Blood Tribe Aohkii Admin Building Project

The Blood Tribe Agricultural Project is proposing to build a new administration office adjacent to their current office building. The proposed site has been previously developed so no clearing and minimal regrading will be required. Proposed project activities include the construction of the new administration building, demolition of the current building, demolition of a shed, removal of an above ground propane tank, installation of a new water well, and installation of a new septic field. The construction waste produced from the project will be hauled to an approved landfill.


Latest update

March 21, 2025 – Indigenous Services Canada issued its Notice of Determination (iaac-aeic.gc.ca) and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document number Document title File Date
2 Notice of Determination for the Blood Tribe Aohkii Admin Building Project - March 21, 2025
1 Blood Tribe Aohkii Admin Building Project - Public Comments Invited - February 11, 2025

Contacts

Environmental Review Process Alberta Region
Lands, Environment and Economic Development
630 Canada Place, 9700 Jasper Avenue
Edmonton, Alberta T5J 4G2
Email: paeab-erpab@sac-isc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Blood Tribe (Alberta)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2025-02-11
  • Proponent

    Blood Tribe Agricultural Project
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    89272