  • Project Reid Road Reservoir Quarry Project
  • Document Category: Additional Information
  • Reference Number: 2
  • Updated: 2019-12-12
  • Document: 133525E.html
  • Relevance: 266.03
  • Analysis Report — whether to designate the Reid Road Reservoir Quarry in Ontario December 2019 Table of contents Context of Request Project Context Project overview Project components and activities Analysis of Designation Request Authority to designate the Project Potential adverse effects within federal jurisdiction Potential adverse direct or incidental effects Public concerns Potential adverse impacts on the rights of Indigenous peoples Regional and strategic ...
3 alternate formats found
English PDF
  • Relevance: 266.03
  • Analysis Report WHETHER TO DESIGNATE THE REID ROAD RESERVOIR QUARRY IN ONTARIO December 2019 Analysis Report Impact Assessment Agency of Canada i TABLE OF CONTENTS CONTEXT OF REQUEST ....................................................................................................................................... 1 PROJECT CONTEXT ...
French HTML
  • Relevance: 215.03
  • Rapport d'analyse — quant à la désignation de la carrière du réservoir du chemin Reid en Ontario conformément à la Loi sur l'évaluation d'impact Décembre 2019 Table des matières Contexte de la demande Contexte du projet Aperçu du projet Composantes et activités du projet Analyse de la demande de désignation Autorité pour désigner le projet Effets négatifs potentiels relevant de la compétence fédérale Effets négatifs directs ou accessoires potentiels Préoccupations du ...
French PDF
  • Relevance: 215.03
  • Rapport d’analyse QUANT À LA DÉSIGNATION DE LA CARRIÈRE DU RÉSERVOIR DU CHEMIN REID EN ONTARIO CONFORMÉMENT À LA LOI SUR L’ÉVALUATION D’IMPACT Décembre 2019 Rapport d’analyse Agence d’évaluation d’impact du Canada i TABLE DES MATIÈRES CONTEXTE DE LA DEMANDE................................................................................................................................. 1 CONTEXTE DU PROJET ...

Document Minister's response

  • Project Reid Road Reservoir Quarry Project
  • Document Category: Additional Information
  • Reference Number: 1
  • Updated: 2019-12-12
  • Document: 133285E.html
  • Relevance: 266.03
  • Minister's response Date: December 12, 2019 Project: James Dick Construction Ltd. is proposing to re-open, operate, and decommission the Reid Road Reservoir Quarry for the extraction and processing of aggregate at a maximum production capacity of 990,000 tonnes per year for approximately 20 years. The Project would be located in Milton, Ontario. Decision: Non-designated project. Reasons: The Minister of Environment and Climate Change has considered the potential for the Project to ...
1 alternate format found
French HTML
  • Relevance: 215.03
  • Réponse du Ministre Date : 12 décembre 2019 Projet : James Dick Construction Ltd. propose de rouvrir, d'exploiter et de désaffecter la carrière du réservoir du chemin Reid pour l'extraction et le traitement d'agrégats à une capacité de production maximale de 990 000 tonnes par année pendant environ 20 ans. Le projet sera situé à Milton, en Ontario. Décision : Projet non désigné. Raisons : Le ministre de l'Environnement et du Changement climatique a examiné la possibilité que le ...