Repair and optimization of the railway bridge at Pie-IX entrance of the Port of Montreal
The mitigation measures taken into account for this determination are as follows:
- Nuisance management (noise, vibration and dust):
- Avoid operations during strong winds
- Use water or dust suppressant on surfaces likely to emit dust
- Cover soil piles
- Limit work at night
- Require dump trucks to be fitted with shock absorbers to prevent rattling
- Require broadband back-up alarms
- Create a loop to prevent machinery from reversing
- Continuous vibration monitoring and measurement
- Development and implementation of a noise management program
- Installation of a temporary retaining wall, respecting excavation slopes and management of accumulated water;
- Capture and management of surface water
- Management of soils, granular materials and other excavated materials
- Management of residual and hazardous materials
- Air quality management :
- Frequent machinery inspections
- Limitation of trucking and idling
- Protection of biodiversity and control of invasive alien species
- Management of environmental emergencies
Therefore, the MPA may perform any duty or function to enable the project to be carried out in whole or in part.
Document reference number: 1