Elsipogtog First Nation - Water Tower Demolition

The Proposed Project

The project includes the demolition and removal of a decommissioned 46 m high water tower with a footprint of approximately 145 m2 located in Elsipogtog First Nation. The steel structure will be cut and disassembled safely, with a carefully planned sequence and with minimal impact on the surrounding site. The material from the tower will be recycled. Activities include excavation, trenching, decommissioning, and backfilling of abandoned water lines and systems serving the tower in parallel with the tower demolition. Grading, paving, and reinstatement to a paved yard will complete the project. 


Latest update

February 29, 2024 - Indigenous Services Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
3 Notice of Determination - February 29, 2024
2 Notice of Intent - Elsipogtog First Nation - Water Tower Demolition (Updated) - January 30, 2024
1 Notice of Intent - Elsipogtog First Nation - Water Tower Demolition - January 26, 2024

Contacts

Indigenous Services Canada - Atlantic
Indigenous Services Canada
PO BOX 160
40 Havelock Street
Amherst, Nova Scotia B4H 3Z3
Telephone: 1-800-567-9604
Fax: 902-661-6237
Email: aadnc.paeat-erpat.aandc@canada.ca


  • Location

    • Elsipogtog First Nation (New Brunswick)
  • Nature of Activity

    • Water Management
  • Assessment Status

    Completed
  • Start Date

    2024-01-26
  • Proponent

    Elsipogtog First Nation
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    87255