Launchway Upgrades, Fleur de Lys, NL
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The proposed project involves upgrading an existing gravel boat launch to a precast concrete launchway. Work includes site preparation, removal of existing gravel surface as needed, grading and stabilization of the sub-base, placement and alignment of precast concrete panels, and restoration of surrounding areas to ensure safe and durable access for watercraft. Work will be completed from the existing shoreline using heavy equipment.
Latest update
September 10, 2025 – The Federal Authorities have issued their Notice of Determination after evaluation of the launchway upgrades at Fleur de Lys SCH and have determined that the project is not likely to cause significant adverse environmental effects and can therefore proceed.
This determination was based on a consideration of the following factors:
- Impacts on rights of Indigenous peoples;
- Community and Indigenous knowledge;
- Comments received from the public; and
- Technically and economically feasible mitigation measures.
Mitigation measures taken into account for this determination are:
- To minimize the possibility of fish habitat contamination and the spread of aquatic invasive (alien) species, all construction equipment which will be immersed into the water or has the possibility of coming into contact with such water during the course of the work, must be cleaned and washed to ensure that they are free of marine growth and alien species.
- Weather conditions are to be assessed on a daily basis to determine the risk of extreme weather in the project areas. Avoid work during periods which Environment and Climate Change Canada has issued rainfall, wind or wave warning for the work area.
- An Erosion and Sediment Control Plan will be developed for the site that minimizes risk of sedimentation to the marine environment.
- Ensure that all in-water activities, or associated in-water structures, do not interfere with fish passage.
- Wash, refuel and service machinery and store fuel and other materials for the machinery in such a way as to prevent any deleterious substances from entering the water.
- Construction material and debris are not to become waterborne. Do not dispose of any materials or waste into marine environment.
- All equipment to be used in or over the marine environment is to be free from leaks or coating of hydrocarbon-based fluids and/or lubricants harmful to the environment. Hoses and tanks are to be inspected on a regular basis to prevent fractures and breaks.
- On site, crews must have emergency spill clean-up equipment adequate for the activity involved, and it must be on site. Spill equipment will include, as a minimum, at least one 250 L (i.e., 55 gallon) overpack spill kit containing items to prevent a spill from spreading; absorbent booms, pillows, and mats; rubber gloves; and plastic disposal bags. All spills or leaks must be contained, cleaned up, and reported to the 24-Hour Environmental Emergencies Report System (1-800-563-9089).
- Ensure that waste is not left at the work site. All construction waste material will be disposed of in a provincially approved manner.
- Workers in contact with hazardous materials must be provided with and use appropriate personal protective equipment.
- Proper safety procedures must be followed throughout the duration of the project as per applicable municipal, provincial, and federal regulations.
- Dispose of and stabilize all excavated material above the ordinary high water mark or top of bank of nearby waterbodies and ensure sediment re-entry is prevented.
- Replace/restore any temporarily disturbed habitat features and remediate any areas impacted by the works, undertakings or activity.
- Sediment controls will be visually monitored throughout the life of the project, and repaired immediately if necessary.
- Any debris or waste material will be disposed of in a provincially approved manner.
- Dust control should be provided for construction activities and open soil areas, primarily by using fresh water.
- Work is to be carried out during hours agreed upon with the Departmental Representative to mitigate any disturbance to harbour users and residents.
.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 3 | Notice of Determination | - | September 10, 2025 |
| 2 | End of Public Comment Period | - | July 25, 2025 |
| 1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | June 25, 2025 |
Contacts
Fisheries and Oceans CanadaJim Fudge, Client Services Officer
4A Bayley St.
Building Bayley Building
St. John's, Newfoundland and Labrador A2A 2T5
Telephone: 709-486-4482
Email: Jim.Fudge@dfo-mpo.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- DFO SCH Site in Fleur de Lys, NL (DFRP #24299) (Newfoundland and Labrador)
-
Nature of Activity
- Ports and Harbours
-
Assessment Status
Completed -
Start Date
2025-06-25 -
Proponent
Fisheries and Oceans Canada - Small Craft Harbours (DFO-SCH) -
Authorities
- Fisheries and Oceans Canada
- Transport Canada
-
Assessment Type
Project on federal lands -
Reference Number
89668
Nearby assessments
...within 200 kilometres-
Point Rousse Port Expansion Project
Baie Verte -
Point Rousse Port Facility Project
Baie Verte -
Floating Dock Installation, Nippers Harbour, NL
The DFO-SCH project site is located in Nippers Harbour, Newfoundland. -
Floating Dock Installation, La Scie, NL
The DFO-SCH project site is located in La Scie, Newfoundland. -
Wharf Reconstruction, Westport, NL
Westport, Newfoundland -
Marginal Wharf Construction, Lushes Bight, NL
The DFO-SCH project site is located in Lushes Bight, Newfoundland. -
Fishway Reconstruction, Indian River, Springdale, NL
Indian River, Springdale, Newfoundland -
DFO-SCH Floating Dock Installation, Roberts Arm, NL
Roberts Arm -
Breakwater Construction, Barr'd Harbour, NL
Barr'd Harbour, Newfoundland -
Launchway Improvements, Port Au Choix, NL
Port aux Choix, Newfoundland -
Marginal Wharf Reconstruction, Port aux Choix, NL
Port aux Choix, Newfoundland -
DFO-SCH Boat Launchway Construction, Jenkins Cove (Twillingate), NL
Jenkins Cove -
Parking Lot Expansion at Twillingate SCH, NL
Twillingate SCH is located within the community of Twillingate, NL. The proposed project site is located on the northeastern side of the property, closest to the entrance. The project site is accessible via Main St. off of Route 340. -
Wharf Reconstruction, Phillip's Head, NL
Phillip's Head, Newfoundland -
Summer guided activities by business license holders for Gros Morne National Park
Gros Morne National Park -
Long Range Campsite Redevelopment
Gros Morne National Park of Canada -
Comfort Cove Floating Dock Installation
Comfort Cove SCH is located within the community of Comfort Cove, NL. The project site is accessible via Poplar Ave off of Route 343. -
Floating Dock Installation at Comfort Cove SCH, NL
The Comfort Cove SCH is located in the community of Comfort Cove-Newstead, Newfoundland. -
Lease Renewal - Lewisporte Marina
Lewisporte -
Exterior Upgrades to Facility - Lewisporte Detachment
Lewisporte -
Outfall Pipeline Extension, Lewisporte, NL
Lewisporte -
Deer Lake Very High Frequency Omni-directional Range (VOR) Replacement
Deer Lake -
Western Brook Bridge Replacement
Gros Morne National Park -
St. Barbe Ranges Replacement
St. Barbe -
Visitor Centre Recapitalization in Gros Morne National Park
Gros Morne National Park -
7Corners Installation Rocky Barachois
Gros Morne National Park of Canada -
Demolition of the Rappel Tower at Canadian Forces Base Beaumont Hamel Armoury, Grand Falls - Windsor, Newfoundland and Labrador
Beaumont Hamel Armoury is located off Memorial Avenue, on the western side of the Town of Grand Falls-Windsor -
Labrador-Island Transmission Link Project
Forteau -
Green Point Access Road Widening
Gros Morne National Park of Canada -
Environment and Climate Change Canada climate station relocation, Gros Morne National Park
Gros Morne National Park -
New Fibre Installation - Labrador Sea
Project site: Labrador Sea -
Lomond River Fishway Replacement
Lomond River -
Airport Surface Infrastructure Improvements, St. Anthony, NL
St. Anthony -
Transmission Main from Chlorine Building to West Link Road
Rocky Harbour -
Martin Point Landfill Remediation
Gros Morne National Park of Canada -
Shoreline Protection, Rocky Harbour, NL
The DFO-SCH project site is located in Rocky Harbour, Newfoundland. -
Conservation and Protection Detachment Construction in Rocky Harbour, NL
On a portion of land on West Link rd., adjacent to the RCMP detachment, in Rocky Harbour, Newfoundland and Labrador (NL) -
Newfoundland and Labrador Hydro Line Modifications in Gros Morne National Park
Gros Morne National Park of Canada -
Highway 431 Barters Hill Renovations
Gros Morne National Park of Canada -
Harbour Development, Norris Point, Newfoundland
Norris Point (Neddys Harbour) -
St. Anthony - Floating Dock Storage
St. Anthony, Newfoundland -
Escape Island Installation on Saddle Island
Red Bay National Historic Site -
Red Bay Underwater Archaeology Reburial Mound Repairs
Red Bay National Historic Site -
Easement Request at L'Anse aux Meadows National Historic Site
L'Anse aux Meadows National Historic Site -
Highway 431 and Tablelands Trail Access Road and Parking Lot Renovations
Gros Morne National Park of Canada -
Trout River Gulch Public and Commercial Snowmobile Corridor
Gros Morne National Park -
Wharf Reconstruction, Carmanville, NL
The DFO-SCH project site is located in Carmanville, Newfoundland. -
DFO-SCH Launchway Construction, Tilting, NL
Tilting, Newfoundland -
Building and Associated Infrastructure Demolition at Canadian Forces Base 9 Wing Gander Careless Cove Site, Newfoundland and Labrador
Canadian Forces Base 9 Wing Gander Careless Cove Site, along Gander Lake -
Labrador-Island Transmission Link Project
Mistaken Cove -
Wharf Reconstruction, Trout River, Newfoundland
Trout River -
Emergency Dredging, Trout River, NL
Trout River, Newfoundland. -
Consolidation of the small fishermen's wharf - Blanc-Sablon, Côte-Nord
Blanc-Sablon Small fishers's wharf -
Construction of a new breakwater and service area at the Grand quai des pêcheurs - Blanc-Sablon, Côte-Nord
Blanc-Sablon fishing harbour -
Harbour Redevelopment, Raleigh, Newfoundland
Raleigh -
Fence deviation at Lourdes-de-Blanc-Sablon Airport, Blanc-Sablon, Quebec
Lourdes-de-Blanc-Sablon Airport -
Lourdes-de-Blanc-Sablon Airport, Québec - new sensors installation
Lourdes-de-Blanc-Sablon -
Installation of a 50,000 L reservoir at the Lourdes-de-Blanc-Sablon airport
Lourdes-de-Blanc-Sablon Airport -
Removal of Above Ground Storage Tanks at Lourdes-de-Blanc-Sablon Airport
Lourdes-de-Blanc-Sablon Airport -
Lourdes-de-Blanc-Sablon Airport - Demolition and reconstruction of a hangar
Lourdes-de-Blanc-Sablon Airport -
Cape Norman Radar Communication site
Cape Norman -
Highway 436 and Parking Lot Rehabilitation at L'Anse aux Meadows NHS
L'Anse aux Meadows National Historic Site of Canada -
L'Anse aux Meadows National Historic Site Viking Silhouette Trail Work
L'Anse aux Meadows National Historic Site of Canada -
Demolition of Buildings 1-11 - 5th Canadian Ranger Patrol Group Site
5th Canadian Ranger Patrol Group Site -
Construction of New Building - Canadian Forces Base (CFB) Gander
Canadian Forces Base (CFB) Gander -
Upgrade Building B160 for Occupancy - 9 Wing Gander
9 Wing Gander -
Brush Cutting and Fence Line Repairs - Canadian Forces Base (CFB) Gander
Canadian Forces Base (CFB) Gander -
Construct New Military Family Resource Centre - Canadian Forces Base (CFB) Gander
Canadian Forces Base (CFB) Gander -
Explosives Storage Area Fence Repairs at 9 Wing Gander, Canadian Forces Base Gander, Newfoundland and Labrador
9 Wing Gander -
Accommodation for Wing Headquarters - 9 Wing Gander
9 Wing Gander -
Shoreline Protection Repairs, Musgrave Harbour, NL
The DFO-SCH project site is located in Musgrave Harbour, Newfoundland. -
Floating Dock construction, Musgrave Harbour, NL
DFO SCH Site in Musgrave Harbour, NL (DFRP # 01303) -
Relocate Sewage Lift Station at Hangar 1, Canadian Forces Base 9 Wing Gander, Newfoundland and Labrador
Hangar 1, Canadian Forces Base 9 Wing Gander -
Repair Cross Loop Access Road - Canadian Forces Station (CFS) Leitrim, Gander
Canadian Forces Station Leitrim, Gander -
Gander Very High Frequency Omni-directional Range (VOR) Replacement
Gander -
Saddle Island Boardwalk Renewal
Red Bay National Historic Site of Canada -
Off-grid conversion of lighthouse buildings on Saddle Island
Red Bay National Historic Site of Canada -
Saddle Island Interpretive Circuit
Red Bay National Historic Site of Canada -
Bay of Islands SAR Project, Corner Brook, Newfoundland
Corner Brook, Newfoundland -
Wharf Replacement, Frenchmans Cove, Newfoundland
Frenchmans Cove -
Harbour Development, Lark Harbour, NL
Lark Harbour, Newfoundland -
Lark Harbour Search and Rescue Wharf Extension
Main Road, Lark Harbour