Okanese Cree Nation - Water Treatment Plant Upgrade
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The existing water treatment plant for Okanese Cree Nation has reached the end of it's life span as it is not able to meet demand of the community, therefore a new water treatment plant is proposed to be constructed in NE 32-22-10 W2M. The water treatment plant upgrades to include a new water treatment plan, including room for expansion to meet the future goals of the community. The upgrade will also include new treatment and pumping equipment, dry pit access, backup power, control upgrades, with upgraded treatment process, including biological and membrane filtration. During the construction phase the following activities will take place: stripping site, excavation for reservoir, demolition of old water plant, salvaging equipment where possible. Disposal of materials from the demolished water plant in suitable landfill as designated by the Engineer.
Latest update
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 2 | Notice of Determination for Okanese Cree Nation - Water Treatment Plant Upgrade | - | July 28, 2022 |
| 1 | Public Comment Period on Intent to Make a Determination | - | November 25, 2020 |
Contacts
ISC-SKENVIndigenous Services Canada
Alvin Hamilton Building, 1783 Hamilton Street
Regina, Saskatchewan S4P 2B6
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Okanese IR 82 (Saskatchewan)
-
Nature of Activity
- Water Management
-
Assessment Status
Completed -
Start Date
2021-04-01 -
Proponent
Okanese Cree Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
81174
Nearby assessments
...within 200 kilometres-
Okanese First Nation Head Start Building Construction
Okanese First Nation -
Okanese Lagoon Access Road Upgrades
Okanese First Nation -
Blanket Permit - SaskEnergy - Gasification of Okanese Indian Reserve No. 82
Okanese First Nation -
Peepeekisis Cree Nation Community Lagoon Improvements
PEEPEEKISIS INDIAN RESERVE NO. 81 -
Little Black Bear First Nation Water Treatment Plant Upgrades
LITTLE BLACK BEAR INDIAN RESERVE NO. 84 -
Peepeekisis Cree Nation Road Construction
PEEPEEKISIS INDIAN RESERVE NO. 81 -
Peepeekisis Cree Nation Youth Safe House
PEEPEEKISIS INDIAN RESERVE NO. 81 -
Star Blanket Water Treatment Plant Upgrades
Star Blanket First Nation -
Peepeekisis Cree Nation Youth Impact Centre
Peepeekisis Cree Nation -
Peepeekisis Community Centre
Peepeekisis IR #81 -
SaskPower Rural Rebuild - 2D-41 Birmingham Southwest
Star Blanket Indian Reserve No. 83-D -
Standing Buffalo Dakota Nation - Solid Waste Transfer Station
Standing Buffalo IR 78 -
Standing Buffalo Dakota Nation - Water Treatment Plant Upgrade
Standing Buffalo IR 78 -
Standing Buffalo Dakota Nation Youth Centre
Standing Buffalo Indian Reserve No. 78 -
Standing Buffalo Day Care and Head Start
Standing Buffalo Indian Reserve No. 78 -
Standing Buffalo Gas Station Expansion
Standing Buffalo Dakota Nation -
Zagime Greenhouse
Zagime IR #74-9 / IR #74-2 -
Pasqua First Nation Lagoon Upgrade
Pasqua First Nation -
Pasqua First Nation - New Spray Park
Pasqua 79 -
Pasqua First Nation Subdivision Phase 4
Pasqua First Nation -
Peepeekisis Community Centre Gas Bar
Peepeekisis IR #81 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NE-32-17-10-2
Cowessess First Nation -
Basadinaa - Crooked Lake Cottage Lots Head Lease #3- Zagime Anishinabek First Nation
Sakimay IR 74, Shesheep IR 74A -
New (Multiple) Tower Construction
School Tower -
Zagime Anishinabek Youth Safe House
Shesheep Indian Reserve No. 74A -
Basadinaa - Crooked Lake Cottage Lots Head Lease #5- Zagime Anishinabek First Nation
Shesheep IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #4- Zagime Anishinabek First Nation
Sakimay IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #4- Zagime Anishinabek First Nation
Shesheep IR 74A -
Basadinaa - Crooked Lake Cottage Lots Head Lease #5- Zagime Anishinabek First Nation
Sakimay IR 74 -
Basadinaa - Crooked Lake Cottage Lots
Shesheep IR 74A & Sakimay IR 74 -
Pasqua First Nation Elders's Centre
Pasqua First Nation -
Zagime Anishinabëk Gasification
Zagime Anishinabëk Indian Reserves 74, 74-2, 74-9, 74-12, 74-16, 74-17 and Shesheep IR 74A -
Hutterite Brethren Church of Twin Creek Inc. - Grazing Permit - Muskowekwan First Nation - 2019-2023
Muskowekwan 85-10 and 85-15 -
Kawacatoose First Nation Road Repair Project
Kawacatoose First Nation -
Zagime Anishinabek New Subdivision Project
Zagime Anishinabek -
Agricultural permits on Saskatchewan First Nation Reserve Lands
Saskatchewan First Nations -
Grazing Permits on Saskatchewan First Nations Reserve Lands
Saskatchewan First Nation Communities -
Zagime Anishinabek Water Treatment Plant and Sewage Pumping Station Upgrade
Zagime Anishinabek First Nations -
Zagime Anishinabek School
Sakimay IR 74 -
New Fibre Installation
Project Site 3: Zagime Anishinabek -
Zagime Anishinabek Youth Centre
Sakimay Indian Reserve No. 74 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SE-08-19a-05-2
Cowessess First Nation -
Muskowekwan Gas Bar & Convenience Store
Muskowekwan IR 85 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-29-20-04-2
Cowessess First Nation -
Muskowekwan Solid Waste Transfer Station
Muskowekwan IR 85 -
New (Multiple) Tower Construction
Muscowpetung Saulteaux Nation - North Tower -
Blanket Permit - SaskEnergy - Gasification of Sakimay
Sakimay -
Muskowekwan Water Treatment Plant Upgrades
Muskowekwan IR 85 -
Crooked Lake Outlet Structure Replacement
Crooked Lake - SW-08-19A-05 W2M -
Vertical Farming and Sustainable Grazing for Food Security and Innovation
near Grenfell -
Muskowekwan Lagoon & Sewage Pumping Station
Muskowekwan IR 85 -
New (Multiple) Tower Construction
Muscowpetung Saulteaux Nation - South Tower -
Muskowekwan Potash Mine Project
Lestock -
Muskowekwan First Nation Wastewater Infrastructure Upgrades
MUSKOWEKWAN INDIAN RESERVE NO. 85 -
Carry the Kettle First Nation - Nakota Junction Gas Station
Assiniboine IR 76 -
Carry The Kettle First Nation Solid Waste Transfer Station
Assiniboine IR 76 -
Carry The Kettle First Nation Lagoon Expansion
Assiniboine IR 76 -
Zagime Community Center
Zagime IR #74-3 -
Muscowpetung Powwow Arbour
Muscowpetung Saulteaux Nation -
Muscowpetung Daycare & Headstart
Muscowpetung First Nation -
Blanket Permit - SaskEnergy - Gasification of Assiniboine Indian Reserve No. 76
Assiniboine Reserve No. 76 -
Yorkton Tribal Council Child & Family Services Office Building
Kahkewistahaw IR 92 A-1 -
Muscowpetung Saulteaux Nation - Solid Waste Transfer Station
Muscowpetung Saulteaux Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation
Cowessess First Nation -
New Fibre Installation
Project Site 2: Cowessess -
Zagime Anishinabek First Nation - Section 95 housing project
Sakimay 74-5 -
Cowessess - Agricultural Permit G. Lerat
Cowessess Indian Reserve 73 -
Cowessess First Nation Solid Waste Transfer Station
Cowessess First Nation -
Multi-use Front Lake Community Walking Path
Multi-use Front Lake Community Walking Path -
On hold - Muskowekwan Wind Farm Project
Muskowekwan Indian Reserve 85-43, 85-49, 85-50, 85-63, 85-64, 85-65 -
George Gordon First Nation Lagoon Upgrades
Gordon 86 Indian Reserve -
George Gordon First Nation Wastewater Infrastructure Upgrades
Gordon 86 Indian Reserve -
Kahkewistahaw First Nation Operations & Maintenance Building and Fire Hall
Kahkewistahaw First Nation -
Kahkewistahaw First Nation Green Links and Teaching Garden: Connecting Elders and Youth
Kahkewistahaw First Nation -
George Gordon First Nation Fire Hall
George Gordon First Nation -
Piapot Lagoon, Forcemain and Sewage Pumping Station
Piapot IR 75 -
Kahkewistahaw First Nation Lagoon Upgrade
Kahkewistahaw IR 72 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NE-06-17-05-02
Cowessess First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-06-17-05-2
Cowessess First Nation -
New Fibre Installation
Project Site 4: Kahkewistahaw -
Kahkewistahaw First Nation Water Treatment Plant Upgrade
Kahkewistahaw First Nation -
Kahkewistahaw First Nation Subdivision Development (Phase 23)
Kahkewistahaw IR 72 -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Kahkewistahaw First Nation Solid Waste Transfer Station
Kahkewistahaw IR 72 -
Muscowpetung Powwow Arbour
Muscowpetung IR 80 -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Piapot First Nation Road to Community Wells
Piapot IR 75 -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Ochapowace Nation Water Treatment Plant Upgrades
Ochapowace Nation -
New Fibre Installation
Project Site 5: Ochapowace -
Ochapowace Nation Subdivision - Phase I
Ochapowace Nation -
Saskatchewan Agriculture Drainage Network - Vipond Drainage Network Project
6 kilometres east of Glenavon -
Active Transportation for Ochapowace First Nation
Active Transportation for Ochapowace First Nation -
New (Multiple) Tower Construction
Poject site 8: Kawacatoose FN I.r. 88 -
New (Multiple) Tower Construction
Poject site 7: Kawacatoose FN I.r. 88 -
New (Multiple) Tower Construction
Poject site 6: Kawacatoose FN I.r. 88 -
New (Multiple) Tower Construction
Poject site 3: Kawacatoose FN I.r. 88 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-09-15-05-2
Cowessess First Nation -
Kawacatoose First Nation Water Treatment Plant Upgrade and Expansion
Kawacatoose IR 88 -
New (Multiple) Tower Construction
Poject site 2: Kawacatoose FN I.r. 88 -
New (Multiple) Tower Construction
Poject site 1: Kawacatoose FN I.r. 88 -
New (Multiple) Tower Construction
Poject site 4: Kawacatoose FN I.r. 88 -
Saskatchewan Agriculture Drainage Network - Saline Lake Drainage Network Project
100 kilometres northwest of Yorkton -
Zagime Anishinabek Solid Waste Transfer Station
Sakimay IR 74 -
New (Multiple) Tower Construction
Poject site 5: Kawacatoose FN I.r. 88 -
Albany Potash Mine Project
30 kilometers southeast of Regina, Saskatchewan, within the Regional Municipalities of Lajord and Francis -
Awasis Solar Project
SE 7-17-18 W2 -
Cowessess 10 MW Solar Project
Cowessess IR #73 -
Awasis Solar - 10 MW Project
Cowessess IR #73 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NW-23-14-05-2
Cowessess First Nation -
Fishing Lake First Nation - Sewage Lagoon Expansion
Fishing Lake IR 89A -
Saskatchewan Agriculture Drainage Network - Wascana Block A Drainage Network Project
25 kilometres southeast of Regina -
Solid Waste Transfer Station - Fishing Lake First Nation
Fishing Lake Indian Reserve 89 -
1236 Albert Street - Cowessess First Nation - Building Development
Cowessess IR No. 73 -
Cowessess Urban Indigenous Health centre
Cowessess Indian reserve No. 73 -
1201 Angus Street - Cowessess First Nation - Building Development for parking
Cowessess IR No. 73 -
Albert Street Building Development
1246 Albert Street, Regina, Saskatchewan -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-23-12-10-2
Cowessess First Nation -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Regina -
Key Junction Gas Bar & Confectionery
The Key First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NW-16-12-10-2
Cowessess First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-18-12-10-2
Cowessess First Nation -
Fishing Lake First Nation - Agricultural Permit - C. Fehr
Fishing Lake IR 89 -
Agricultural permit - Fishing Lake - C. Fehr #2
Fishing Lake IR 89 -
Fishing Lake First Nation Prevention Centre
FISHING LAKE INDIAN RESERVE NO. 89 -
Installation of Potassium Acetate Tanks - Public Comments Invited
Regina International Airport -
Installation of Potassium Acetate Tanks - Public Comments Invited
Regina International Airport -
Runway De-Icing Liquid Storage Tank
Regina -
Runway 13-31 Rehabilitation
Regina -
West Land Road and Sewer Extension
Sakimay IR 74-6 -
Saskatchewan Indigenous Enterprise Foundation Inc. Southern Office Complex
Lot 19 Plan 112422, NE 1/4 Sec. 20-17-20, W.2 M -
Bekevar Wind Energy Project
Cowessess IR No. 73A -
Keeseekoose - Agricultural Permit - K. Martenuik
Keeseekoose - Agricultural Permit - K. Marteniuk -
Saskatchewan Agriculture Drainage Network - Blackbird Creek Drainage Network Project
50 kilometres east of Yorkton, Saskatchewan -
Ocean Man First Nation 1 MW Solar Project
Ocean Man IR 69I -
Ocean Man Indian Reserve 69E Well pad2
Ocean Man Indian Reserve 69E -
Ocean Man First Nation Headstart and Daycare
Ocean Man Indian Reserve No. 69 -
New Fibre Installation - Central and Southeastern SK
Project site 1: Cote 64 -
The Key First Nation Firehall
The Key First Nation -
Walkway to support healthy lifestyle for Cote First Nation
Bagerville -
Upgrade Single Tower & New Fibre Installation
Project Site 2: Central East region -Badgerville -
The Key First Nation Lagoon Upgrade Project
The Key First Nation -
Cote First Nation Main Landfill Decommissioning
Cote IR 64 -
Cote First Nation #64 - Landfill decommissioning at the Main Landfill Site
Badgerville -
New Fibre Installation - Central and Southeastern SK
Project site 6: COTE I.R. 64 -
Ocean Man Indian Reserve 69E Pipeline2
Ocean Man Indian Reserve 69E -
Ocean Man Indian Reserve 69E Pipeline3
Ocean Man Indian Reserve 69E -
Ocean Man Indian Reserve 69E Well pad
Ocean Man Indian Reserve 69E -
Ocean Man Indian Reserve 69 Well Pad FS-2023
Ocean Man Indian Reserve 69 -
Ocean Man Indian Reserve 69E Pipeline4
Ocean Man Indian Reserve 69E -
Cote First Nation Wood Treatment Remediation Project
Cote IR 64 -
Meadow Lake Tribal Council: Solar Project
NE¼-31-09-09 W2M -
Keeseekoose Education Center Drainage
KEESEEKOOSE INDIAN RESERVE NO. 66 -
Keeseekoose First Nation Well Completions
KEESEEKOOSE INDIAN RESERVE NO. 66 -
Keeseekoose Road to Community Wells
KEESEEKOOSE INDIAN RESERVE NO. 66 -
SaskPower's Power Generation - Ocean Man Solar Interconnect
Ocean Man IR 69I -
Keeseekoose Multi-Purpose Health facility
Keeseekoose IR 66 -
New Fibre Installation - Central and Southeastern SK
Project site 10: KEESEEKOOSE I.R. 66 -
Cote First Nation Solid Waste Transfer Station
Cote IR 64 -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA BAND I.R. 68 (Site #2) -
Keeseekoose - Agricultural Permit - S. Marsh
Keeseekoose - Agricultural Permit - S. Marsh -
Saskatchewan Agriculture Drainage Network - Lang West Drainage Network Project
32 kilometres northwest of Weyburn -
PADCOM Potash Solution Mining Project
16 kilometres west of Russell -
Last Mountain Lake National Wildlife Area Observation Tower II
Last Mountain Lake National Wildlife Area -
Last Mountain Lake National Wildlife Area Water Control Structure Re-naturalization Project
Last Mountain Lake National Wildlife Area -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA BAND I.R. 68 (Site #1) -
Stalwart National Wildlife Area Water Control Structure Re-naturalization Project
Stalwart National Wildlife Area -
Pheasant Rump Lagoon Expansion
Pheasant Rump Nakota IR 68D -
Cultural Centre for Women, Girls and Two Spirited Band Members
Kisbey -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA INDIAN RESERVE NO. 68D (Site #3) -
Pheasant Rump Nakota Nation Subdivision Expansion
SW 19-08-005 W2M -
Pheasant Rump Nakota IR 68D Gasification Project
Pheasant Rump Nakota IR 68D -
Pheasant Rump Nakota First Nation - Cultural Centre
Pheasant Rump Nakota First Nation - Cultural Centre -
Yellow Quill First Nation New Subdivision
Yellow Quill IR 90 -
New Fibre Installation
Project Site 1: White Bear -
White Bear First Nation Wastewater Upgrade Project
White Bear First Nation -
White Bear First Nation Solid Waste Transfer Station Project
White Bear First Nation -
Yellow Quill First Nation Wastewater Infrastructure Upgrades
Yellow Quill IR 90 -
White Bear First Nation Community Spray Park
White Bear 70 -
Energy East Project
Moosomin -
Runway Rehabilitation of 11R-29L - 15 Wing Moose Jaw
15 Wing Moose Jaw -
Yellow Quill First Nation Subdivision Stage 2
Yellow Quill IR 90 -
Moose Jaw Combined Cycle Power Station Project
Moose Jaw -
Saskatchewan Agriculture Drainage Network - Dry Lake Drainage Network Project
50 kilometres northeast of Weyburn -
Tootinaowaziibeeng - CHRT 41 - Wellness Centre
Tootinaowaziibeeng -
Tootinaowaziibeeng - CHRT 41 - Jordan's Principle - Multiple Buildings - 2324
Tootinaowaziibeeng - CHRT 41 - Jordan's Principle - Multiple Buildings - 2324 -
Aspen Power Station Project
Lanigan -
Relocate RV Compound - 15 Wing Moose Jaw
15 Wing Moose Jaw -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Northwest -
Construct North Access Road - 15 Wing Moose Jaw
15 Wing Moose Jaw -
Sanitary Force Main Pipeline Replacement Design and Construction - 15 Wing Moose Jaw
15 Wing Moose Jaw -
Water Distribution Network Replacement and Storm and Sanitary Network Rehabilitation at 15 Wing Moose Jaw
15 Wing Moose Jaw -
Runway Rehabilitation - 15 Wing Moose Jaw
15 Wing Moose Jaw -
Remediate Sites and Construct Buildings for Future Aircrew Training (FAcT) Program- 15 Wing Moose Jaw
15 Wing Moose Jaw -
On hold - Piapot Wind Farm Project
Piapot Indian Reserve 75 -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Southwest -
Birdtail Sioux First Nation Aerated Lagoon Project
Birdtail Lagoon First Nation -
Waywayseecappo First Nation - Water Treatment Plant
Waywayseecappo First Nation -
Birdtail Sioux Dakota Nation Prevention Centre for the Delivery of FNCFS
Birdtail Sioux Dakota Nation -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Northeast -
Waywayseecappo - New Water Treatment Plant - 2324
Waywayseecappo WTP -
Tower Hill VHF Tower
Riding Mountain National Park -
PARKS CANADA AGENCY - Riding Mountain National Park (West Side) Addition of New Site Known as Tower Hill
PARKS CANADA AGENCY - Riding Mountain National Park (West Side) -
Waywayseecappo First Nation - School Water Treatment Plant Recovery
Waywayseecappo First Nation -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Southeast -
Pheasant Rump Nakota Nation Solid Waste Transfer Station
Pheasant Rump IR 68 -
Kawacatoose First Nation Subdivision
Kawacatoose IR 88 -
Kinistin Saulteaux Nation Barrier River Bridge Replacement
Kinistin Saulteaux Nation -
Kinistin Saulteaux Nation Sewage Lagoon Expansion
Kinistin IR No. 91 -
Kinistin Solid Waste Transfer Station
Kinistin Saulteaux Nation -
Baldy Prescribed Fire
Riding Mountain National Park of Canada -
Menzies Prescribed Fire
Riding Mountain National Park of Canada