From Timiskaming First Nation to the Impact Assessment Agency of Canada - Response to the Request for Input on the Alexandra Bridge Replacement Project

Reference Number
31
Text

I had sent in some comments on behalf of Timiskaming First Nation last night. I would like to add a few comments/questions that had derived from our meeting last week. I know that you most likely recorded them but I said that I would add them as well but did not include them in my document last night. Can you please add the following?

 

Additional comments from the meeting

 

TFN asked the question if the design will remain the same due to the heritage of the bridge.

TFN would like more information around de-watering and the coffer dam.

What type of chemicals will be used for dust and where and when will it be used?

Which green spaces will be closed off for construction use?

TFN is interested in knowing which tourism and businesses will be impacted?

Are there local fisherman that use that area?

 

 

Thanks so much, have a great day!

 

Lindsay McLaren Polson

Sustainable Development Manager

Timiskaming First Nation

<personal information removed>

Submitted by
Administrator on behalf of Timiskaming First Nation
Phase
Planning
Public Notice
Public Notice - Public Comments Invited on a Summary of the Initial Project Description
Attachment(s)
N/A
Date Submitted
2022-04-25
Date modified: