Francis Street Upgrades - Madawaska Maliseet First Nation

The Francis Street Upgrade project involves extending the Storm Water Drainage system, adding Curbs and sidewalk, and installing a prefabricated steel pedestrian bridge across Snake Stream.

The existing Francis Street storm water drainage system is made up of a mixture of open ditch, driveway culverts, and underground piping. This project is to replace the open ditch/driveway culverts with an underground drainage system, complete with concrete curbs and sidewalk. Approximately 100m of Pipeline Road (Crush Rock surface) will be regraded and surfaced with 3 coats of chipseal.


Latest update

August 3, 2023 – Indigenous Services Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of determination - August 3, 2023
1 Notice of Intent to Make a Determination - Start of Public Comment Period - June 23, 2023

Contacts

Indigenous Services Canada - Atlantic
Indigenous Services Canada
PO BOX 160
40 Havelock Street
Amherst, Nova Scotia B4H 3Z3
Telephone: 1-800-567-9604
Fax: 902-661-6237
Email: aadnc.paeat-erpat.aandc@canada.ca


  • Location

    • Madawaska Maliseet First Nation (New Brunswick)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2023-06-23
  • Proponent

    Madawaska Maliseet First Nation
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    85710
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 