February 29, 2024 – Indigenous Services Canada has determined that the Elsipogtog First Nation – Water Tower Demolition is not likely to cause significant adverse environmental effects

This determination was based on a consideration of the following factors:

  • impacts on rights of Indigenous peoples;
  • Indigenous knowledge;
  • community knowledge;
  • technically and economically feasible mitigation measures.

Mitigation measures taken into account for this determination are:

  • Impacts to Surface and Groundwater
  • Impacts to Air and Noise

Indigenous Services Canada is satisfied that the carrying out of the project is not likely to cause significant adverse environmental effects.

Therefore, Indigenous Services Canada may carry out the project, exercise any power, perform any duty or function, or provide financial assistance to enable the project to be carried out in whole or in part.