Little Pine First Nation Lagoon Upgrade and Bridge over Battle River
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The project will include the construction of a new sewage lagoon , including common excavation, synthetic liner, and transfer piping. The lagoon will be design and constructed to meet the 10 year design horizon, with practical considerations to allow for easy expansion to meet the 20 year design horizon, when appropriate. Lagoon sizing is 3.45ha primary cell; 95,100 cubic meter storage cell. The project will include a 200mm sewage forcemain of approximately 3,300 lin. m. in length. Sewage pumping station upgrades include new sewage pumps, piping and a sewage grinder. The project will include approximately 3,300 lin. m. of access road construction and bridge construction will take place in Section 31, Township 45, Range 21 W3. Road width of 7m with gravel surface.
Lagoon construction will take place in portion of NW6 - TWP46 - Rng 21- W3M.Sewage force main will be in portion of, NW31 - 45 - 21 - W3M, NW31 - 45 - 21 - W3M, SE6 - 46 - 21 - W3M and NW6 - 46 - 21 - W3M. All parcels were previously disturbed by farming activities.
New and permanent infrastructure will include the new sewage force main and sewage treatment lagoon. Activities include feasibility study, design, tender, construction operation and maintenance. Waste generation is expected to be minimal for this project. Waste generation to include typical construction waste. Waste will be collected in transportation bins and hauled to the nearest regional landfill.
Force main crossing to be completed by horizontal directional drilling under Battle River. Fisheries permit is not required for directional drilling, and proponent confirms that all mitigation measures noted here will be followed: http://www.dfo-mpo.gc.ca/pnw-ppe/measures-mesures-eng.html
Latest update
.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 3 | Notice of Determination for Little Pine First Nation Lagoon Upgrade and Bridge over Battle River | - | February 17, 2023 |
| 2 | Public Comment Period on Intent to Make a Determination | - | November 23, 2022 |
| 1 | Public Comment Period on Intent to Make a Determination | - | July 7, 2022 |
Contacts
ISC-SKENVIndigenous Services Canada
Alvin Hamilton Building, 1783 Hamilton Street
Regina, Saskatchewan S4P 2B6
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Little Pine IR No. 116 (Saskatchewan)
-
Nature of Activity
- Water Management
- Waste Management
-
Assessment Status
Completed -
Start Date
2022-07-07 -
Proponent
Little Pine First Nation -
Authorities
- Indigenous Services Canada
- Transport Canada
-
Assessment Type
Project on federal lands -
Reference Number
83776
Nearby assessments
...within 200 kilometres-
Great Sandhills Railway Switching Operation at North West Terminal Project - Revised Design
1 kilometre east of Unity, Saskatchewan -
Great Sandhills Railway Switching Operation at North West Terminal Project
1 kilometre east of Unity -
New Towers Construction, Upgrade single tower & New Fibre Installation
Project Site 1: West Central region - Sweetgrass -
Sweetgrass New School
Sweetgrass IR 113 -
Sweetgrass Daycare and Early Learning Head Start Centre Project
Saskatoon -
Sweetgrass First Nation Wastewater System Upgrades
Sweetgrass First Nation -
Poundmaker Cree Nation Lagoon Upgrades
Poundmaker Indian Reserve No. 114 -
Poundmaker Cree Nation New Bridge Construction
Poundmaker Indian Reserve No. 114 -
Little Pine First Nation Health Clinic
Little Pine Indian Reserve No. 116 -
Mosquito First Nation Lagoon Upgrades
Mosquito First Nation -
Mosquito Grizzly Bear's Head Lean Man First Nation - Core Area Subdivision
Mosquito Grizzly Bear's Head Lean Man First Nation -
Red Pheasant Cree Nation - Eagle Landing Development
Red Pheasant Reserve No. 108 -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Kerrobert -
Moosomin Road Repair and Drainage
Moosomin IR No. 112B -
Saulteaux First Nation Subdivision Development
Saulteaux Indian Reserve No. 159 -
Saulteaux First Nation Firehall and Vehicle Storage Facility
Saulteaux Indian Reserve Number 159 -
Saulteaux Fire Hall / Maintenance Facility
Saulteaux IR 159 -
Thunderchild First Nation Lagoon Upgrade
Thunderchild IR115B -
Thunderchild First Nation - Solid Waste Transfer Station
Thunderchild IR115B & 115C -
Thunderchild First Nation - Turtle Lake Site 115C WTP Process Waste Pond
Thunderchild IR 115C -
Thunderchild First Nation Firehall
Thunderchild First Nation Indian Reserve No. 115B -
Thunderchild First Nation Powwow Arbor
THUNDERCHILD FIRST NATION 115B -
New Towers Construction, Upgrade single tower & New Fibre Installation
Project Site 3: West Central region - Thunderchild -
Thunderchild Community Walking Trail
Thunderchild First Nation -
Thunderchild First Nation Water Treatment Plant and Well Upgrades
THUNDERCHILD FIRST NATION 115B -
Thunderchild Wellness Centre
Thunderchild Wellness Centre -
Thunderchild First Nation New Subdivision
THUNDERCHILD FIRST NATION INDIAN RESERVE NO. 115B -
GL7 Phase 1 Transmission Rebuild Project (L007) / Saulteaux and Moosomin First Nations
Saulteaux IR 159G & Moosomin IR 112L -
SaskPower - 2E-33 Mullingar Rural Rebuild
Mosquito Grizzly Bear's Head Lean Man TLE Indian Reserve -
Building Foundation Removal and Site Restoration in Lost Farm Area at 3CDSB Wainwright
The Range Training Area (RTA) at Detachment Wainwright -
New Fibre Installation, Upgrade (Single) Tower
Moonlight bay -
Thunderchild First Nation - Turtle Lake Site 115C Sewage Lagoon Operations
Thunderchild First Nation -
Saulteaux IR159 Timber Harvest Plan 2020-21
Saulteaux IR 159EE -
Saulteaux IR159 Timber Harvest Plan 2021-22
Saulteaux IR 159EE -
Electrical Power Upgrade for Building 650 (B650) at Garrison Wainwright
Garrison Wainwright (Denwood) -
Upgrade Railhead at Garrison Wainwright
Garrison Wainwright (Denwood) -
Reconfigure Power Distribution at the Exercise Control Site
CFB Suffield, Medicine Hat -
New Power Line Installation
CFB Suffield, Medicine Hat -
Upgrades to Roads within Administrative Area- Garrison Wainwright
Garrison Wainwright -
Skate Park Design-Build Project - Garrison Wainwright
Garrison Wainwright -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Building 633) -
Demolish Pre-Wash Facility - Garrison Wainwright
Garrison Wainwright -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Bulk parking lot) -
Front Gate Water Loop - Garrison Wainwright
Garrison Wainwright in Denwood -
Upgrade Main Petroleum Oils and Lubricants (POL) Facility at Garrison Wainwright
Garrison Wainwright in Denwood -
Construct Hazardous Waste Storage Facility - Garrison Wainwright
Garrison Wainwright -
Demolition of Tent City, Building 313 and Water Point - Garrison Wainwright
Garrison Wainwright -
Upgrade Water and Sewer Utilities to Building AW22 at Garrison Wainwright
Garrison Wainwright (Denwood) -
Upgrade Range 1 at Garrison Wainwright
Garrison Wainwright in Denwood -
Provide Power to Troop Shelters at Garrison Wainwright
Garrison Wainwright (Denwood) -
Construct Building for Ammunition Salvage at Garrison Wainwright
Garrison Wainwright -
Remedial activities at a site impacted by Aqueous Film Forming Foam (AFFF) - Garrison Wainwright
Garrison Wainwright -
Install Cattle Watering Line in the Range and Training Area - Garrison Wainwright
Garrison Wainwright -
Lucky Man Cree Nation Access Road Design and Construction
Lucky Man Reserve -
Lucky Man Cree Nation Community Access Road
LUCKY MAN RESERVE -
Construct Sniper Range at Garrison Wainwright
Garrison Wainwright (Denwood) -
Upgrades to Range 8 - Garrison Wainwright
Garrison Wainwright -
Onion Lake Family Services Inc. Child and Family Services Building
Onion Lake First Nation -
Install New Trailer Complex at P12 at Garrison Wainwright
Garrison Wainwright (near Denwood) -
Onion Lake Cree Nation Aquatic Centre Project
Onion Lake Cree Nation Aquatic Centre Project -
Lloydminster Region Abandonment Project
Makaoo Indian Reserve 120 (Onion Lake Cree Nation) -
RW-4851 Authorization to Construct and Operate a Right of Way for a gas pipeline
Frog Lake First Nation -
Battle River Pumphouse Replacement - Garrison Wainwright
Garrison Wainwright -
Witchekan Lake Subdivision
Witchekan Lake IR 161 -
Witchekan Lake First Nation Solid Waste Transfer Station
Witchekan Lake First Nation -
Witchekan Lake First Nation Sweat Lodge
Witchekan Lake Indian Reserve No. 117 -
Witchekan Lake First Nation Cultural Centre
Witchekan Lake Indian Reserve No. 117 -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Building 750) -
Stabilize Temporary Bridge Abutments - Garrison Wainwright
Garrison Wainwright -
Demolition of Building 598 - Canadian Forces Base Wainwright
Canadian Forces Base Wainwright -
Upgrade of Main Refueling Station at Canadian Forces Base Wainwright (Alberta)
CFB Wainwright -
Demolition of Building 27 - Canadian Forces Base Wainwright
Canadian Forces Base Wainwright -
Demolish and Upgrade Vertical Village - Garrison Wainwright
Garrison Wainwright -
Pelican Lake Community Harvest Program Phase 2022-2024
Chitek Lake IR 191 -
Hardisty Rail Terminal Project
10 km southeast of Hardisty -
Food Sovereignty Project- Bison and Elk Farms, and Community Gardens
Pelican Lake First Nation, near Leoville -
New Fibre Installation - Central and Southeastern SK
Project site 5: MUSKEG LAKE I.R. 102 -
Pelican Lake Child and Family Services Facility
Pelican Lake First Nation -
Pelican Lake First Nation Subdivision
CHITEK LAKE INDIAN RESERVE NO. 191 -
Pelican Lake First Nation - Quonset Addition
Chitek Lake IR 191 -
Construction of a Royal Canadian Mounted Police Detachment in Vermilion, Alberta
Vermilion -
Potential Regional Assessment of a Western Energy Corridor
near Vermilion -
Energy East Project
Hardisty -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Hardisty -
Pelican Lake First Nation 191 A, B, C, D Gasification Project
Pelican Lake First Nation 191 A, B, C, D -
Pelican Lake Farms - farm site development
Pelican Lake IR 191-B -
Onion Lake 3D 2026 Seismic Program
Onion Lake 3D 2026 Seismic Program -
Pelican Lake Bioenergy Project
Pelican Lake First Nation -
Pelican Lake North Sewage Lagoon Expansion and Upgrades
Chitek Lake IR 191 -
Pelican Lake Timber Harvesting Plan 2021-22
Chitek Lake IR 191 & 191A -
Pelican Lake Timber Harvesting Plan
Chitek Lake IR 191 -
Big River First Nation Reserve Drainage Re-Establishment
Big River First Nation -
Trench Removal and Site Restoration in C1 area at CFB Wainwright
The Range Training Area (RTA) at Detachment Wainwright -
Upgrade Single Tower & New Fibre Installation
Project site 2: North East region - Chamakese Resort (Chitek Lake) -
Walk Into History
Chitek Lake -
Upgrade Single Tower & New Fibre Installation
Project site 5: North East region - Mistawasis -
Mistawasis Nêhiyawak Lake - Traditional Lands, Gathering Space
Mistawasis Nêhiyawak Lake -
Mistawasis Nêhiyawak Community Center
Mistawasis -
Kahkewistahaw Landing Infrastructure Construction
Kahkewistahaw IR 72A - 2 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 3) -
General Aviation Hangars Development
Saskatoon International Airport YXE -
Apron III infill
Saskatoon International Airport YXE -
Nutrien Aviation Hangar Expansion
STARS Saskatoon Base -
Kahkewistahaw First Nation - Mamawi Business Center
Kahkewistahaw No. 72A -
Mistawasis Nehiyawak Rural Transit Solutions
Mistawasis -
45th & Airport Holdings Ltd. Restaurant and Gas Station Commercial Development
Restaurant/Gas Station Commercial Development -
Saskatchewan Indian Institute of Technologies Hangar Expansion
Saskatchewan Indian Institute of Technologies -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 2) -
Saskatoon Airport Solar - 1MW Project
1MW Ground Mounted Solar Facility -
Makwa Sahgaiehcan First Nation Well Completion
Makwa Sahgaiehcan First Nation -
Ahtahkakoop Cree Nation New School
AHTAHKAKOOP INDIAN RESERVE NO. 104 -
Ahtahkakoop Cree Nation Lagoon and Sewage Pumping Station
Ahtahkakoop IR #104 -
Mistawasis Nehiyawak Lagoon Upgrades
Mistawasis Nêhiyawak -
SaskPower HR-01033 - RPD-511 PQ Rural Rebuild (Makwa Rebuild)
Makwa First Nation -
New Fibre Installation - Central and Southeastern SK
Project site 7: AHTAHKAKOOP I.R. 104 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 1) -
Cree Nation Treatment Haven Replacement
Ahtakakoop First Nation -
Frog Lake Waskonaman Hill Gravel Project (Amendment)
Frog Lake First Nation -
Ahtahkakoop Cree Nation Water Treatment Plant
Ahtahkakoop IR 104 -
Makwa Sahgaiehcan First Nation Transfer Station
Makwa Sahgaiehcan First Nation -
Muskeg Lake Cree Nation - Construction of commercial/retail building
ASIMAKANISEEKAN ASKIY 102A -
OS-7250 Authorization to Construct and Operate a Surface Lease for an access road and a multi-well pad
Frog Lake First Nation -
Makwa Lake Resort Development
Makwa Lake Indian Reserve No. 129B -
OS-6826 Authorization to extend an existing surface lease area for a multi-well pad
Frog Lake First Nation -
OS-7257 Authorization to construct and operate a surface lease for an access road and for a multi-well oil pad
Frog Lake First Nation -
OS-7262 Authorization to Construct and Operate a Surface Lease for a multiwell oil pad
Frog Lake First Nation -
OS-6825 Authorization to Construct an access road and a Surface Lease Extension and Operate a Multi-well oil pad
OS-6825 -
Lac La Ronge Morin Lake Solid Waste Transfer Station & Decommissioning
Morin Lake IR 217 -
Frog Lake First Nation 4 Unit Housing Project
Frog Lake First Nation -
Lac Eauclaire Timber Harvest Program
Pelican Lake IR 191-C -
Regional Psychiatric Centre - Removal of an Underground Storage Tank
Regional Psychiatric Centre -
New Fibre Installation - Central and Southeastern SK
Project site 4: Big River 118 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161A -
Big River First Nation Drainage Reestablishment Phase 1B
BIG RIVER INDIAN RESERVE NO. 118 -
Frog Lake CFS Equine Centre
Frog Lake -
Mistahi Sipiy Child and Family Service and Big River First Nation Prevention Building
Big River First Nation -
Big River First Nation Arena Build Project
Big River IR 118 -
Ahtahkakoop Powwow Grounds & Access Road
Ahtahkakoop Cree Nation -
Construction and Installation of a Clear Span Acrow Panel Bridge at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 3) -
Whitecap Dakota First Nation Community Drainage
Whitecap Dakota First Nation No 94 -
Ahtahkakoop Cree Nation Debden Road Upgrades
AHTAHKAKOOP INDIAN RESERVE NO. 104 -
125 Aspen Place Infrastructure & New Building Construction Project
125 Aspen Place, Saskatoon -
Ministikwan Subdivision Development
Ministikwan IR 161 -
Whitecap Dakota First Nation Subdivision Stage 4
NE 35-33-6 W3M -
Buffalo Berry Culvert Work
Whitecap IR #94 -
Whitecap Dakota First Nation Sewage Pumping Station 3
Whitecap Dakota First Nation No 94 -
Ministikwan Lake Cree Nation - Solid Waste Transfer Station
Ministikwan IR161 -
Whitecap Dakota First Nation Multi-Use Trails
Whitecap Dakota First Nation Multi-Use Trails -
Whitecap Dakota Nation Water Treatment Plant Upgrade & Wells Project
Whitecap Dakota First Nation No 94 -
Dakota Springs Spa
Whitecap IR #94 -
Whitecap Dakota Nation Virtual Health Hub
Whitecap Dakota First Nation No 94 -
Whitecap Dakota Nation Wellbeing Centre
Whitecap No. 94 -
North Creek Trail Realignment
17 Wing Detachment - Dundurn's Range and Training Area -
Woods Trail Bridge Replacement and Water Course Alteration – 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
OS-6634 Authorization to extend an existing surface lease area for a multi-well pad
Frog Lake First Nation -
OS-6870 Authorization to extend an existing surface lease area for a multi-well pad
Frog Lake First Nation -
Flying Dust Commercial Project
Meadow Lake -
Upgrade Woods Trail - 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
OS-7251 Authorization to Construct and Operate a Surface Lease for an access road and a multi-well pad
Frog Lake First Nation -
OS-7259 Authorization to construct and operate a surface lease for a multi-well oil pad
Frog Lake First Nation -
OS-7268 Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell oil pad.
Frog Lake First Nation -
OS-6908 Authorization to Construct and Operate a Surface Lease
Frog Lake First Nation -
OS-6870 Authorization to extend an existing surface lease area for a multi-well pad
Frog Lake First Nation -
Frog Lake First Nation Water System Project
Frog Lake First Nation -
Flying Dust First Nation Railway Infrastructure Development Project
Flying Dust First Nation Indian Reserve No. 105 -
Flying Dust First Nation Residential Subdivision Development
Flying Dust First Nation Indian Reserve No. 105 -
OS-6891 Authorization to Construct and Operate a Surface Lease
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
EAGLES LAKE I.R. 165C -
Frog Lake First Nation Water System Project
Frog Lake First Nation -
OS-7270 Authorization to Construct and Operate a Surface Lease for an access road and a multiwell oil pad, with a temporary log deck
Frog Lake First Nation -
Frog Lake Waste Management Transfer Station
Frog Lake First Nation -
Fishing Lake First Nation Sewage Pumping Station Upgrades
Fishing Lake First Nation -
OS-7267 Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell oil pad
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WATERHEN I.R. 130 -
OS-7260 Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell oil pad
Frog Lake First Nation -
OS-7269 Authorization to Construct and Operate a Surface Lease for an access road and a multiwell oil pad, with a temporary log deck
Frog Lake First Nation -
OS-7265 Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell oil pad
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 1 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 2) -
EX-9999 Authorization for a 3D seismic exploration program for oil and gas development
Frog Lake First Nation -
Frog Lake First Nation Landfill Cap Construction
Frog Lake First Nation -
Flying Dust First Nation Regional Landfill
Flying Dust IR 105 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 1) -
Flying Dust - New Water Treatment Plant
Flying Dust IR 105 -
OS-7266 Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell oil pad
Frog Lake First Nation -
Ahtahkakoop South Subdivision Phase 1
Ahtakakoop Cree Nation -
Beardy's and Okemasis Cree Nation Solid Waste Removal and Landfill Decommissioning
Beardy's and Okemasis Cree Nation -
Woods Trail Intersection Realignment
17 Wing Detachment Dundurn's Range and Training Area -
Magazine Area Recapitalization Canadian Forces Ammunition Depot (CFAD) - 17 Wing Detachment Dundurn
Canadian Forces Ammunition Depot Dundurn,17 Wing Detachment Dundurn -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Point of presence -
Beardy's and Okemasis Cree Nation Water Treatment Plant Upgrades Project
Beardy's and Okemasis Cree Nation -
OS-7261 Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell oil pad
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 2 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 3 -
Install Security Fence along Pryor Road at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Replacement of the Fuel Transfer Station and Fuel Tank Systems
17 Wing Detachment Dundurn -
Beardy's & Okemasis Cree Nation Stage 4 Subdivision
Beardy's & Okemasis Cree Nation -
OS-7263 Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell oil pad
Frog Lake First Nation -
Ministikwan Community Road Repairs
Ministikwan Lake Cree Nation -
OS-7264 Authorization to Construct and Operate a Surface Lease for multiwell oil pad
Frog Lake First Nation -
Gas Station Construction Saskatoon
Kahkewistahaw Indian Reserve No. 72A-2 -
Grasswoods Reserve Septage Receiving Station, Retention Pond and Final Disposal to City of Saskatoon Forcemain
Grasswoods IR 192J -
Willow Cree Healing Lodge - Construction of Ready to Move (RTM) Buildings
Willow Cree Healing Lodge -
Beardy's & Okemasis Cree Nation Sewage Lagoon and Pumping Station Upgrades
Beardy's and Okemasis IR No. 96 & 97 -
Witchekan Lake First Nation Youth Lodge
Witchekan Lake Indian Reserve No. 117 -
Beaver dam and lodge removal
Prince Albert National Park -
New Fibre Installation - Central and Southeastern SK
Project site 3: One Arrow 95-1A -
Construction of Two Bridge Files in Saddle Lake Cree Nation
Construction of Two Bridge Files in Saddle Lake Cree Nation -
Batoche Drainage Improvement
Grasslands National Park -
Fuel Reduction Program for Batoche National Historic Site
Batoche National Historic Site