ATCO Kainai Forage Gas Distribution Project

ATCO is proposing to install a new natural gas regulating facility, line heater, and natural gas distribution main on Blood Tribe 148 Reserve Lands to service existing homes and commercial buildings. The proposed regulating facility and line heater will be located adjacent to the Kainai Forage Development and the gas main will be installed from the regulating facility and extend for 5.1 kilometers East along an unnamed road. The gas main will be installed by a combination of trenchless horizontal direction drilling, plowing, and trenching. Additional project activities include the construction of a 10 x 10 meter gravel approach, grading, installation of a gravel pad and fencing for the regulating facility, and installation of solar panels.

 

The gas main will cross one unnamed Class D watercourse and ten wetland areas along the roadside. No tree clearing is expected for the proposed work. The Project is not in the vicinity of any known species at risk but is within the ranges of sharp-tailed grouse, prairie falcon, golden eagle, and ferruginous hawk. Indigenous Services Canada will be issuing a Land Permit under Section 28(2) of the Indian Act.

More


Latest update

May 15, 2025 – The Indigenous Services Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document number Document title File Date
1 Notice of Determination - May 15, 2025

Contacts

Environmental Review Process Alberta Region
Indigenous Services Canada
Environmental Review Process Alberta Region
630 Canada Place, 9700 Jasper Avenue
Edmonton, Alberta T5J 4G2
Email: paeab-erpab@sac-isc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Blood Tribe 148 Reserve (Alberta)
  • Nature of Activity

    • Oil and Gas
  • Assessment Status

    Completed
  • Start Date

    2025-04-09
  • Proponent

    ATCO
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    89438