Tataskweyak Cree Nation - Water Treatment Plant Upgrade
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The proposed project (the Project) involves the design and construction of:
• a new WTP located on a 720 m2 area on a partially forested site located 4.6 km northwest from the existing WTP at
approximate UTM coordinates 14 V 674972 m E 6238410 m N (the Site; Appendix A: Figure 1, Appendix B: Photo
ID 2-4)
• upgrades to the existing WTP, located at approximate UTM coordinates 14 V 679391 m E 6236830 m N, to convert
it into a booster station with a capacity of up to 32 L/s to service the approximately 550 residents located on the
peninsula (Appendix A: Figure 1; Appendix B: Photo ID 1)
• a 3 m diameter concrete wet well with intake pumphouse located at approximate UTM coordinates 14V 670219 m
E 2641788 m N, equipped with 3 x 21 L/s submersible pumps to convey raw water to the new WTP (Appendix A:
Figure 1)
• a new raw water intake structure located approximately 250 m northwest of the intake pumphouse in Assean
Lake, installed to a depth of approximately 6-8 m underwater, connecting to the wet well via 300 mm raw water
intake pipe (Appendix A: Figure 2)
• installation of approximately 7.6 km of 300 mm watermain from the intake pumphouse to the new WTP
• an approximately 5 km long, 6 m wide gravel access road within an approximately 20 m wide right of way
connecting Provincial Road 280 on the west side of the TCN lagoon and heading northeast connecting to the intake
pumphouse, following the same alignment as the proposed watermain shown in Appendix A: Figure 2
• approximately 2.6 km of watermain upgrades (see Appendix A: Figure 2) including:
o a 2.6 km long, 300 mm watermain connecting the new WTP to the existing community distribution system
o approximately 40 m of minor sizing upgrades to the existing water distribution system
o approximately 1.4 km of process wastewater line to convey concentrated intake water that has not been
chemically treated, from the new WTP to discharge to Split Lake (Appendix A: Figure 2)
The proposed water system upgrades will provide treated water that meets drinking water quality guidelines and 20-year
calculated flow requirements.
Latest update
January 12, 2024 - Indigenous Services Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.
.
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination | - | January 12, 2024 |
1 | Public Comment Period on Intent to Make a Determination | - | February 2, 2023 |
Contacts
Indigenous Services CanadaShelly Johnson, Environmental Specialist
365 Hargrave Street
Winnipeg, Manitoba R3B 3A3
Telephone: 204-984-0709
Email: shelly.johnson@canada.ca
-
Location
- Tataskweyak Cree Nation (Manitoba)
-
Nature of Activity
- Water Management
-
Assessment Status
Completed -
Start Date
2023-02-02 -
Proponent
Tataskweyak Cree Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
84291
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Tataskweyak Cree Nation Environmental Remedial Actions at the Former Federal School Site
Tataskweyak Cree Nation Split Lake 171 -
Tataskweyak Cree Nation New Commercial Parcel Utility Development
Tataskweyak Cree Nation -
Tataskweyak Cree Nation New Co-op Store
Tataskweyak Cree Nation -
Tataskweyak - 100 unit subdivision - 2324
Tataskweyak -
York Factory First Nation Remedial Actions Project
York Factory First Nation -
York Factory Prevention Centre
York Factory -
York Factory - New Subdivision with road and utilities - 2324
York Factory -
War Lake First Nation Moosenose Lake Dam
Moosenose Lake Dam Reinforcement -
York Factory First Nation Remedial Actions Project
York Factory First Nation -
Keeyask Generation Project
Gull Rapids -
Thompson Very High Frequency Omni-directional Range (VOR) Replacement
Directory of Federal Real Property # 13101: Thompson (VOR/DME) (Manitoba) -
Community Resource Centre
Bird -
Fox Lake Cree Nation Water and Sewer System Development Project
Fox Lake Cree Nation -
Xplornet Communications Inc. Radiocommunication Antenna Addition on Peguis First Nation Reserve No. 269
Peguis First Nation Reserve No. 269 -
Bunibonibee Cree Nation - 48 Unit Subdivision
Bunibonibee Cree Nation -
Project 6 - All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation and God's Lake First Nation
-
Moody Road Development Municipal Servicing Project
Nishichawayasihk Cree Nation -
Nisichawayasihk Cree Nation Road Paving Project Phase 2
Nisichawayasihk Cree Nation Road Paving Project - Phase 2 -
Project 6 - All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation and God's Lake First Nation