This project involves engineered reinstatement and careful placement of material that was lost recently due to erosion. This will ensure the bank is stabilized and can withstand further erosive forces. The work will require in-water placement of aggregate material with the use of heavy machinery as well as replacement and adjustment of filter cloth.


Latest update

September 19, 2025 – The authority issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document number Document title File Date
2 Notice of Determination - PSPC - September 19, 2025
1 Bank Stabilization at Latchford Dam - January 9, 2025

Contacts

Environment, Health and Safety
Public Services and Procurement Canada
11 Laurier Street
Portage III, Place du Portage
Gatineau, Quebec K1A 0S5
Email: TPSGC.RCNLVEEListedeControle-NCRECMPChecklist.PWGSC@tpsgc-pwgsc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Latchford Dam (Ontario)
  • Nature of Activity

    • Other, not otherwise specified
  • Assessment Status

    Completed
  • Start Date

    2025-01-09
  • Proponent

    PSPC
  • Authorities

    • Public Services and Procurement Canada
  • Assessment Type

    Project on federal lands