Mont Sorcier Mining Project
Voyager Metals Inc. is proposing the construction, operation, decommissioning, and closure of an open-pit iron and vanadium mine located in the Eeyou Istchee James Bay Territory, in the municipality of Chibougamau, about 20 kilometres northeast of the Town of Chibougamau, Quebec, in the traditional Cree territory. As proposed, the Mont Sorcier Mining Project would include a pit and the construction of an ore processing facility. The proponent also plans to build a 49-kilometre railroad that would connect to the existing track to transport the concentrate by train to the Grande-Anse Marine Terminal, where it would be stockpiled for export purposes. The mine's production capacity would be about 5 million tonnes per year (average rate of 13,700 tonnes/day) and the estimated life of the project would be 21 years.
Latest update
At a glance
Planning
Planning
Key documents
- Cooperation Plan September 19, 2025
- Permitting Plan September 19, 2025
- Indigenous Engagement and Participation Plan September 19, 2025
- Public Participation Plan September 19, 2025
- Tailored Impact Statement Guidelines September 19, 2025
- Notice of Impact Assessment Decision with Reasons June 9, 2025
- Notice of Time Limit Resumption May 29, 2025
- Notice of time limit suspension with reasons October 23, 2024
- Summary of Issues July 24, 2023
- Description initiale du projet d'un projet désigné (French Only) May 29, 2023
- Summary of an Initial Project Description of a Designated Project May 29, 2023
Comment periods
- Public Notice - Comments Invited on the Draft Tailored Impact Statement Guidelines and Draft Public Participation Plan July 17, 2025 to August 16, 2025 - Closed
- Public Notice - Public Comments Invited on a Summary of the Initial Project Description May 29, 2023 to July 14, 2023 - Closed
Impact Statement
Impact Statement
Key documents
- Notice of Commencement of an Impact Assessment September 19, 2025
Post Decision
Post Decision phase is an ongoing process
Post Decision
Participate
Contacts
Media RelationsImpact Assessment Agency of Canada
160 Elgin Street, 22nd Floor
Ottawa, Ontario K1A 0H3
Email: media@iaac-aeic.gc.ca
Mont Sorcier Mining Project
Impact Assessment Agency of Canada
901-1550 d'Estimauville Avenue
Québec, Quebec G1J 0C1
Telephone: 418-649-6444
Email: montsorcier@iaac-aeic.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Eeyou Istchee James Bay Territory (Quebec)
-
Nature of Activity
- Mines and Minerals
-
Assessment Status
In progress -
Start Date
2023-05-29 -
Proponent
Voyager Metals Inc. -
Authorities
- Impact Assessment Agency of Canada
-
Assessment Type
Impact Assessment by the Agency -
Reference Number
84616
Nearby assessments
...within 200 kilometres-
BlackRock Mining Project
Chibougamau, Lemoine Township -
Renard Diamond Mine Project
Mistissini -
Troilus Mining Project
Municipality of Baie-James -
Lac Windfall Mine Project
Eeyou Istchee-James Bay Territory -
New (Single) Tower Construction - Atikamekw d'Opitciwan
Obedjiwan Indian Reserve No.28 Project site 1: -
Modification of Hydro-Québec facilities, including the construction of a new sectioning post to optimize and integrate energy produced by a forest biomass cogeneration plant in Opitciwan
Opitciwan -
Opitciwan Cogeneration Plant project
Atikamekw d'Opitciwan Obedjiwan 28 Reserve -
Construction of a cogeneration plant
The Atikamekw of Opitciwan -
New (Single) Tower Construction - Atikamekw d'Opitciwan
Obedjiwan Indian Reserve No.28 Project site 2: -
Environmental rehabilitation at the Opitciwan Power Station
Opitciwan -
Construction of a new pediatric center "Mamonitokiwan center"
Council of the Atikamekw Nation -
Extension of Amisk Street in Opitciwan
Opitciwan -
Air medic heliport at Obedjiwan
Obedjiwan -
Normandin Heating System Project
Normandin