District Detachment
Salsbury -
Construction of an industrial building on Metepenagiag Urban Reserve No. 3, City of Moncton
Metepenagiag Urban Reserve No. 3, City of Moncton -
Kreative Rentals Corp. Commercial Building
Charlottetown -
2025 BioVectra Aqueous Waste Treatment Building
Charlottetown -
2022 BioVectra Biopharmaceutical Expansion
Charlottetown -
Air Canada New Type I and Type IV Glycol Storage System
Charlottetown Airport -
Charlottetown Airport Terminal Expansion - Phase 1
Charlottetown -
Charlottetown Airport Terminal Expansion - Phase 2/3
Charlottetown -
Parking Lot Repaving at Letter Carrier Depot (LCD) Charlottetown, PE
200 Maple Hills Avenue, Charlottetown -
Kreative Acres Corp. Building Expansion
Charlottetown -
Savage Harbour Wharf Reconstruction
3388 Savage Harbour Road (Route 218), Savage Harbour, Kings County -
Trans-Canada Highway Realignment Through New Haven-Bonshaw, Queen's County, PEI
Bonshaw