Upper Nicola Band - Nicola River Road and Michel Road Drainage Upgrades
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The Proposed Project is paving and minor widening of Nicola River Road and Michel Road, introduction of underground storm water collection piping, approximately 2.1 km of road distance to be improved.
Latest update
February 24, 2026 – The public comment period on the project is closed. The authority is considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects.].
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 1 | Notice of Intent to Make a Determination – Start of Public Comment Period | - | January 25, 2026 |
Contacts
BC Environment TeamIndigenous Services Canada
600-1138 Melville Street
Vancouver, British Columbia V6E 4S3
Email: bcciarpubliccomments@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Upper Nicola (British Columbia)
-
Nature of Activity
- Highways and Roads
-
Assessment Status
In progress -
Start Date
2026-01-25 -
Proponent
Upper Nicola Band -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
90183
Nearby assessments
...within 200 kilometres-
Upper Nicola Band - Quilchena Community Centre
Upper Nicola Band - Quilchena Community Centre -
Upper Nicola Band/Okanagan Nation Alliance Solar Farm Project
NICOLA LAKE 1 -
Douglas Lake Ranch Transmission 3 - Phase Line Relocation
Douglas Lake IR 3 -
Lower Nicola Indian Band Community Solar Gardens
Lower Nicola Reserve Lands - Nicola Mameet No. 1, Joeyaska No. 2, and Zoht No. 4 -
New Fibre Installation
Nooaitch -
New Fibre Installation
Coldwater -
Kingsvale-Oliver Natural Gas Pipeline Reinforcement Project
Kingsvale -
Ajax Mine Project
Kamloops -
Shackan - Sand and Gravel operation on Shackan IR11
Shackan 11 -
Construction of a new building in Kamloops, British Columbia
324 Mt. Paul Way, Kamloops, British Columbia -
Tk'emlúps te Secwepemc CLC Stormwater Detention Facility
Kamloops 1 -
Tk'emlups Commercial Complex Lot 164
Tk'emlúps te Secwépemc 07173 - KAMLOOPS 1 -
New Fibre Installation
TteS West Tkemlups -
TteS Road Realignment and Roundabout Project
Kamloops Indian Reserve No. 1 -
Tk?emlúps te Secwépemc - Mount Paul Multi-family Residential Development
Kamloops IR1, BC -
Construction of a building on Kamloops Indian Reserve No. 1, City of Kamloops
Kamloops Indian Reserve No.1, city of Kamloops -
T'kemlúps te Secwépemc - Kamloops IR1, Lot 8-1 and 9, Commercial Lease
Kamloops -
North Thompson Rail Terminal Development Project
Kamloops -
Tk'emlúps te Secwépemc Stswékstem Engineered Waste Management Facility
Tk'emlúps te Secwépemc, Kamloops #1 -
Nzen'man' Bird's Nest Project
Nzen'man' Bird's Nest Project -
Sackum Creek Overhead Bridge Replacement
Sackum IR No. 3 and Gulada IR No. 3A -
Cook's Ferry Indian Band, BC
Cook's Ferry Indian Band, BC -
Skeetchestn Pipeline Segment Replacement and Valve Site Installation
Site Location -
OKIB IR1 Lot 27 & 28 - Gas Station and Convenience Store
OKIB IR1 Lot 27 & 28 -
New School - Okanagan IR#1 Elementary School
Okanagan Indian Band -
Speyum Creek Watercourse Restoration
Speyum Creek -
Skeetchestn Learning Garden Centre
Skeetchestn Indian Band -
Lytton First Nation - Nuuautin IR2B Subdivision & Stein Water System Improvement Project
Lytton First Nation - Nuuautin IR2B Subdivision & Stein Water System Improvement Project -
Skuppah Indian Band - Food Security Centre
Inklyuhkinatko no 2 reserve -
Skuppah Indian Band - Food Security and Cultural Garden
Inklyuhkinatko Reserve No. 2 -
Okanagan Indian Band Business Park Phase 1
Lots 1, 1-2, 1-3, and 14, Duck Lake IR7 -
OKIB Business Park, Phase 2
OKIB Business Park, Phase 2 -
Lytton First Nation - Battlefield Housing and Food Hub
Lytton First Nation, Lytton, BC -
Timixw Mixed Use Development
Vernon, BC -
New Telus Communications Inc. Telecommunication Tower Project on Skeetchestn Reserve.
Telecommunication Tower Project on Skeetchestn Reserve -
Princeton Detachment Replacement
Princeton -
Combined Operations Building - Kelowna International Airport
Kelowna International Airport -
Runway End Safety Area - Kelowna International Airport
Kelowna International Airport -
Lytton First Nation - Stein Water System Intake Improvements Project
Lytton First Nation - Stein Water System Intake Improvements Project -
Okanagan Indian Band 1 - Fortis BC Natural gas pipeline replacement project
Okanagan Indian Band, Salmon River -
Ashcroft Indian Band - Community Centre
Ashcroft Indian Band - Community Centre -
Vernon Rifle Range Geotechnical Investigation
Vernon Rifle Range -
OKIB Round Lake/Madeline Lake/Heart Lake/Salmon River Water System Improvements
Head of the Lake, Vernon BC -
TELUS Cell Tower Cable Upgrade
1100 Mission Rd, Vernon -
New Fibre Installation
Okanagan -
Automated Weather Station at 250 Allan Brooks Way, Vernon, BC
250 Allan Brooks Way, Vernon -
New Fibre Installation
Project Site 1: NISKONLITH 1 -
Irish Creek/Head of the Lake Water System Upgrades
Okanagan Indian Band IR1 -
Norah's Pond Expansion
Allan Brooks Nature Centre, Vernon, BC -
Okanagan Indian Band Gravel Pit Reactivation
Okanagan IR No. 1 -
Construct Buildings and Washrack at Vernon Military Camp
Vernon Military Camp, 3100 15th Ave, Vernon -
Main Camp Utilities Upgrade at Vernon Military Camp
Vernon Military Camp -
Head of the Lake Subdivision
Vernon -
New Fibre Installation
Project Site 2: OKANAGAN 1 -
Fence and Obstacle Course - Vernon Military Camp
Vernon Military Camp -
Pump Station Demolition- 3rd Canadian Division Support Group (CDSG), Detachment British Columbia Mainland - Chilliwack
3rd Canadian Division Support Group (CDSG), Detachment British Columbia Mainland - Chilliwack -
Pump Station Demolition - 3rd Canadian Division Support Group (CDSG), Detachment British Columbia Mainland - Chilliwack
Detachment British Columbia Mainland - Chilliwack -
TELUS Communications Inc.'s New Antenna Proposal for Existing Tower on Mount Wallensteen.
TELUS Communications Inc.'s New Antenna Proposal for Existing Tower on Mount Wallensteen -
New Fibre Installation
Project Site 4: SALMON RIVER 1 -
New Fibre Installation
Project Site 02: Whispering Pines 4 -
Adams Lake-Sahhltkum IR#4 Water Treatment and Reservoir
07155 - SAHHALTKUM 4 -
Westsyde Road Multi-Use Pathway
Whispering Pines 4 -
Whispering Pines IR#4 Watermain Extension
Whispering Pines IR#4 -
Timber harvesting on Salmon River 1
Salmon River 1 -
Westsyde Road Multi-Use Pathway: Phase 2
Westsyde Road Multi-Use Pathway: Phase 2 -
New Fibre Installation
Project site 2: Salmon River -
Whispering Pines/Clinton Indian Band Living Revetment Site 2B
Whispering Pines/Clinton Indian Band Living Revetment Site 2B -
Shoreline Revetment on Whispering Pines/Clinton Indian Band Reserve Lands
Whispering Pines/Clinton Indian Band Reserve #4 -
Spuzzum First Nation Drinking Water Access Road
Spuzzum Access Road -
New Fibre Installation
Project Site 10: Kamloops 4 -
Summerland Chemical Storage Building Project
Summerland -
Agriculture and Agri-Food Canada Building Demolition at Summerland
Summerland -
Summerland Irrigation Infrastructure Rehabilitation
Summerland -
Field Covering System and Cherry Orchard
Summerland Research and Development Centre -
New Fibre Installation
Project Site 3: MEADOW CREEK 3 -
Penticton IR1 - Bell Media Tower Replacement Project
Penticton IR 1 - Mount Nkwala -
Timber harvesting on CHUM CREEK 2 07179 & SCOTCH CREEK 4 07181
CHUM CREEK 2 07179 -
Harvesting of damaged timber by the 2023 forest fire on Quaaout 1
Quaaout 1 -
Splatsin Shihiya K4-G7 Elementary School
Splatsin Enderby IR #2 -
Forest Fuel Management Quaaout #1
Quaaout #1 -
Penticton Indian Band Sage Road 24 Lot Subdivision
Penticton Indian Band 24 Lot Sage Road Subdivision Development -
Affordable Housing Units
Adams Lake Indian Band -
Outma Sqilx'W School Addition
Penticton Indian Band IR. No. 1 -
New Fibre Installation
Project Site 6: SWITSEMALPH -
Timber harvesting on Hustalen IR #1 Adams Lake
Hustalen #1 -
New Fibre Installation
Project site 1: Enderby 2 -
Terminated - Penticton Airport Parking Lot Rehabilitation and Expansion
Penticton Airport -
Terminated - Penticton Airport - North Apron Expansion
Penticton -
Project Removed by Federal Authority - Penticton Airport - Lot 43 - Canadian Helicopters Ltd - Lease Expansion to Construct New Aircraft Storage Hangar
Penticton -
Project Removed by Federal Authority - Penticton Airport - Lot 28 - Construction of 11 private hangars
Penticton -
BC Ministry of Transportation and Infrastructure Highway 1 Four-Laning
North Bay IR 5 -
New Fibre Installation
Project Site 5: ENDERBY 2 -
Timber harvesting on CHUM CREEK 2 07179 & SCOTCH CREEK 4 07181
SCOTCH CREEK 4 07181 -
New Fibre Installation
Project Site 06: Louis Creek 4 -
Yale First Nation Recreation Centre
Stulkawhits No. 8 Reserve Land -
Shuswap North Okanagan Rail Trail
Splatsin First Nation -
McCartney's Flat IR#4 Water System Improvements
T'IT'Q'ET McCartney's Flat IR#4 -
New Fibre Installation - TELUS
Project Site 01: Lillooet Corridor -
Chawathil - Schkam IR#2 Sewer System Improvements
Chawathil, Schkam IR#2 -
Marine yard development
Marine yard development -
Upper Similkameen Indian Band - Water System Upgrades
Chuchuwayha I.R. No. 2 -
Xaxli'p First Nation Green Hydrogen Production Facility
Xaxli'p Fountain IR1B, Lillooet, BC -
Pole Removal at NRC Dominion Radio Astrophysical Observatory
Dominion Radio Astrophysical Observatory, British Columbia -
Cayoose Creek Water System Connection to Village of Lillooet
Cayoose Creek IR 1 -
DWS Cayoose Creek IR #1 interconnection with DOL
Seton River near Lillooet -
Vaseux Floodplain re-engagement at Vaseux-Bighorn National Wildlife Area
Vaseux-Bighorn National Wildlife Area -
FortisBC Pipeline Integrity Dig at Vaseux-Bighorn National Wildlife Area
Vaseux-Bighorn National Wildlife Area -
Simpcw: Chinook Cove Water System Upgrades and Extension
Simpcw First Nation North Thompson IR1 -
Boardwalk Replacement Project - Vaseux Bighorn National Wildlife Area
Vaseux-Bighorn National Wildlife Area -
New Dock Installation - 317 Sasamat Lane
New Dock Installation - 317 Sasamat Lane -
Maintenance Dredging - Lhoist North America of Canada Inc.
Maintenance Dredging - Lhoist North America of Canada Inc. -
Dunn Lake Road Widening and Realignment Project
Simpcw First Nation -
New Fibre Installation
Project Site 08: North Thompson 1 -
Timber harvesting on North Thompson 1
North Thompson IR #1 -
Underground Conduit Upgrade at NRC Dominion Radio Astrophysical Observatory
Dominion Radio Astrophysical Observatory -
Canadian Hydrogen Observatory and Radio-transient Detector (Dominion Radio Astrophysical Observatory)
Dominion Radio Astrophysical Observatory -
Well and Septic Installation Project at NRC Dominion Radio Astrophysical Observatory
Dominion Radio Astrophysical Observatory -
Fuel tank removal at the NRC Dominion Radio Astrophysical Observatory
Dominion Radio Astrophysical Observatory -
Shxw'owhámél First Nation Outdoor Recreation Infrastructure Project
Shxw'owhámél First Nation -
Simpcw Community Centre - NEQWEYQWELSTEN SCHOOL
Simpcw First Nation, North Thompson 1 -
Peters First Nation Phase 3 Erosion Mitigation
Peters First Nation -
Peters Island Flood and Erosion Mitigation
Peters First Nation - Peters 2 -
Peters First Nation - Fraser River Flood Control Berm
Peters First Nation, British Columbia -
Peters First Nation Gravel Pit Activation
Peters IR 1 -
Kingsvale-Oliver Natural Gas Pipeline Reinforcement Project
Oliver -
Lower Similkameen Indian Band - Deflection Berms Project
Lower Similkameen Indian Band - Deflection Berms Project -
Douglas First Nation - Douglas IR# 8 Lot# 30 and 31 Development
Douglas IR#8 (08013) -
Xa'xtsa (Douglas First Nation) Wastewater and Sludge Management
Douglas IR#8 (08013) -
Sunrise Expansion Program
Reserve - Seabird Island Band -
Orchard/Vineyard Lease - Lot 42, Similkameen IR#2
Lot 42, Similkameen IR#2 -
Debris Deflector Installation
Debris Deflector Installation -
Annacis Water Main No. 2 Scour Protection project
Annacis Water Main No. 2 Scour Protection project -
Seabird Island Indian Band - Seabird Island Community and Cultural Centre
Seabird Island Indian Band - Seabird Island Community and Cultural Centre -
Lower Similkameen Indian Band - Flood Mitigation Project
Chopaka 7 & 8 Indian Reserve -
Seabird Island Cultural Education, Community Resource Centre and Long-House Project
Agassiz, British Columbia -
Sunrise Expansion Program
Reserve - Cheam First Nation -
Skatin-Wastewater System and Sludge Management
Skatin First Nation, 08015 - SKOOKUMCHUCK 4 -
Timber harvesting on Skookumchuck 4
Skoomkumchuk 4, 4A and 9 -
New Fibre Installation
Project Site 09: PopKum 1 -
Vito Shipyards Wharf Repairs - Extension to the Expiry Date - Public comments invited
Vito Shipyards Wharf Repairs - Extension to the Expiry Date -
Osoyoos Indian Band - Rendezvous Beach Resort
Osoyoos Indian Band - Rendezvous Beach Resort -
Proposed Vineyard at Osoyoos IR1
Osoyoos IR1 -
Site preparation for a subdivision on Popkum IR 2
Popkum IR2 -
New Fibre Installation
Project Site 03: Cheam 1 -
N'Quatqua-Wastewater and Sludge Management
07991 - NEQUATQUE 1-75805CLSRBC / 75667CLSRBC -
N'Quatqua Watermain Extension and Phase 1 Subdivision
N'Quatqua IR#1 -
Kwìkwèxwelhp Healing Village - Access Road Repair and Re-grading
Kwìkwèxwelhp Healing Village -
N'Quatqua Multi-Use Facility Project
N'Quatqua Multi-Use Facility Project -
Samahquam-Wastewater System and Sludge Management
Samahquam First Nation, 08041 - Q'ALATKU7EM -
New Fibre Installation
Project Site 01:Schelowat 1 -
Osoyoos Indian Band - Wolf Creek Affordable Housing Project
Osoyoos Indian Band - Wolf Creek Affordable Housing Project -
Yellowhead Copper Project
150 kilometres northeast of Kamloops -
Electric Vehicle Charging Station Installation at Osoyoos Border Crossing
Osoyoos Border Crossing -
Sq'éwlets Cultural and Recreational Multi-use Trail Project
Squawkum Creek No.3 -
Timber harvesting on MOUNT CURRIE 6
Mount Currie 6 -
Sq'ewlets - Squawkum Creek IR#3 Water System Upgrade
Squawkum Creek IR#3 -
Timber harvesting on MOUNT CURRIE 6 & MOUNT CURRIE 7
Mount Currie 6 -
Lílwat Nation: Xetólacw Village Road Resurfacing
Xetólacw Village where works are planned to occur is located roughly 5 km east of Mount Currie Village on IR #6. -
Sediment Removal at Hope Slough, Chilliwack
Hope Slough, Chilliwack -
Timber harvesting on MOUNT CURRIE 6 & MOUNT CURRIE 7
Mount Currie 7 -
Yakweakwioose First Nation Stormwater Outfall
Yakweakwioose 12 I.R. -
Cedarbrook Housing Development Project
Skway Indian Reserve No.5 (Shxwhá:y Village), Chilliwack, BC -
Nicomen Dike upgrade - Skumulsph IR 16
Athey Road, Nicomen Dike, Skumulsph IR 16 -
Ashwell Road Development Project
Ashwell Road, Chilliwack, BC -
Skowkale / Yakweakwioose; Subdivision Preloading
08059 -YAKWEAKWIOOSE 12 -
Stormwater Outflow into Chilliwack Creek
Skowkale 10.1.R. -
SAY Community Centre
Skowkale No. 10 Reserve Land -
Skowkale / Yakweakwioose; Subdivision Preloading
08049 - SKOWKALE10 -
Chilliwack Creek Stormwater Outfall Installation
Chilliwack -
Timber harvesting on MOUNT CURRIE 6
Mount Currie 6 -
Aitchelitz Subdivision and Community Infrastructure Upgrades
Aitchelitz -
Aitchelitz First Nation Stormwater Outfall
Aitchelitz First Nation -
(Lil'wat IR# 10) Poleyard Dike Improvements along Birkenhead River
Lil'wat IR#10 -
New Fibre Installation
Project Site 05: Tzeachten 13 -
Deroche Creek Long Term Solutions
Deroche Creek -
Deroche Creek Realignment and Sediment Removal
Deroche -
Harper Creek Mine Project
Vavenby -
Access Route and Drill Pad Construction at Inch Creek Hatchery
Inch Creek Hatchery -
PRTC Temporary Training Shelter
Chilliwack -
Road Realignment and Culvert Installation - 3rd Canadian Division Support Group (CDSG), Detachment British Columbia Mainland - Chilliwack
3rd Canadian Division Support Group (CDSG), Detachment British Columbia Mainland - Chilliwack -
Bivouac Site, OPSEE Training Area
OPSEE Training Area, Vance road, Cultus Lake -
New Fibre Installation
Project Site 04: Soowahlie 14 -
Inch Creek Hatchery Modernization: Construction of Tub Module
Inch Creek Hatchery -
Cultus Lake Septic Upgrade Project
Cultus Lake Laboratory -
Ministry of Transportation and Infrastructure - Culvert Replacement Columbia Valley Road
The Cultus Lake Laboratory -
Septic Tank Replacement at Edgewood BC Post Office
211 Lakeshore Ave, Edgewood, BC, V0G1J0 -
Mission Institution (Medium) - Hydro Service Connection
Mission Institution -
New Fibre Installation
Canoe Creek IR#2 -
Maintenance Dredging, Fraser River, Small Craft Harbours
Mission Harbour -
Sumas IR6 Former Brick Plan Demolition and Remediation
Sumas First Nation Indian Reserve 6 -
Construction of two buildings on Sumas First Nation Land, Abbotsford
Sumas First Nation, Abbotsford -
New Fibre Installation
Project Site 07: Langley 4 -
Kwantlen First Nation Housing Project
Langley IR2 -
Kwantlen First Nation Affordable Housing, BC
Kwantlen First Nation Affordable Housing -
Mómeqwem Multi-Use Pathway and McLennan Creek Active Transportation Crossing, Province of British Columbia
Abbotsford, BC -
Fraser Grain Terminal - Grain Export Facility Amendment (Utilities)
Fraser Grain Terminal - Grain Export Facility Amendment (Utilities) -
BC Ministry of Transportation and Infrastructure (MOTI) Highway 7 Expansion
Site Location -
Highway Widening at Whonnock Creek
Highway Widening Whonnock Creek -
Above ground demolition - former Hammond mill
Above ground demolition - former Hammond mill -
Highway Widening at York Creek
Highway Widening at York Creek -
New Telus Communications Inc. Telecommunication Tower Project in Canoe Creek I.R. No. 1 on Stswecem'c Xget'tem Nation Lands
Canoe Creek I.R. No. 1 on Stswecem'c Xget'tem Nation Lands -
Parking Lot repave
301 3rd Street West, Revelstoke -
Revision to the Posting for IAA Reference Number 85749 (Canoe Creek). Telus Communications Inc. is Proposing a Revision to their Original Telecommunication Tower Project in Canoe Creek I.R. No. 1 on Stswecem'c Xget'tem Nation Lands
Telecommunication Tower Project in Canoe Creek I.R. No. 1 on Stswecem'c Xget'tem Nation Lands -
Stswecem'c Xget'tem First Nation - Telus Telecommunications Tower - Canoe Creek/Meadow Lake
Stswecem'c Xget'tem First Nation -
Maintenance Dredging, Fraser River, Small Craft Harbours
Whonnock Harbour -
Snowforest Campground Upgrades
Mount Revelstoke National Park of Canada -
Amrize Pitt River Quarry Maintenance Dredging
Amrize Pitt River Quarry Maintenance Dredging -
Maintenance Dredging, Fraser River, Small Craft Harbours
McIvors Landing -
Parking Lot and Roadway Reconstruction at Mail Processing Plant (MPP) Langley, BC
5711 Production Way, Langley -
Port Haney waterfront redevelopment - Maple Ridge
Port Haney waterfront redevelopment -
AAFC Clearbrook Sub-Station Building Demolition and Construction
Abbotsford -
Maintenance Dredging, Fraser River, Small Craft Harbours
Kanaka Landing -
Maintenance Dredging, Fraser River, Small Craft Harbours
McMillan Island Harbour -
Bedford Channel Dredge Material Placement on McMillan Island IR6
McMillan Island Indian Reserve No.6 -
CP Logistics Park Vancouver and Pitt Meadows Road and Rail Improvements Projects
Pitt Meadows -
Passenger dock replacement - Indian Arm barge landing
Passenger dock replacement - Indian Arm barge landing -
FortisBC Eagle Mountain Barge Landing Improvements - Indian Arm
FortisBC Eagle Mountain Barge Landing Improvements - Indian Arm -
Log dump habitat restoration
Log dump habitat restoration -
Flood Mitigation and Beaver Management - Naval Radio Station Aldergrove
Naval Radio Station Aldergrove -
Pile and debris removal - Interfor water lots
Pile and debris removal - Interfor water lots -
Upland removals - Interfor Hammond Mill
Upland removals - Interfor Hammond Mill -
Stormwater outfall and dike upgrades
Stormwater outfall and dike upgrades -
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-04 - Amendment (Condition 36 - Extended Hours)
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-04 - Amendment (Condition 36 - Extended Hours) -
Lower berth access improvement
Lower berth access improvement -
Amendment to the construction hours in respect to condition 15 of the approved Golden Ears Forcemain (GDEFM) (PER No. 20-163)
Golden Ears Forcemain Project -
Burnco Langley Maintenance Dredging Project
Burnco Langley Maintenance Dredging Project -
Burnco Langley Maintenance Dredging
Burnco Langley Maintenance Dredging -
Langley Outfall Maintenance Dredging
Langley Outfall Maintenance Dredging -
Maintenance dredging - Metro Vancouver Langley Outfall
Maintenance dredging - Metro Vancouver Langley Outfall -
Amendment to the construction hours in respect to condition 15 of the approved Golden Ears Forcemain (GDEFM) (PER No. 20-163)
Amendment to the construction hours in respect to condition 15 of the approved Golden Ears Forcemain (GDEFM) (PER No. 20-163) -
Marina replacement - Katzie First Nation, Bishop's Reach
Marina replacement - Katzie First Nation, Bishop's Reach -
Katzie First Nation Shoreline Clean Up
Pitt Meadows -
City of Pitt Meadows/Katzie First Nation Stormwater Outfall - Bonson Rd.
City of Pitt Meadows/Katzie First Nation Stormwater Outfall - Bonson Rd. -
Wild Duck Inn-Pub Inc. - Site cleanup
Wild Duck Inn-Pub Inc. - Site cleanup -
Dredge pipe removals
Dredge pipe removals -
Dredge Pipe Removals - Permit Amendment 21-063-01
Dredge Pipe Removals - Permit Amendment 21-063-01 -
Creosote Pile Removal and Disposal - Extension PER No. 19-022-01
Creosote Pile Removal and Disposal - Extension PER No. 19-022-01 -
S&R Sawmills - D-Mill Urgent Bank Stabilization - Extension to Expiry Date
S&R Sawmills - D-Mill Urgent Bank Stabilization - Extension to Expiry Date -
Parsons channel maintenance dredging
Parsons channel maintenance dredging -
Revision to the Posting for IAA Reference Number 85748 (Dog Creek). Telus Communications Inc. is Proposing a Revision to their Original Telecommunication Tower Project in Dog Creek I.R. No. 1 on Stswecem'c Xget'tem Nation Lands.
Telecommunication Tower Project in Dog Creek I.R. No. 1 on Stswecem'c Xget'tem Nation Lands. -
Stswecem'c Xget'tem First Nation - Telus Telecommunications Tower - Dog Creek
Stswecem'c Xgat'tem First Nation -
New Telus Communications Inc. Telecommunication Tower Project in Dog Creek 1 Reserve on Stswecem'c Xget'tem Nation Lands
Dog Creek I.R. No. 1 on Stswecem'c Xget'tem Nation Lands -
New Dock Installation - Lot 14 Best Point
New Dock Installation - Lot 14 Best Point -
Maintenance dredging - S&R Sawmills
Maintenance dredging - S&R Sawmills -
Replacement of the Aldergrove Weather Radar
26600 8th Avenue, Langley, BC V0X 1A0 -
Halo Sawmill Maintenance Dredging
Halo Sawmill Maintenance Dredging -
Log Grapple Installation - Halo Sawmill
Log Grapple Installation - Halo Sawmill -
S&R Sawmills Ltd. - Maintenance Dredging
S&R Sawmills Ltd. - Maintenance Dredging -
Matsqui IR4 Multiuse Pathway
Matsqui IR4 Multiuse Pathway -
Metro Vancouver Maple Ridge Forcemain Scour Protection
Metro Vancouver Maple Ridge Forcemain Scour Protection -
Paving for Return Lane to USA at Aldergrove
Aldergrove, BC -
Seaichem Hiyam Housing Project
Seaichem IR 16, Squamish, BC -
Maintenance dredging - Teal-Jones waterlot
Maintenance dredging - Teal-Jones waterlot -
Teal-Jones Maintenance Dredging
Teal-Jones Maintenance Dredging -
Paved Berth Access - Harken Towing
Port Coquitlam -
Barnston Island Ferry Terminal Repairs
Barnston Island Ferry Terminal Repairs -
Reeve Slough Salmon Habitat Reconnection Project
Reeve Slough, Coquitlam, BC -
New Shared Dock for 702 and 706 Alderside Rd
Port Moody -
Jimmy Jimmy (Judd) Slough Culvert Replacement
Jimmy Jimmy (Judd) Slough Culvert Replacement -
New Float Installation for 2250 Farrer Cove Place
Public Notice New Float Installation for 2250 Farrer Cove Place -
New dock installation, located at 306 Sasamat Lane
New dock installation, located at 306 Sasamat Lane -
Private Dock replacement - 864 and 868 Alderside Rd.
Public Dock Replacement -
Rocky Point Park Boat Ramp Repair in Port Moody
Rocky Point Boat Ramp Repair in Port Moody -
New Dock Installation - 1000 Alderside Road
New Dock Installation - 1000 Alderside Road -
Private dock installation
Private dock installation -
New Dock Installation - 1020 Alderside Road
New Dock Installation - 1020 Alderside Road -
Rocky Point Park Maintenance Dredging
Rocky Point Park Maintenance Dredging -
Private residential dock at 1108 Alderside Road
Private residential dock at 1108 Alderside Road -
Existing Dock Replacement for 1140 Alderside Road
Existing Dock Replacement for 1140 Alderside Road -
New Buoy Installation
New Buoy Installation -
Flavelle Sawmill Can-Buoy Removals
Flavelle Sawmill Can-Buoy Removals -
Surrey Langley SkyTrain Project and Broadway Subway Project
Langley