Bruce C Nuclear Project

Comment Search Mobile

Comment Search

Skip to filters

329 results

Attachment Posting of Bruce Power’s List of Impact Assessment and Regulatory Documents, Workplan and Impact Statement Schedule

  • Bruce C Nuclear Project
  • Author: Northwatch
  • Reference Number: 267
  • Submitted: 2026-03-10 - 2:35 PM
  • Updated: 2026-03-23 - 3:41 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: N/A
  • March 10, 2026 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd floor Ottawa, Ontario K1A 0H3 Sent by Email: Bruce@iaac-aeic.gc.ca (mailto:Bruce@iaac-aeic.gc.ca) Re.        Posting of Bruce Power’s List of Impact Assessment and Regulatory Documents, Workplan and Impact Statement Schedule Since the “completion” of the planning phase IAAC has posted a number of documents related to the IA process, including the Notice of Commencement of an Impact Assessment (August 19, 2025), a Notice of the Establishment of Time Limits for the Integrated Impact Assessment for the Bruce C Nuclear Project and a “Project Charter”, On September 9th the Agency sent a letter (Registry #257 (https://iaac-aeic.gc.ca/050/documents/p88771/163162E.pdf)) to Bruce Power  about the submission of project ...
  • Attachment Included
  • March 10, 2026 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd floor Ottawa, Ontario K1A 0H3 Sent by Email: Bruce@iaac-aeic.gc.ca Re. Posting of Bruce Power’s List of Impact Assessment and Regulatory Documents, Workplan and Impact Statement Schedule Since the “completion” of the planning phase IAAC has posted a number of documents related to the IA process, including the Notice of Commencement of an Impact Assessment (August 19, 2025), a Notice of the Establishment of Time Limits for the Integrated Impact Assessment for the Bruce C Nuclear Project and a “Project Charter”, On September 9th the Agency sent a letter (Registry #257) to Bruce Power about the submission of project information, setting out a requirement that Bruce C provide a preliminary list of all impact assessment and regulatory documents before November 20, 2025 and requesting that Bruce C submit a final list of impact assessment and regulatory ...

Report

Attachment Posting of Bruce Power’s List of Impact Assessment and Regulatory Documents, Workplan and Impact Statement Schedule

  • Bruce C Nuclear Project
  • Author: Northwatch
  • Reference Number: 267
  • Submitted: 2026-03-10 - 2:35 PM
  • Updated: 2026-03-23 - 3:29 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: N/A
  • March 10, 2026 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd floor Ottawa, Ontario K1A 0H3 Sent by Email: Bruce@iaac-aeic.gc.ca (mailto:Bruce@iaac-aeic.gc.ca) Re.        Posting of Bruce Power’s List of Impact Assessment and Regulatory Documents, Workplan and Impact Statement Schedule Since the “completion” of the planning phase IAAC has posted a number of documents related to the IA process, including the Notice of Commencement of an Impact Assessment (August 19, 2025), a Notice of the Establishment of Time Limits for the Integrated Impact Assessment for the Bruce C Nuclear Project and a “Project Charter”, On September 9th the Agency sent a letter (Registry #257 (https://iaac-aeic.gc.ca/050/documents/p88771/163162E.pdf)) to Bruce Power  about the submission of project ...
  • Attachment Included
  • March 10, 2026 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd floor Ottawa, Ontario K1A 0H3 Sent by Email: Bruce@iaac-aeic.gc.ca Re. Posting of Bruce Power’s List of Impact Assessment and Regulatory Documents, Workplan and Impact Statement Schedule Since the “completion” of the planning phase IAAC has posted a number of documents related to the IA process, including the Notice of Commencement of an Impact Assessment (August 19, 2025), a Notice of the Establishment of Time Limits for the Integrated Impact Assessment for the Bruce C Nuclear Project and a “Project Charter”, On September 9th the Agency sent a letter (Registry #257) to Bruce Power about the submission of project information, setting out a requirement that Bruce C provide a preliminary list of all impact assessment and regulatory documents before November 20, 2025 and requesting that Bruce C submit a final list of impact assessment and regulatory ...

Report

Attachment SON Comments on TISG and Expectations for Impact Statement

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Saugeen Ojibway Nation
  • Reference Number: 259
  • Submitted: 2025-11-03 - 12:55 PM
  • Updated: 2025-11-19 - 3:38 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • November 3, 2025 Larry Shuter Senior Policy Analyst, Consultation Operations Division Impact Assessment Agency of Canada Marina Martin Policy Officer, Indigenous Consultation and Engagement Division Canadian Nuclear Safety Commission Mike Rinker Vice President, Regulatory Affairs Bruce Power Joanna Moffat Technical Officer, Indigenous Engagement & Partnerships Bruce Power Dear Mr. Shuter, Ms. Martin, Mr. Rinker and Ms. Moffat: Re: Saugeen Ojibway Nation Additional Comments on the Bruce C Project Assessment We have enclosed with this letter additional comments from the Saugeen Ojibway Nation (SON) on the information that Bruce Power must produce as part of the assessment of the Bruce C Project (the Project). Since the Bruce C Project was first announced, SON has been clear that we are willing to consider the proposal with open minds, but that the Project and its impacts must be carefully assessed and considered before any decision is reached ...
  • Attachment Included
  • Information shared on this page is for the integrated assessment of the proposed Bruce C project and has not been approved for use for other purposes. This information is the property of SON and can not be used for other purposes without SON's consent. November 3, 2025 Additional Comment Table from Saugeen Ojibway Nation on "Integrated TISG for Bruce C" Submitted to IAAC, CNSC, and Bruce Power as SON Expectations to shape the Impact Statement This table should be read with the cover letter provided by SON. SON was not provided sufficient time to finalize and submit these comments during the Planning Phase of the Integrated Impact Assessment. SON requested additional time for this, but this request was refused. These comments have been submitted as soon as possible. TISG Section Comment/Concern In response to these additional comments, Bruce Power must provide SON with a concordance table showing how each comment has been addressed, and if not addressed, provide a ...

Report

Attachment SON's Concerns respecting process and substance of the Draft Integrated TISG for Proposed Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Saugeen Ojibway Nation
  • Reference Number: 240
  • Submitted: 2025-07-22 - 11:03 AM
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • Saugeen Ojibway Nation Environment Office 010129 Highway 6, Georgian Bluffs, ON N0H 2T0 (519) 534-5507 saugeenojibwaynation.ca Addressed To: Larry Shuter Senior Policy Analyst, Consultation Operations Division Impact Assessment Agency of Canada (IAAC) Kirsten Sellers Senior Policy Officer Canadian Nuclear Safety Commission (CNSC) SON’s Concerns respecting process and substance of the Draft Integrated TISG for Proposed Bruce C Nuclear Project DATE: July 22, 2025 Dear Larry and Kirsten, We write further to the Saugeen Ojibway Nation’s (“SON”) letter of June 18, 2025. As conveyed in that letter to the Impact Assessment Agency of Canada (“IAAC”) and the Canadian Nuclear Safety Commission (“CNSC”), SON was deeply disappointed by the decision to recommence the Planning Phase—a decision which has continued to undermine our ability to engage meaningfully with the federal impact assessment process for the Bruce C Nuclear ...

Report

Attachment Comments from Ministry of Emergency Preparedness and Response-Nuclear, Radiological and Scientific Response Programs F.Tourneur on behalf of Michael Munro

  • Bruce C Nuclear Project
  • Author: Ministry of Emergency Preparedness and Response - Nuclear Radiological and Scientific Response Programs
  • Reference Number: 235
  • Submitted: 2025-07-15 - 8:53 AM
  • Project Phase: Planning
  • Participation Notice: N/A
  • Comments from Ministry of Emergency Preparedness and Response-Nuclear, Radiological and Scientific Response Programs F.Tourneur on behalf of Michael Munro
  • Attachment Included
  • CIAR #: 88771 Bruce C Nuclear Project Page 1 of 4 Comment Form – Draft Cooperation Plan and Draft Integrated Tailored Impact Statement Guidelines – Provincial Review Team Bruce C Nuclear Project Response required by: July 11, 2025 All comments should be submitted via the Submit a Comment feature available on the Project’s Canadian Impact Assessment Registry page (https://iaac-aeic.gc.ca/050/evaluations/proj/88771?culture=en-CA). Documents can be uploaded using this feature. If you have any difficulties submitting this way, please contact the Registry directly at registry-registre@iaac-aeic.gc.ca. All comments submitted using this form will be posted on the Registry website for the Project. Please note that this is your opportunity to tailor the draft Tailored Impact Statement Guidelines. Ministry/Office: Ministry of Emergency Preparedness and Response IA Contact: Michael Munro Senior Manager, Nuclear, Radiological and Scientific Response Programs ...

Report

Attachment Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Jacquelyn Drechsler and Jocelyn DeCrescenzo
  • Reference Number: 228
  • Submitted: 2025-07-11 - 10:41 PM
  • Updated: 2025-07-14 - 2:18 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • Thank you for the opportunity to submit comments regarding the Bruce C Project. Without having selected a reactor design, Bruce Power has already started an impact assessment, wanting approval without stating what kind of nuclear power plant they would build. Most assuredly and idiotically putting the cart before the horse.Without this information and wanting approval without stating what kind of power plant they will build, it is impossible for a review panel to approve this project, as their impact assessment would be missing critical information. The guidelines are clear.There has not been an examination of the need for this project, nor an examination of environmentally friendlier and less costly alternatives. How is it possible to even consider approval? There is the matter of the creation of massive amounts of radioactive nuclear waste. What kind of reactor? How much more waste? If SMR's are considered, and according to Lindsay Krall and Alison McFarland, we know ...

Report

Attachment Northwatch's Comment on the draft Public Participation Plan for the Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Northwatch
  • Reference Number: 232
  • Submitted: 2025-07-12 - 7:56 AM
  • Updated: 2025-07-15 - 3:52 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • Bruce C Nuclear Project Brennain Lloyd Comment on the Draft Integrated Tailored Impact Statement Guidelines IAA Reference # 88771 July 11, 2025 Northwatch Comments on Bruce C Nuclear Project draft Integrated Tailored Impact Statement Guidelines 1 Introduction On June 12, 2025 the Impact Assessment Agency of Canada and the Canadian Nuclear Safety Commission announced a 30 day comment period closing July 11, 2025 and invited comments on the draft Integrated Tailored Impact Statement Guidelines and the draft public participation plan for the Bruce C Nuclear Project. In total there are four plans – the Draft Indigenous Engagement and Partnership Plan , Draft Permitting Plan, Draft Cooperation Plan, and a Draft Public Participation Plan – but the invitation for public comment was limited to the draft public participation plan. In response to Northwatch’s request that the Agency confirm that there is also a public comment period on the ...
  • Attachment Included
  • July 11, 2025 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd floor. Ottawa, Ontario K1A 0H3 IAA Reference # 88771 Comments on the Public Participation Plan for the Bruce C Nuclear Project Review In the Agency’s June 12th announcement of the 30-day comment period on the draft Integrated Tailored Impact Statement Guidelines and the draft Public Participation Plan, the public was invited to comment on those two draft documents. Our comments on the guidelines are provided under separate cover, as are our brief comments on a Draft Indigenous Engagement and Partnership Plan. Public Participation Plan We have reviewed the draft public participation plan and offer the following comments, suggestions, and / or requests for changes or additions to the final public participation plan: - The revised public participation plan should clearly set out the various steps and public comment opportunities in the ...

Report

Attachment Judith Fox Lee Comments on the Bruce C draft guidelines and public participation plan

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Judith Fox Lee
  • Reference Number: 230
  • Submitted: 2025-07-11 - 11:21 PM
  • Updated: 2025-07-18 - 2:24 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • 1 From: Judith Fox Lee Sent: Friday, July 11, 2025 11:21 PM To: Bruce C Nuclear Integrated Assessment / Évaluation Intégrée Bruce C Nucléaire (IAAC/AEIC) Subject: Judith Fox Lee Comments on the Bruce C draft guidelines and public participation plan Categories: Add to DL To Whom It May Concern, I, Judith Fox Lee of Perth Ontario hereby submit my comments on the draft Integrated Guidelines and the draft Public Participation Plan for the Bruce C Nuclear Project, its current expansion proposal. I will appreciate it if my comments are fully tracked, posted and shared with all concerned members of the Proponent's team, the related IAAC and CNSC staff, the Review Panel members, and the Governor in Council, to assist them in making a reasonable determination on this Integrated Assessment process, in deciding whether the project is in the public interest . I also hereby ask to be added to the distribution list at this same email address, . To wit: I fully recommend that ...

Report