Fishing Lake First Nation Sewage Pumping Station Upgrades
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Fishing Lake First Nation is proposing to upgrade the sewage pumping station servicing the community. The existing core sewage pumping station in Fishing Lake First Nation is undersized, causing damage to residential housing in the area via sewage backups. This project is in conjunction with the Fishing Lake Lagoon upgrade project to upgrade the waste water infrastructure in the community. The project will include the excavation and construction of a new wet dry sewage pumping station close in proximity to the existing sewage pumping station. The station is anticipated to have a life span of over 20+ years. Th new sewage pumping station will be built on a concrete foundation to store pumps, mechanical and electrical hardware and is designed to store and pump sewage to the facultative lagoon located on SW 1/4 Sec 15 TP 33 R12 W3. The project also includes the replacement of the existing 100mm dia. sewage forcemain with a 200mm dia. sewage forcemain. Approximately 2000m of sewage force main will be installed in the same right of way as the existing main to the lagoon via excavation and directional drilling.
Decommissioning of the existing sewage pumping station will be completed after commissioning the new system. Installation of ~2000 meters if HDPE sewage forcemain, via excavation and directional drilling. General construction waste, to be disposed off-site on an approved landfill.
Latest update
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 2 | Notice of Determination for the Fishing Lake Sewage Pumping System Upgrade | - | March 25, 2024 |
| 1 | Notice of Intent -Start of Public Comment Period | - | February 23, 2024 |
Contacts
ISC-SKENVIndigenous Services Canada
Alvin Hamilton Building, 1783 Hamilton Street
Regina, Saskatchewan S4P 2B6
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Fishing Lake First Nation (Saskatchewan)
-
Nature of Activity
- Waste Management
-
Assessment Status
Completed -
Start Date
2024-02-23 -
Proponent
Fishing Lake First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
87363
Nearby assessments
...within 200 kilometres-
Magazine Area Recapitalization Canadian Forces Ammunition Depot (CFAD) - 17 Wing Detachment Dundurn
Canadian Forces Ammunition Depot Dundurn,17 Wing Detachment Dundurn -
Woods Trail Intersection Realignment
17 Wing Detachment Dundurn's Range and Training Area -
Upgrade Woods Trail - 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Install Security Fence along Pryor Road at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Replacement of the Fuel Transfer Station and Fuel Tank Systems
17 Wing Detachment Dundurn -
Whitecap Dakota Nation Wellbeing Centre
Whitecap No. 94 -
Whitecap Dakota Nation Virtual Health Hub
Whitecap Dakota First Nation No 94 -
Whitecap Dakota Nation Water Treatment Plant Upgrade & Wells Project
Whitecap Dakota First Nation No 94 -
Dakota Springs Spa
Whitecap IR #94 -
Whitecap Dakota First Nation Multi-Use Trails
Whitecap Dakota First Nation Multi-Use Trails -
Whitecap Dakota First Nation Sewage Pumping Station 3
Whitecap Dakota First Nation No 94 -
Whitecap Dakota First Nation Subdivision Stage 4
NE 35-33-6 W3M -
Buffalo Berry Culvert Work
Whitecap IR #94 -
Whitecap Dakota First Nation Community Drainage
Whitecap Dakota First Nation No 94 -
Woods Trail Bridge Replacement and Water Course Alteration – 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
North Creek Trail Realignment
17 Wing Detachment - Dundurn's Range and Training Area -
Construction and Installation of a Clear Span Acrow Panel Bridge at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Grasswoods Reserve Septage Receiving Station, Retention Pond and Final Disposal to City of Saskatoon Forcemain
Grasswoods IR 192J -
Gas Station Construction Saskatoon
Kahkewistahaw Indian Reserve No. 72A-2 -
125 Aspen Place Infrastructure & New Building Construction Project
125 Aspen Place, Saskatoon -
Muskeg Lake Cree Nation - Construction of commercial/retail building
ASIMAKANISEEKAN ASKIY 102A -
Kahkewistahaw First Nation - Mamawi Business Center
Kahkewistahaw No. 72A -
Regional Psychiatric Centre - Removal of an Underground Storage Tank
Regional Psychiatric Centre -
Kahkewistahaw Landing Infrastructure Construction
Kahkewistahaw IR 72A - 2 -
45th & Airport Holdings Ltd. Restaurant and Gas Station Commercial Development
Restaurant/Gas Station Commercial Development -
Nutrien Aviation Hangar Expansion
STARS Saskatoon Base -
Saskatchewan Indian Institute of Technologies Hangar Expansion
Saskatchewan Indian Institute of Technologies -
Apron III infill
Saskatoon International Airport YXE -
General Aviation Hangars Development
Saskatoon International Airport YXE -
Saskatoon Airport Solar - 1MW Project
1MW Ground Mounted Solar Facility -
Beardy's & Okemasis Cree Nation Sewage Lagoon and Pumping Station Upgrades
Beardy's and Okemasis IR No. 96 & 97 -
Lake Diefenbaker Irrigation Expansion Projects
Lake Diefenbaker -
Aspen Power Station Project
Lanigan -
New Fibre Installation - Central and Southeastern SK
Project site 3: One Arrow 95-1A -
Remediation of One Arrow First Nation River Lot 62
One Arrow IR 95 -
Batoche Drainage Improvement
Grasslands National Park -
Fuel Reduction Program for Batoche National Historic Site
Batoche National Historic Site -
Beardy's and Okemasis Cree Nation Solid Waste Removal and Landfill Decommissioning
Beardy's and Okemasis Cree Nation -
Last Mountain Lake National Wildlife Area Water Control Structure Re-naturalization Project
Last Mountain Lake National Wildlife Area -
Stalwart National Wildlife Area Water Control Structure Re-naturalization Project
Stalwart National Wildlife Area -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 1 -
Willow Cree Healing Lodge - Construction of Ready to Move (RTM) Buildings
Willow Cree Healing Lodge -
Last Mountain Lake National Wildlife Area Observation Tower II
Last Mountain Lake National Wildlife Area -
Beardy's and Okemasis Cree Nation Water Treatment Plant Upgrades Project
Beardy's and Okemasis Cree Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 2 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 3 -
Upgrade Single Tower & New Fibre Installation
Project site 3: North East region - One Arrow -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Point of presence -
Beardy's & Okemasis Cree Nation Stage 4 Subdivision
Beardy's & Okemasis Cree Nation -
New Fibre Installation - Central and Southeastern SK
Project site 5: MUSKEG LAKE I.R. 102 -
Tway National Wildlife Area Water Control Structure Re-naturalization Project.
Tway National Wildlife Area -
Mosquito Grizzly Bear's Head Lean Man First Nation - Core Area Subdivision
Mosquito Grizzly Bear's Head Lean Man First Nation -
Lucky Man Cree Nation Community Access Road
LUCKY MAN RESERVE -
Lucky Man Cree Nation Access Road Design and Construction
Lucky Man Reserve -
Mosquito First Nation Lagoon Upgrades
Mosquito First Nation -
Mistawasis Nêhiyawak Community Center
Mistawasis -
Upgrade Single Tower & New Fibre Installation
Project site 5: North East region - Mistawasis -
Mistawasis Nehiyawak Rural Transit Solutions
Mistawasis -
Mistawasis Nehiyawak Lagoon Upgrades
Mistawasis Nêhiyawak -
Mistawasis Nêhiyawak Lake - Traditional Lands, Gathering Space
Mistawasis Nêhiyawak Lake -
SaskPower - 2E-33 Mullingar Rural Rebuild
Mosquito Grizzly Bear's Head Lean Man TLE Indian Reserve -
Red Pheasant Cree Nation - Eagle Landing Development
Red Pheasant Reserve No. 108 -
Peter Ballantyne Child and Family Services Facility
Kistapinin IR 211 -
Blanket Permit - SaskPower - Kistapinan Indian Reserve No.211
Kistapinan Indian Reserve No. 211 -
Muskoday First Nation Booster Station Upgrades
Muskoday First Nation -
New (Multiple) Tower Construction
Poject site 5: Kawacatoose FN I.r. 88 -
Muskoday First Nation - Construct Cultural Centre
Muskoday First Nation - Construct Cultural Centre -
New (Multiple) Tower Construction
Poject site 2: Kawacatoose FN I.r. 88 -
Muskoday First Nation - Community Access Road
Muskoday First Nation Reserve -
New (Multiple) Tower Construction
Poject site 1: Kawacatoose FN I.r. 88 -
Kawacatoose First Nation Water Treatment Plant Upgrade and Expansion
Kawacatoose IR 88 -
Muskoday First Nation - Drainage Improvements Phase 1
Muskoday First Nation Reserve -
New (Multiple) Tower Construction
Poject site 4: Kawacatoose FN I.r. 88 -
Muskoday First Nation Subdivision Development
Muskoday First Nation I.R. 99 -
Northern Lights Casino Expansion and Renovation
Northern Lights Indian Reserve No.220 -
Blanket Permit - SaskEnergy - Northern Lights Indian Reserve No. 220
Northern Lights Indian Reserve No. 220 -
Kistaphinanihk Office Building
Kistaphinanihk IR No. 231 -
New (Multiple) Tower Construction
Poject site 3: Kawacatoose FN I.r. 88 -
Peter Ballantyne Cree Nation Parcel E Development
CHIEF JOSEPH CUSTER RESERVE -
Parcel E Sublease - Eagle Ridge Residential Building
Parcel E of Chief Joseph Custer Reserve -
Peter Ballantyne Child and Family Services Inc. Central Office Extension
Chief Joseph Custer Reserve -
Prince Albert Administration Office Addition
Chief Joseph Custer Reserve -
Piapot First Nation Prince Albert Urban Gas Bar & Convenience Store
Piapot IR 75 -
Muskoday First Nation Sewage Lagoon Upgrade
Muskoday First Nation -
MEDA 324 kW Solar Farm
Muskoday IR 99 -
Sturgeon Lake First Nation - Renovation for gas bar and convenience store
Sturgeon Lake First Nation - Prince Albert Strip Mall -
Potential Regional Assessment of a Western Energy Corridor from Alberta to Manitoba
Prince Albert -
Potential Regional Assessment of a Western Energy Corridor
near Prince Albert -
New (Multiple) Tower Construction
Poject site 6: Kawacatoose FN I.r. 88 -
New (Multiple) Tower Construction
Poject site 7: Kawacatoose FN I.r. 88 -
Fenceline Replacement - Prince Albert Training Area, Saskatchewan
DND Prince Albert Training Area -
New (Multiple) Tower Construction
Poject site 8: Kawacatoose FN I.r. 88 -
Wahpeton Roads Upgrades
Wahpeton Dakota Nation -
Wahpeton Dakota Nation Sewage Lagoon Expansion
WAHPATON INDIAN RESERVE NO. 94A -
Wahpeton Dakota Nation New School
Wahpeton Dakota Nation -
New Fibre Installation - Central and Southeastern SK
Project site 8: WAHPATON I.R. 94A -
New Fibre Installation - Central and Southeastern SK
Project site 2: Wahpaton 94A -
Yuasni Tipi Lodge Lease
Wahpeton Dakota Nation -
Big River First Nation Reserve Drainage Re-Establishment
Big River First Nation -
Kawacatoose First Nation Subdivision
Kawacatoose IR 88 -
Ahtahkakoop Cree Nation New School
AHTAHKAKOOP INDIAN RESERVE NO. 104 -
Ahtahkakoop Cree Nation Water Treatment Plant
Ahtahkakoop IR 104 -
New Fibre Installation - Central and Southeastern SK
Project site 7: AHTAHKAKOOP I.R. 104 -
Ahtahkakoop Cree Nation Lagoon and Sewage Pumping Station
Ahtahkakoop IR #104 -
Cree Nation Treatment Haven Replacement
Ahtakakoop First Nation -
George Gordon First Nation Fire Hall
George Gordon First Nation -
Ahtahkakoop Powwow Grounds & Access Road
Ahtahkakoop Cree Nation -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Kerrobert -
Beaver dam and lodge removal
Prince Albert National Park -
George Gordon First Nation Lagoon Upgrades
Gordon 86 Indian Reserve -
George Gordon First Nation Wastewater Infrastructure Upgrades
Gordon 86 Indian Reserve -
Multi-use Front Lake Community Walking Path
Multi-use Front Lake Community Walking Path -
Sturgeon Lake First Nation Child and Family Service Centre
STURGEON LAKE INDIAN RESERVE NO. 101 -
On Hold - Aggregate Business Development Plan - Phase 2, Sturgeon Lake First Nation I.R. 101
Sturgeon Lake IR 101 -
Sturgeon Lake First Nation Children's Playgrounds
Park location 1 -
Kapasiwin Bungalows Installation of Deep Water and Sewer Infrastructure
Prince Albert National Park -
Blanket Permit - SaskEnergy - Gasification of Sturgeon Lake Indian Reserve No. 101
Sturgeon Lake Indian Reserve No. 101 -
Sweetgrass New School
Sweetgrass IR 113 -
Sweetgrass Daycare and Early Learning Head Start Centre Project
Saskatoon -
Sturgeon Lake First Nation Children's Playgrounds
Park location 2 -
Sweetgrass First Nation Wastewater System Upgrades
Sweetgrass First Nation -
Oskâyak Miyoayâwin Youth Learning Centre
STURGEON LAKE INDIAN RESERVE NO. 101 -
Phase 2 - Sturgeon Lake First Nation Active Transportation Network
Phase 2 - Sturgeon Lake First Nation Active Transportation Network -
Sturgeon Lake First Nation - East Lagoon Expansion
Sturgeon Lake IR 101 -
New Towers Construction, Upgrade single tower & New Fibre Installation
Project Site 1: West Central region - Sweetgrass -
Ahtahkakoop Cree Nation Debden Road Upgrades
AHTAHKAKOOP INDIAN RESERVE NO. 104 -
Sturgeon Lake First Nation Subdivision
Sturgeon Lake IR 101A -
Moosomin Road Repair and Drainage
Moosomin IR No. 112B -
Sturgeon Lake First Nation Children's Playgrounds
Park location 3 -
Upgrade Single Tower & New Fibre Installation
Project site 6: North East region - Sturgeon Lake -
Sturgeon River Pedestrian Bridge
Sturgeon Lake Indian Reservation No.101 -
Saulteaux First Nation Subdivision Development
Saulteaux Indian Reserve No. 159 -
Moose Jaw Combined Cycle Power Station Project
Moose Jaw -
Little Pine First Nation Lagoon Upgrade and Bridge over Battle River
Little Pine IR No. 116 -
James Smith Cree Nation Solid Waste Transfer Station
James Smith Cree Nation -
Relocate RV Compound - 15 Wing Moose Jaw
15 Wing Moose Jaw -
Kinistin Saulteaux Nation Barrier River Bridge Replacement
Kinistin Saulteaux Nation -
Great Sandhills Railway Switching Operation at North West Terminal Project
1 kilometre east of Unity -
James Smith Cree Nation Headstart and Daycare
JAMES SMITH INDIAN RESERVE NO. 100 -
Great Sandhills Railway Switching Operation at North West Terminal Project - Revised Design
1 kilometre east of Unity, Saskatchewan -
Tower Alteration for James Smith Cree Nation Justice & Policing communication system on James Smith Reserve No. 100
James Smith Cree Nation -
Saulteaux First Nation Firehall and Vehicle Storage Facility
Saulteaux Indian Reserve Number 159 -
Saulteaux Fire Hall / Maintenance Facility
Saulteaux IR 159 -
Upgrade Single Tower & New Fibre Installation
Project site 8: Central East region - James Smith -
Water Distribution Network Replacement and Storm and Sanitary Network Rehabilitation at 15 Wing Moose Jaw
15 Wing Moose Jaw -
Construct North Access Road - 15 Wing Moose Jaw
15 Wing Moose Jaw -
Remediate Sites and Construct Buildings for Future Aircrew Training (FAcT) Program- 15 Wing Moose Jaw
15 Wing Moose Jaw -
Sanitary Force Main Pipeline Replacement Design and Construction - 15 Wing Moose Jaw
15 Wing Moose Jaw -
Runway Rehabilitation - 15 Wing Moose Jaw
15 Wing Moose Jaw -
James Smith Cree Nation Peonan Creek Crossing
James Smith Cree Nation -
James Smith Cree Nation Subdivision Stage 4
James Smith Cree Nation -
James Smith Miyo-Pimatisiwin Wellness Centre
JAMES SMITH INDIAN RESERVE NO. 100 -
Witchekan Lake First Nation Youth Lodge
Witchekan Lake Indian Reserve No. 117 -
Lac La Ronge Morin Lake Solid Waste Transfer Station & Decommissioning
Morin Lake IR 217 -
Muskowekwan First Nation Wastewater Infrastructure Upgrades
MUSKOWEKWAN INDIAN RESERVE NO. 85 -
SaskPower Pole Mount Transformer Replacement for Hawood
Prince Albert National Park -
Muskowekwan Lagoon & Sewage Pumping Station
Muskowekwan IR 85 -
Kinistin Solid Waste Transfer Station
Kinistin Saulteaux Nation -
Kinistin Saulteaux Nation Sewage Lagoon Expansion
Kinistin IR No. 91 -
Muskowekwan Potash Mine Project
Lestock -
Piapot First Nation Road to Community Wells
Piapot IR 75 -
Witchekan Lake Subdivision
Witchekan Lake IR 161 -
The Lac La Ronge Indian Band Little Red River Water Upgrades
LITTLE RED RIVER 106C -
Muskowekwan Water Treatment Plant Upgrades
Muskowekwan IR 85 -
Muskowekwan Solid Waste Transfer Station
Muskowekwan IR 85 -
Muskowekwan Gas Bar & Convenience Store
Muskowekwan IR 85 -
New Fibre Installation - Central and Southeastern SK
Project site 4: Big River 118 -
Great Plains Generating Station Project
Northwest of Swift Current -
Chinook Power Station Project
Approximately 11 kilometres northwest of Swift Current -
Grazing Permits on Saskatchewan First Nations Reserve Lands
Saskatchewan First Nation Communities -
Agricultural permits on Saskatchewan First Nation Reserve Lands
Saskatchewan First Nations -
New Fibre Installation - Central and Southeastern SK
Project site 9: LITTLE RED RIVER I.R. 106C -
Zagime Anishinabëk RV Trailer Park
Sakimay IR 74 -
Upgrade Single Tower & New Fibre Installation
Project site 4: North East region - Montreal Lake -
Montreal Lake Cree Nation Little Red River Water Treatment Plant Upgrade Project
Montreal Lake Cree Nation -
Piapot Lagoon, Forcemain and Sewage Pumping Station
Piapot IR 75 -
Montreal Lake IR 106B Gasification
Montreal Lake IR 106B -
Montreal Lake Cree Nation & Little Red River Solid Waste Transfer Station & Decommissioning
Montreal Lake IR 106B -
On hold - Muskowekwan Wind Farm Project
Muskowekwan Indian Reserve 85-43, 85-49, 85-50, 85-63, 85-64, 85-65 -
Mistahi Sipiy Child and Family Service and Big River First Nation Prevention Building
Big River First Nation -
Big River First Nation Arena Build Project
Big River IR 118 -
Biocontrol of Yellow Toadflax using Rhinusa pilosa, in Prince Albert National Park
Prince Albert National Park -
Witchekan Lake First Nation Solid Waste Transfer Station
Witchekan Lake First Nation -
SaskPower Ground Mount Transformer Installation Red Deer Campground
Prince Albert National Park of Canada -
Poundmaker Cree Nation Lagoon Upgrades
Poundmaker Indian Reserve No. 114 -
SaskPower Poles Replacement in Prince Albert National Park near south west boundary.
Prince Albert National Park -
Witchekan Lake First Nation Cultural Centre
Witchekan Lake Indian Reserve No. 117 -
Hutterite Brethren Church of Twin Creek Inc. - Grazing Permit - Muskowekwan First Nation - 2019-2023
Muskowekwan 85-10 and 85-15 -
Witchekan Lake First Nation Sweat Lodge
Witchekan Lake Indian Reserve No. 117 -
Poundmaker Cree Nation New Bridge Construction
Poundmaker Indian Reserve No. 114 -
GL7 Phase 1 Transmission Rebuild Project (L007) / Saulteaux and Moosomin First Nations
Saulteaux IR 159G & Moosomin IR 112L -
Ahtahkakoop South Subdivision Phase 1
Ahtakakoop Cree Nation