York Factory First Nation Ten Shilling Aerodrome Project
York Factory First Nation is proposing to construct and operate a new aerodrome along Ten Shilling Creek, approximately four kilometres south of York Factory settlement and National Historic Site, in northeastern Manitoba. As proposed, the project would include a single, private 1,530-metre-long airplane runway that would be used for emergency services, improve access to York Factory First Nation's traditional territory, and support tourism and future development in the local area.
Latest update
August 15, 2025 — The Impact Assessment Agency of Canada (IAAC) issued an early decision that no further assessment is required. IAAC’s analysis found the project’s potential adverse effects within federal jurisdiction would be limited or addressed through other means, as noted in the Notice of Impact Assessment Decision with Reasons. The project may now move forward with obtaining any necessary authorizations and permits from federal and provincial authorities.
At a glance
Planning
Planning
Completed
59/180 days
Key documents
- Summary of Issues June 5, 2025
- Initial Project Description of a Designated Project April 25, 2025
- Summary of the Initial Project Description of a Designated Project April 25, 2025
Comment periods
- Public Notice - Comments Invited on the Summary of the Initial Project Description May 5, 2025 to May 26, 2025 - Closed
Participate
Contacts
Impact Assessment Agency of Canada160 Elgin Street, 22nd Floor
Ottawa, Ontario K1A 0H3
Telephone: 613-957-0700 or 1-866-582-1884
Fax: 613-957-0862
Email: information@iaac-aeic.gc.ca
Media Relations
Impact Assessment Agency of Canada
160 Elgin Street, 22nd Floor
Ottawa, Ontario K1A 0H3
Email: media@iaac-aeic.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Along Ten Shilling Creek in northeastern Manitoba (Manitoba)
-
Nature of Activity
- Airport and Airfields
-
Assessment Status
Completed -
Start Date
2025-05-05 -
Proponent
York Factory First Nation -
Authorities
- Impact Assessment Agency of Canada
-
Assessment Type
Early decision - No further assessment required -
Reference Number
89488
Nearby assessments
...within 200 kilometres-
SHAMATTAWA - WOMENS TRANSITION HOUSING
Shamattawa First Nation -
Shamattawa Re-unification Centre and Visiting Professional Accommodation
Shamattawa First Nation -
Shamattawa 30 Unit Housing Subdivision
Shamattawa First Nation -
Shamattawa RCMP Detachment Fence Replacement
Shamattawa -
Shamattawa RCMP Above Ground Storage Tank Replacement
Shamattawa -
New (Multiple) and Upgrades (Multiple) Radiocommunications Towers
Shamattawa -
Shamattawa Water treatment plant
Shamattawa Water Treatment Plant -
Fox Lake Cree Nation Water and Sewer System Development Project
Fox Lake Cree Nation -
Community Resource Centre
Bird -
Keeyask Generation Project
Gull Rapids