Okanese Lagoon Access Road Upgrades

The Okanese First Nation is proposing to construct the new lagoon access roadway upgrade project. The project consists of widening of the existing road to a 7m wide driving surface and extending the turn around pad where the access road terminates at the lagoon. The road will be constructed utilizing nearby clay materials as fill, and surfacing will consist of 100mm of base course followed by 75mm of traffic gravel.

 

A culvert will also be replaced where a natural drainage course intersects the access road. This drainage course generally conveys water during spring melt periods, and is often dry during summer/fall. Erosion control measures will be implemented until adequate vegetative growth has re-established to mitigate sediment deposition to the drainage course.

More


Latest update

June 23, 2025 - Indigenous Services Canada issued its notice of determination Notice of Determination for the Okanese Lagoon Access Road Upgrades and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document number Document title File Date
1 Notice of Intent -Start of Public Comment Period - February 18, 2025

Contacts

ISC-SKENV
Indigenous Services Canada
Alvin Hamilton Building, 1783 Hamilton Street
Regina, Saskatchewan S4P 2B6
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Okanese First Nation (Saskatchewan)
  • Nature of Activity

    • Highways and Roads
  • Assessment Status

    Completed
  • Start Date

    2025-02-18
  • Proponent

    Okanese First Nation
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    89294