Marginal Wharf Construction, Little Heart's Ease, NL

Fisheries and Oceans Canada, Small Craft Harbours (DFO SCH) is the proponent of the above-referenced project. The project at Little Heart's Ease will require the demolition and removal of the existing gabion wall in order to facilitate the placement of timber cribs for the new marginal wharf. The area of crib placement will be excavated and a rock mattress will be utilized to allow for the placement of cribs. Fenders from the finger pier will be removed to allow for the joining of the marginal wharf to the finger pier. There will also be excavation, scarification, and compaction of the existing parking area sub-grade in order to facilitate the placement of new rock fill and granulars along with the installation of a new catch basin.


Latest update

March 14, 2024 – The authorities issued their Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
1 Notice of Determination - March 14, 2024

Contacts

Fisheries and Oceans Canada
Paul Curran, Regional Engineer
10 Barters Hill
St. John's, Newfoundland and Labrador A1C 5X1
Telephone: 709-772-6660
Email: paul.curran@dfo-mpo.gc.ca


  • Location

    • Little Heart's Ease, Newfoundland (Newfoundland and Labrador)
  • Nature of Activity

    • Ports and Harbours
  • Assessment Status

    Completed
  • Start Date

    2022-02-18
  • Proponent

    Fisheries and Oceans Canada- Small Craft Harbours (DFO-SCH)
  • Authorities

    • Fisheries and Oceans Canada
    • Transport Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    83383
Disclaimer