The project involves stabilizing and protecting approximately 840 meters of the Lake Winnipeg shoreline within Traverse Bay and the Sagkeeng First Nation. Slope stabilization and erosion protection are required to arrest severe shoreline erosion and slope failure that are approaching three residences and the community's North Shore Road.
Key elements of the design include excavating a keyway for scour protection at the base of the eroded bank (isolated from the water's edge by a beach), regrading the eroded bank to a 2h:1v slope, installing non-woven geotextile along the bank and keyway, placing a 0.45 m thick bedding layer of 200 mm down granular material, placing 300 to 1200 mm diameter riprap (blast rock) above the bedding material to a final grade of 2.5h:1v, and site restoration works. Access will be from North Shore Road, and the top of the bank will be cleared to the extent required for equipment to work from the top of the bank. No in-water work will be conducted. Some material will be stockpiled on site at nearby locations.
The construction is to take place between January 21 and July 31 2026, with completion of the bank stabilization and erosion protection works (all work below the extreme high water mark) by April 7 2026. It will result in a permanent change (stabilization) of the shoreline above the normal water level.
A Request for Review has been submitted to Fisheries and Oceans Canada to determine whether the project will need authorization under the Fisheries Act.
Latest update
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 2 | Notice of Determination | - | January 16, 2026 |
| 1 | Traverse Bay Shoreline Stabilization - Site A (North Shoreline) | - | December 16, 2025 |
Contacts
Indigenous Services CanadaAngela Bidinosti, Sr. Environmental Specialist
200-365 Hargrave Street
Winnipeg, Manitoba R3B 3A3
Telephone: 204-227-0835
Email: angela.bidinosti@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Traverse Bay North Shoreline - Fort Alexander Reserve (Manitoba)
-
Nature of Activity
- Other, not otherwise specified
-
Assessment Status
Completed -
Start Date
2025-12-16 -
Proponent
Sagkeeng First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
90098
Nearby assessments
...within 200 kilometres-
Sagkeeng First Nation - Shoreline Stabilization - Segment 4
Sagkeeng First Nation -
Sagkeeng (Fort Alexander) Assisted Living Complex
Sagkeeng First Nation -
Sagkeeng First Nation - Hybrid Green Infrastructure Shoreline Protection
Sagkeeng First Nation - Hybrid Green Infrastructure Shoreline Protection -
Victoria Beach Harbour Manitoba - Routine Maintenance Dredging of Lake Winnipeg at Victoria Beach - Winter 2019
Victoria Beach Harbour -
Victoria Beach Hydrometric Stilling Well Removal - Winter 2024
Victoria Beach Harbour -
Black River First Nation - Transitional Housing
Black River First Nation -
Black River First Nation Watermain Renewal Project
Black River First Nation -
Xplornet Communications Inc. Radiocommunication Antenna Addition on Black River First Nation Reserve No. 260
Black River First Nation Reserve No. 260 -
Black River First Nation Prevention Centre
Black River First Nation -
New Fibre Installation
Black River First Nation no. 9 -
Black River Waste Transfer Station
Black River Reserve -
Launch Ramp Replacement, Balsam Bay, Manitoba
Balsam Bay, Manitoba -
Brokenhead - CHRT41 - Jordan's Principle Building/Centre for BON - 2324
Brokenhead Jordan's Principle Centre -
Multi-use Arbour & Powwow Grounds on Brokenhead Reserve
Scanterbury on the Brokenhead Reserve -
Brokenhead Ojibway Nation - Elder's Lodge - 2324
Brokenhead Ojibway Nation - Elder's Lodge - 2324 -
Brokenhead Ojibway Nation Elders Lodge Project
Brokenhead Ojibway Nation -
Brokenhead Ojibway Nation Land Base Building
Brokenhead Ojibway Nation - Reserve No. 4 -
Brokenhead Ojibway Nation - Cultural Healing Lodge Development
Brokenhead Ojibway Nation -
Gimli Harbour Launch Ramp Reconstruction - Gimli, MB - Winter 2021/22
Gimli Harbour, Gimli, MB -
Arnes Harbour Manitoba - Routine Maintenance Dredging of the Drunken River at Lake Winnipeg - Winter 2019
Arnes Harbour -
In Situ Decommissioning of the Whiteshell Reactor #1
Pinawa -
Hnausa Harbour, Manitoba - FFMC Barge Loading Ramp Construction - Winter 2021
Hnausa Harbour -
Hnausa Harbour Manitoba - Harbour Dredging of Lake Winnipeg at Hnausa - Winter 2020-21
Hnausa Harbour -
Hnausa – Wharf Replacement Project
Hnausa -
Hollow Water First Nation Transitional Spaces
Hollow Water First Nation -
Float Replacement, Hecla, Manitoba
Hecla, Manitoba -
Hollow Water First Nation Prevention Centre
Hollow Water First Nation -
Hollow Water - CHRT 41 - Staff Accommodations - 2324
Hollow Water - CHRT 41 - Staff Accommodations - 2324 -
New Tower Construction, Upgrade single tower & New Fibre Installation
Project site 4: Hollow Water No. 10 -
New Fibre Installation
Hollow Water First Nation no.10 -
Hollow Water Wharf Construction
Hollow Water -
Launch Ramp Reconstruction - Riverton, Manitoba
Riverton, Manitoba -
Selkirk CCG Asphalt paving
Selkirk Coast Guard Base -
Gull Harbour Lighthouse Rebuild
Gull Harbour -
Launch Ramp Reconstruction - Gull Harbour, MB - Fall 2021
Gull Harbour -
Rockwood National Wildlife Area Water Control Structure Re-naturalization Project
Rockwood National Wildlife Area -
Lower Fort Gary Wastewater Treatment Plant Outflow Pipe Replacement
Lower Fort Garry National Historic Site -
St. Andrews Lock and Dam Bridge Deck Replacement
St. Andrews Lock and Dam -
Wharf Reconstruction - Little Grindstone, MB - Winter/Spring 2020
Little Grindstone Harbour -
Vivian Sand Project
Springfield -
Pond and Landscape Upgrade at the Winnipeg Tax Centre
Winnipeg -
Sugar Creek Peat Harvesting Project
Fisher River Cree Nation -
Energy East Project
Winnipeg -
New (Multiple) Tower Construction & New Fibre Installation
Mosakahiken Cree Nation (Moose Lake), Northern Manitoba -
Temporary Dock - The Forks National Historic Site, Red River, MB
The Forks National Historic Site, Winnipeg -
T-91 VORTAC Site Decommissioning
Winnipeg Richardson International Airport -
Avis overflow storage compound Sherwin Road - Decommissioning
Winnipeg Richardson International Airport -
T-201 Standard Aero Plant 6 Building Expansion
Winnipeg Richardson International Airport -
Electric Bus Charging Station Removal and Demolition
Winnipeg Richardson International Airport -
YWG Groundside Roadway Infrastructure Upgrade Project
Winnipeg Richardson International Airport -
Runway 18-36 Rehabilitation at YWG
Winnipeg Richardson International Airport -
East Side Air Cargo Development at Winnipeg Richardson International Airport (YWG)
Winnipeg Richardson International Airport -
Perimeter Aviation T-5 Hangar Door Replacement
Winnipeg Richardson International Airport -
2026 Airfield Improvements Project
Winnipeg Richardson International Airport -
Perimeter Aviation Terminal Building Expansion
Winnipeg Richardson International Airport -
2023 YWG Airfield Improvements Project
Winnipeg Richardson International Airport -
Keewatin Air T-216 Hanger - Medevac Facility Addition
Winnipeg Richardson International Airport -
Perimeter Aviation LP Parking Lot
Winnipeg Richardson International Airport -
Airport West Perimeter Road and Primary Security Line Relocation
Winnipeg Richardson International Airport -
Winnipeg Airport West Lands Moray Street Extension and Site Servicing
Winnipeg Richardson International Airport -
T-283 SkyNorth Air Apron Pavement Expansion project
Winnipeg Richardson International Airport -
T-145 STARS Hangar Addition
Winnipeg Richardson International Airport -
Generator Replacement and Fire Panel Upgrade at existing Hangar building
Winnipeg Richardson International Airport (YWG) -
New electrical service to existing building at 80 Hangar Line Road
Winnipeg Richardson International Airport (YWG) -
Upgrade of 17 Wing Vehicle Fuel Farm - 17 Wing Winnipeg
17 Wing Winnipeg -
T-149 & T-150 Air Canada Hangar, Petroleum Storage System Upgrades
Winnipeg Richardson International Airport -
Air Canada Hangar T-149 water supply refurbishment project
Winnipeg Richardson International Airport -
17 Wing Winnipeg - V6600 Disposal of 13 RHUs and 18 Garages (South Site)
17 Wing Winnipeg -
Hangar Line Road Extension - 17 Wing Winnipeg
17 Wing Winnipeg -
Manitoba-Minnesota Transmission Project
Riel Converter Station, near Dorsey, Manitoba -
Naawi Oodena - Subdivision - Parcel A - 2324
Naawi Oodena -
Freshwater Institute Underground Chilled Water Piping Replacement
Freshwater Institute in Winnipeg, MB -
Launch Ramp Reconstruction - Calders Dock, MB - Fall 2021
Calders Dock Harbour -
City of Winnipeg Insect Control Branch and Heliport Relocation Project
City of Winnipeg -
New Fibre Installation
Project site 11 (Wabaseemoong Independent Nations) -
Xplornet Communications Inc. Radiocommunication Antenna Addition on Peguis First Nation Reserve No. 269
Peguis First Nation Reserve No. 269 -
Fisher River Used Oil Burner Installation
Fisher River Cree Nation -
Fisher River Cree Nation East Road Replacement Project
Fisher River Cree Nation Reserve no. 44 -
Peguis First Nation Recreation Centre Soil Remediation
Peguis First Nation Recreation Centre Soil Remediation -
New Peguis First Nation Radiocommunication Tower in Peguis, MB
Peguis, MB -
Hydrometric Station Decommissioning - Fisher River, Manitoba
Fisher River, Manitoba -
Launch Ramp Replacement, Pine Dock, Manitoba
Pine Dock -
Fisher River Cree Nation Jordan Principle Building
Fisher River Cree Nation -
Potential Regional Assessment of the Trans-Canada Highway Improvement Project
Whiteshell Provincial Park -
Potential Regional Assessment of the Trans-Canada Highway Improvement Project
Kenora -
Twinning of the Trans-Canada Highway in Manitoba
Whiteshell Provincial Park -
Twinning of the Trans-Canada Highway in Manitoba
Whiteshell Provincial Park -
Trans-Canada Highway Twinning Project
Highway 17 at Manitoba/Ontario border -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 3: BCN-BLD-TW3 -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 2: BCN-BLD-TW2 -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein First Nation School
Bloodvein School -
Launch Ramp Replacement, Matheson Island, Manitoba
Matheson Island -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
Bloodvein River Airport Wildlife Fencing
Bloodvein River -
Bloodvein First Nation CFS Prevention Building
Bloodvein First Nation -
Bloodvein First Nation Staff Housing
Bloodvein First Nation -
Bloodvein First Nation Environmental Remedial Actions - 5 PHC Sites
Bloodvein First Nation -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 1: BCN-BLD-TW1 -
New (Multiple) and Upgrades (Multiple) Radiocommunications Towers
Bloodvein -
Bell MTS Radiocommunication Tower on Bloodvein Reserve No. 12
Bloodvein Reserve No. 12 -
Subsurface Septic System Rehabilitation
Ontario -
Shoal Lake 40 New K-8 School
Shoal Lake 40 -
Women's Lodge & Cultural Safe Space
Kejick -
New Fibre Installation
Project site 24 (Shoal Lake No.39) -
Communal Wastewater Collection and Treatment Rehabilitation
Kenora -
Niisaachewan Anishinaabe Nation Gas Station, Convenience Store & Canteen
Niisaachewan Anishinaabe First Nation -
Niisaachewan Anishinaabe Nation - Micro Subdivision Development Project
Niisaachewan Anishinaabe Nation -
Trans-Canada Highway Twinning Project
Kenora -
Lake Manitoba - South Access Road Upgrades - 2324
Lake Manitoba -
Obashkaandagaang First Nation Water Treatment Project
Obashkaandagaang First Nation -
Replace Existing Distribution Water Main at West End WTP and Upgrade 10 Residential Septic Fields ICIP (57278)
Washagamis Bay First Nation -
ENV - 268 - EA - ERP - Kinonjeoshtegon - CHRT 41 - JP New Building and Renovation - P057361 - 2425
Kinonjeoshtegon First Nation -
Contaminated Soil Remediation
Martheson Bay Road, Kenora Indian Reserve No. 38b, Kenora, Ontario -
Anishinabe of Wauzhushk Onigum - Golden Eagle Centre Retrofitting Project
Anishinabe of Wauzhushk Onigum -
Development of 20 Residential Housing Lots on Anishinabe of Wauzhushk Onigum Nation
Anishinabe of Wauzhushk Onigum -
Dakota Tipi First Nation - New Jordan's Principle Facility
Dakota Tipi First Nation -
Lake Manitoba First Nation - CHRT41 FNCFS Prevention Centre
Lake Manitoba First Nation -
Little Grand Rapids Dock & Dock Foundation Posts
Little Grand Rapids -
Little Grand Rapids RCMP New Living Quarters
Little Grand Rapids -
New Fibre Installation
Project site: Various parts of Manitoba -
New Fibre Installation
Project site 08 (Kenora No. 38B) -
New Broadband Communications North Inc. Telecommunication Tower at Lake Manitoba First Nation on Dog Creek Reserve No. 46
Lake Manitoba First Nation, MB -
Wauzhushk Onigum Multi-Purpose Centre
Wauzhushk Onigum Multi-Purpose Centre -
Construction of Land-Based and Cultural Learning Centre on Wauzhushk Onigum Nation
Wauzhushk Onigum Nation -
Southeast CFS Little Grand Rapids Staff Housing (Personnel and Visiting Professionals) and Prevention Centre
Little Grand Rapids First Nation -
Little Grand Rapids First Nation School
Little Grand Rapids First Nation School -
Sandy Bay First Nation New Water Treatment Plant
Sandy Bay First Nation -
Little Grand Rapids First Nation Transitional Housing (Temporary Housing)
Little Grand Rapids First Nation -
New Fibre Installation - Sandy Bay
Project site: Sandy Bay -
Aboveground Fuel Storage Replacement in Little Grand Rapids, Manitoba
Little Grand Rapids -
Sandy Bay First Nation CFS Prevention Center Temporary Facilities (10 RTMs)
Sandy Bay First Nation -
Northwest Angle 33 First Nation Water Treatment Project - Angle Inlet
Northwest Angle #33 FN -
Little Grand Rapids Submarine Cable Installation Project
Little Grand Rapids -
Grassy Narrows First Nation 20-unit Apartment Complex
Grassy Narrows First Nation -
Grassy Narrows Long-term Care and Treatment Facility Construction
Grassy Narrows Long-term Care and Treatment Facility Construction -
Grassy Narrows First Nation Water and Wastewater System Upgrades
Grassy Narrows First Nation -
Grassy Narrows - Health Centre Renewal
Grassy Narrows -
Windigo Island Dock Replacement Project
Animakee Wa Zhing #37 -
Long Plain FN - Directional Drilling - Water and Sewer Pipeline
Long Plain First Nation -
Windigo Island Water Treatment Project
Animakee Wa Zhing First Nation - Windigo Island -
Upgrade of the Windigo Island Docking Infrastructure Accessibility
Windigo Islands -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake Manitoba Outlet Channel inlet in Lake Manitoba -
Long Plain - CHRT41 - Prevention Centre - P055810 - 2324
Long Plain First Nation -
Long Plain School Renovation & Addition
Long Plain First Nation -
Berens River 13 Rapid Housing Fourplexes
Berens River 13 -
Long Plain First Nation - Water Treatment Plant Upgrades
Long Plain First Nation -
Roseau River AFN Riverbank Stabilization Project
Roseau River AFN Riverbank Stabilization Project -
Roseau River Anishinaabe First Nation Waste Transfer Station
Roseau River Anishinaabe First Nation -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake Manitoba Outlet Channel outlet on Lake St. Martin -
Dakota Women's Lodge (Winyan Tipi)
Portage la Prairie -
Xplornet Communications Inc. - XCS - Antenna Structure - Piney Port Border Crossing, Hwy 89, Piney Port, MB
Piney Port Border Crossing -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake St. Martin Outlet Channel outlet on Lake Winnipeg -
Pauingassi First Nation Child and Family Services Prevention Building and Staff Housing
Pauingassi First Nation -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake St. Martin Outlet Channel inlet on Lake St. Martin -
South Junction Port of Entry Redevelopment
South Junction Port of Entry -
Chief Elsie Bouchie Culture Camp
Pigeon River 13A -
McBeth Point Harbour Improvements
McBeth Point Harbour -
Great Bear Gold Project
23 kilometres southeast of Red Lake -
Great Bear Advanced Exploration Project
25 kilometres southeast of Red Lake -
Dauphin River Harbour Manitoba - Routine Maintenance Dredging of the Dauphin River at Lake Winnipeg - Winter 2019
Dauphin River Harbour -
Dauphin River Small Craft Harbour Dredging and Pile Installation
Dauphin River Small Craft Harbour -
Lake St. Martin - Water Treatment Plant Zebra Mussels Control
Lake St. Martin -
New Fibre Installation - Dauphin River
Project site 1: Anama Bay -
Sprague Port of Entry Redevelopment
Sprague Port of Entry -
Project 4 - All-Season Road Connecting Berens River to Poplar River First Nation
East side of Lake Winnipeg, between Poplar and Berens Rivers -
Addition to Buffalo Point First Nation Radiocommunication Tower at Buffalo Point, MB.
Buffalo Point, MB -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 5: BCN-BRR-TW2 -
Ebb and Flow First Nation - Road and Drainage Upgrades
Ebb and Flow First Nation -
Berens River Bridge Replacement
Berens River First Nation -
Berens River First Nation Road Upgrades
Berens River -
Berens River Water Treatment Plant Upgrade
Berens River First Nation -
Xplornet Inc. Radiocommunication Antenna Addition on Ebb and Flow First Nation Reserve No. 280
Ebb and Flow First Nation Reserve No. 280 -
New Tower Construction, Upgrade single tower & New Fibre Installation
Project site 3: Berens River 13 -
New (Multiple) Tower Construction or Upgrade & New Fibre Installation
Project site 4: BCN-BRR-TW1 -
CSC97 - Ebb and Flow First Nation Water Supply Line Project
Ebb and Flow First Nation -
Harbour Improvements - Berens River - Sigurdsson Island, MB
Berens River -
Berens River Harbour Launch Ramp Reconstruction
Berens River Small Craft Harbours -
Pinaymootang First Nation Water Treatment Upgrades
Pinaymootang First Nation -
New Fibre Installation - Dauphin River
Project site 2: Obushkudayang Indian Reserve -
Berens River Small Craft Harbour Breakwater Repairs and Pile Installation
Berens River - Sigurdsson Island Small Craft Harbour