Bruce C Nuclear Project

Comment Search Mobile

Comment Search

Skip to filters

290 results

Attachment SON Comments on TISG and Expectations for Impact Statement

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Saugeen Ojibway Nation
  • Reference Number: 259
  • Submitted: 2025-11-03 - 12:55 PM
  • Updated: 2025-11-19 - 3:38 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • November 3, 2025 Larry Shuter Senior Policy Analyst, Consultation Operations Division Impact Assessment Agency of Canada Marina Martin Policy Officer, Indigenous Consultation and Engagement Division Canadian Nuclear Safety Commission Mike Rinker Vice President, Regulatory Affairs Bruce Power Joanna Moffat Technical Officer, Indigenous Engagement & Partnerships Bruce Power Dear Mr. Shuter, Ms. Martin, Mr. Rinker and Ms. Moffat: Re: Saugeen Ojibway Nation Additional Comments on the Bruce C Project Assessment We have enclosed with this letter additional comments from the Saugeen Ojibway Nation (SON) on the information that Bruce Power must produce as part of the assessment of the Bruce C Project (the Project). Since the Bruce C Project was first announced, SON has been clear that we are willing to consider the proposal with open minds, but that the Project and its impacts must be carefully assessed and considered before any decision is reached ...
  • Attachment Included
  • Information shared on this page is for the integrated assessment of the proposed Bruce C project and has not been approved for use for other purposes. This information is the property of SON and can not be used for other purposes without SON's consent. November 3, 2025 Additional Comment Table from Saugeen Ojibway Nation on "Integrated TISG for Bruce C" Submitted to IAAC, CNSC, and Bruce Power as SON Expectations to shape the Impact Statement This table should be read with the cover letter provided by SON. SON was not provided sufficient time to finalize and submit these comments during the Planning Phase of the Integrated Impact Assessment. SON requested additional time for this, but this request was refused. These comments have been submitted as soon as possible. TISG Section Comment/Concern In response to these additional comments, Bruce Power must provide SON with a concordance table showing how each comment has been addressed, and if not addressed, provide a ...

Report

Attachment SON's Concerns respecting process and substance of the Draft Integrated TISG for Proposed Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Saugeen Ojibway Nation
  • Reference Number: 240
  • Submitted: 2025-07-22 - 11:03 AM
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • Saugeen Ojibway Nation Environment Office 010129 Highway 6, Georgian Bluffs, ON N0H 2T0 (519) 534-5507 saugeenojibwaynation.ca Addressed To: Larry Shuter Senior Policy Analyst, Consultation Operations Division Impact Assessment Agency of Canada (IAAC) Kirsten Sellers Senior Policy Officer Canadian Nuclear Safety Commission (CNSC) SON’s Concerns respecting process and substance of the Draft Integrated TISG for Proposed Bruce C Nuclear Project DATE: July 22, 2025 Dear Larry and Kirsten, We write further to the Saugeen Ojibway Nation’s (“SON”) letter of June 18, 2025. As conveyed in that letter to the Impact Assessment Agency of Canada (“IAAC”) and the Canadian Nuclear Safety Commission (“CNSC”), SON was deeply disappointed by the decision to recommence the Planning Phase—a decision which has continued to undermine our ability to engage meaningfully with the federal impact assessment process for the Bruce C Nuclear ...

Report

Attachment Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Jacquelyn Drechsler and Jocelyn DeCrescenzo
  • Reference Number: 228
  • Submitted: 2025-07-11 - 10:41 PM
  • Updated: 2025-07-14 - 2:18 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • Thank you for the opportunity to submit comments regarding the Bruce C Project. Without having selected a reactor design, Bruce Power has already started an impact assessment, wanting approval without stating what kind of nuclear power plant they would build. Most assuredly and idiotically putting the cart before the horse.Without this information and wanting approval without stating what kind of power plant they will build, it is impossible for a review panel to approve this project, as their impact assessment would be missing critical information. The guidelines are clear.There has not been an examination of the need for this project, nor an examination of environmentally friendlier and less costly alternatives. How is it possible to even consider approval? There is the matter of the creation of massive amounts of radioactive nuclear waste. What kind of reactor? How much more waste? If SMR's are considered, and according to Lindsay Krall and Alison McFarland, we know ...

Report

Attachment Northwatch's Comment on the draft Public Participation Plan for the Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Northwatch
  • Reference Number: 232
  • Submitted: 2025-07-12 - 7:56 AM
  • Updated: 2025-07-15 - 3:52 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • Bruce C Nuclear Project Brennain Lloyd Comment on the Draft Integrated Tailored Impact Statement Guidelines IAA Reference # 88771 July 11, 2025 Northwatch Comments on Bruce C Nuclear Project draft Integrated Tailored Impact Statement Guidelines 1 Introduction On June 12, 2025 the Impact Assessment Agency of Canada and the Canadian Nuclear Safety Commission announced a 30 day comment period closing July 11, 2025 and invited comments on the draft Integrated Tailored Impact Statement Guidelines and the draft public participation plan for the Bruce C Nuclear Project. In total there are four plans – the Draft Indigenous Engagement and Partnership Plan , Draft Permitting Plan, Draft Cooperation Plan, and a Draft Public Participation Plan – but the invitation for public comment was limited to the draft public participation plan. In response to Northwatch’s request that the Agency confirm that there is also a public comment period on the ...
  • Attachment Included
  • July 11, 2025 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd floor. Ottawa, Ontario K1A 0H3 IAA Reference # 88771 Comments on the Public Participation Plan for the Bruce C Nuclear Project Review In the Agency’s June 12th announcement of the 30-day comment period on the draft Integrated Tailored Impact Statement Guidelines and the draft Public Participation Plan, the public was invited to comment on those two draft documents. Our comments on the guidelines are provided under separate cover, as are our brief comments on a Draft Indigenous Engagement and Partnership Plan. Public Participation Plan We have reviewed the draft public participation plan and offer the following comments, suggestions, and / or requests for changes or additions to the final public participation plan: - The revised public participation plan should clearly set out the various steps and public comment opportunities in the ...

Report

Attachment Judith Fox Lee Comments on the Bruce C draft guidelines and public participation plan

  • Bruce C Nuclear Project
  • Author: Administrator on behalf of Judith Fox Lee
  • Reference Number: 230
  • Submitted: 2025-07-11 - 11:21 PM
  • Updated: 2025-07-18 - 2:24 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Impact Statement
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment Included
  • 1 From: Judith Fox Lee Sent: Friday, July 11, 2025 11:21 PM To: Bruce C Nuclear Integrated Assessment / Évaluation Intégrée Bruce C Nucléaire (IAAC/AEIC) Subject: Judith Fox Lee Comments on the Bruce C draft guidelines and public participation plan Categories: Add to DL To Whom It May Concern, I, Judith Fox Lee of Perth Ontario hereby submit my comments on the draft Integrated Guidelines and the draft Public Participation Plan for the Bruce C Nuclear Project, its current expansion proposal. I will appreciate it if my comments are fully tracked, posted and shared with all concerned members of the Proponent's team, the related IAAC and CNSC staff, the Review Panel members, and the Governor in Council, to assist them in making a reasonable determination on this Integrated Assessment process, in deciding whether the project is in the public interest . I also hereby ask to be added to the distribution list at this same email address, . To wit: I fully recommend that ...

Report

Attachment Comments on Draft Cooperation Plan and Draft Integrated Impact Statement Guidelines

  • Bruce C Nuclear Project
  • Author: Ministry of the Environment, Conservation and Parks
  • Reference Number: 221
  • Submitted: 2025-07-11 - 5:06 PM
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Attached are the Ministry of the Environment, Conservation and Parks (MECP) comments on both the draft cooperation plan and draft integrated impact statement guidelines.  Please note that MECP may have additional technical comments to provide.  We appreciate and thank you for the opportunity to comment.  Feel free to contact me if you have any questions or would like to discuss the attached comments. 
  • Attachment Included
  • CIAR #: 88771 Bruce C Nuclear Project Page 1 of 4 Comment Form – Draft Cooperation Plan and Draft Integrated Tailored Impact Statement Guidelines – Provincial Review Team Bruce C Nuclear Project Response required by: July 11, 2025 All comments should be submitted via the Submit a Comment feature available on the Project’s Canadian Impact Assessment Registry page (https://iaac-aeic.gc.ca/050/evaluations/proj/88771?culture=en-CA). Documents can be uploaded using this feature. If you have any difficulties submitting this way, please contact the Registry directly at registry-registre@iaac-aeic.gc.ca. All comments submitted using this form will be posted on the Registry website for the Project. Please note that this is your opportunity to tailor the draft Tailored Impact Statement Guidelines. Ministry/Office: Ministry of the Environment, Conservation and Parks IA Contact: May Lyn Trudelle Telephone: 437-855-6117 Email: MayLyn.Trudelle@ontario.ca ...

Report

Attachment Comments on the Draft Cooperation Plan and the Draft Integrated Tailored Impact Statement Guidelines

  • Bruce C Nuclear Project
  • Author: Ministry of Natural Resources
  • Reference Number: 220
  • Submitted: 2025-07-11 - 4:20 PM
  • Updated: 2025-11-07 - 3:18 PM
  • Rationale: Comment updated for administrative purposes
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Thank you for the opportunity to review the draft Cooperation Plan and the draft Integrated Guidelines for the Bruce C Nuclear Project. Please find MNR's responses in the attached form. We have intentionally left the Table in Section 2 blank. The draft Integrated Guidelines are comprehensive and we do not foresee any information requirements extending outside of these requirements for any potential provincial legislative or regulatory oversight. Please do not hesitate to reach out if you have any questions.
  • Attachment Included
  • CIAR #: 88771 Bruce C Nuclear Project Page 1 of 3 Comment Form – Draft Cooperation Plan and Draft Integrated Tailored Impact Statement Guidelines – Provincial Review Team Bruce C Nuclear Project Response required by: July 11, 2025 Revised by MNR and submitted August 12, 2025 All comments should be submitted via the Submit a Comment feature available on the Project’s Canadian Impact Assessment Registry page (https://iaac-aeic.gc.ca/050/evaluations/proj/88771?culture=en-CA). Documents can be uploaded using this feature. If you have any difficulties submitting this way, please contact the Registry directly at registry-registre@iaac-aeic.gc.ca. All comments submitted using this form will be posted on the Registry website for the Project. Please note that this is your opportunity to tailor the draft Tailored Impact Statement Guidelines. Ministry/Office: Ministry of Natural Resources (MNR) - Land Use Planning and Strategic Issues Section (LUPSIS) ...

Report

Attachment Comments on draft Tailored Impact Statement Guidelines and Cooperation Plan on the Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Ministry of Citizenship and Multiculturalism (Heritage Planning Unit)
  • Reference Number: 217
  • Submitted: 2025-07-11 - 3:38 PM
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Dear IAAC team, Please find attached the Ministry of Citizenship and Multiculturalism’s comments on the draft Tailored Impact Statement Guidelines and Cooperation Plan on the Bruce C Nuclear Project. Do not hesitate to contact me with any questions or concerns. Best regards, Anastasia Abrazhevich  | Heritage Planner Heritage Planner | Citizenship, Inclusion and Heritage Division Ministry of Citizenship and Multiculturalism  |  Ontario Public Service 437.240.2379 | Anastasia.Abrazhevich@ontario.ca   Submitted by The Ministry of Citizenship and Multiculuturalism     
  • Attachment Included
  • CIAR #: 88771 Bruce C Nuclear Project Page 1 of 7 Comment Form – Draft Cooperation Plan and Draft Integrated Tailored Impact Statement Guidelines – Provincial Review Team Bruce C Nuclear Project Response required by: July 11, 2025 All comments should be submitted via the Submit a Comment feature available on the Project’s Canadian Impact Assessment Registry page (https://iaac-aeic.gc.ca/050/evaluations/proj/88771?culture=en-CA). Documents can be uploaded using this feature. If you have any difficulties submitting this way, please contact the Registry directly at registry-registre@iaac-aeic.gc.ca. All comments submitted using this form will be posted on the Registry website for the Project. Please note that this is your opportunity to tailor the draft Tailored Impact Statement Guidelines. Ministry/Office: Ministry of Citizenship and Multiculturalism (MCM) IA Contact: Anastasia Abrazhevich, Heritage Planner, Heritage Planning Unit Karla ...

Report

Attachment DFO comments on the draft TISGs for the Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Fisheries and Oceans Canada
  • Reference Number: 216
  • Submitted: 2025-07-11 - 3:32 PM
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Please find the attached comments from DFO on the draft TISGs for Bruce C Nuclear Project, as requested by the Impact Assessment Agency of Canada.
  • Attachment Included
  • CIAR #: 88771 Bruce C Nuclear Project Page 1 of 6 Unclassified - Non-Classifié Comment Form – Draft Permitting Plan and draft Integrated Tailored Impact Statement Guidelines – Federal Review Team Bruce C Nuclear Project Response required by: July 11, 2025 All comments should be submitted via the Submit a Comment feature available on the Project’s Canadian Impact Assessment Registry1 (the Registry). Documents can be uploaded using this feature. If you have any difficulties submitting this way, please contact the Registry team directly at registry-registre@iaac-aeic.gc.ca. All comments submitted using this form will be posted on the Registry website for the Project. Please note that this is your opportunity to customize the draft Integrated Tailored Impact Statement Guidelines. Department/Agency: Department of Fisheries and Oceans IA Contact: William Glass Telephone: (289) 527-1128 Email: William.Glass@afo-mpo.gc.ca Section 1 – Draft Permitting ...

Report

Attachment Transport Canada Comments on the Draft Permitting Plan and Draft Integrated Tailored Impact Statement Guidelines for the Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Transport Canada
  • Reference Number: 215
  • Submitted: 2025-07-11 - 3:25 PM
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Transport Canada's Comments on the Draft Permitting Plan and Draft Integrated Tailored Impact Statement Guidelines for the Bruce C Nuclear Project are attached.
  • Attachment Included
  • CIAR #: 88771 Bruce C Nuclear Project Page 1 of 3 Comment Form – Draft Permitting Plan and draft Integrated Tailored Impact Statement Guidelines – Federal Review Team Bruce C Nuclear Project All comments should be submitted via the Submit a Comment feature available on the Project’s Canadian Impact Assessment Registry1 (the Registry). Documents can be uploaded using this feature. If you have any difficulties submitting this way, please contact the Registry team directly at registry-registre@iaac-aeic.gc.ca. All comments submitted using this form will be posted on the Registry website for the Project. Please note that this is your opportunity to customize the draft Integrated Tailored Impact Statement Guidelines. Department/Agency: Transport Canada IA Contact: Jeremy Craigs Telephone: Email: Jeremy.craigs@tc.gc.ca Section 1 – Draft Permitting Plan: 1. Indicate whether your department or agency has identified any power that it will be unable to ...

Report

Attachment Health Canada's Comments on the Draft Permitting Plan and Draft Integrated Tailored Impact Statement Guidelines for the Bruce C Nuclear Project

  • Bruce C Nuclear Project
  • Author: Health Canada
  • Reference Number: 214
  • Submitted: 2025-07-11 - 3:00 PM
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Dear Joshua Won,   Thank you for your email on June 12, 2025, requesting Health Canada’s review of the Draft Permitting Plan and Draft Integrated Tailored Impact Statement Guidelines for the Bruce C Nuclear Project. Health Canada has completed its review of the Draft Integrated Tailored Impact Statement Guidelines and has provided comments in the attachment.   Should you have any questions related to Health Canada’s comments, please contact the undersigned.    Sincerely,     Impact Assessment Team Health Canada / Government of Canada ia-ei@hc-sc.gc.ca (mailto:ia-ei@hc-sc.gc.ca) L’équipe d’évaluation d’impact Santé Canada / Gouvernement du Canada ia-ei@hc-sc.gc.ca (mailto:ia-ei@hc-sc.gc.ca)
  • Attachment Included
  • 1 Environmental Health Program Regulatory Operations and Enforcement Branch Health Canada 180 Queen Street West, Floor 10 Toronto, Ontario M5V 3L7 July 11, 2025 Joshua Won Integrated Review Team for the Bruce C Nuclear Project Impact Assessment Agency of Canada 55 York St Toronto, ON M5J 1R7 Submitted to the Impact Assessment Agency of Canada Registry Health Canada’s Comments on the Draft Permitting Plan and Draft Integrated Tailored Impact Statement Guidelines for the Bruce C Nuclear Project Dear Joshua Won, Thank you for your email on June 12, 2025, requesting Health Canada’s review of the Draft Permitting Plan and Draft Integrated Tailored Impact Statement Guidelines for the Bruce C Nuclear Project. Health Canada is the federal department responsible for helping Canadians maintain and improve their health. One of the ways this is accomplished is through participation in the review of potential ...
  • Attachment Included
  • CIAR #: 88771 Bruce C Nuclear Project Page 1 of 9 Unclassified / Non classifié Comment Form – Draft Permitting Plan and draft Integrated Tailored Impact Statement Guidelines – Federal Review Team Bruce C Nuclear Project Response required by: July 11, 2025 All comments should be submitted via the Submit a Comment feature available on the Project’s Canadian Impact Assessment Registry1 (the Registry). Documents can be uploaded using this feature. If you have any difficulties submitting this way, please contact the Registry team directly at registry-registre@iaac-aeic.gc.ca. All comments submitted using this form will be posted on the Registry website for the Project. Please note that this is your opportunity to tailor the draft Integrated Tailored Impact Statement Guidelines. Department/Agency: Health Canada 180 Queen Street West – 10th Floor Toronto, Ontario IA Contact: Joel Kaushansky Regional Impact Assessment Specialist – Ontario Region ...

Report

Attachment Municipality of Kincardine - submission on draft documents

  • Bruce C Nuclear Project
  • Author: Municipality of Kincardine
  • Reference Number: 211
  • Submitted: 2025-07-11 - 2:08 PM
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Please accept the attached comments from the Municipality of Kincardine on the draft Integrated Tailored Impact Statement Guidelines, the draft Public Participation Plan, the draft Cooperation Plan and the draft Permittig Plan.
  • Attachment Included
  • The Municipality of Kincardine 1475 Concession 5, R.R. #5, Kincardine, ON N2Z 2X6 Phone: 519-396-3468 | Fax: 519-396-8288 kincardine.ca June 25, 2025 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd Floor Ottawa, Ontario K1A 0H3 RE: Municipality of Kincardine comments on the draft Public Participation Plan To Whom it May Concern: Please accept this submission from the Municipality of Kincardine on the draft Public Participation Plan for the Bruce C Nuclear Project. This submission was endorsed by the Council for the Corporation of the Municipality of Kincardine at the July 9, 2025 meeting. The Municipality of Kincardine is the host municipality to Bruce Power, Ontario Power Generations’ Western Waste Management Facility and the Douglas Point Nuclear Generating Station. The Municipality, including the former Township of Bruce, has been host to the nuclear industry for almost 60 years. Our Mayor and Council are ...
  • Attachment Included
  • The Municipality of Kincardine 1475 Concession 5, R.R. #5, Kincardine, ON N2Z 2X6 Phone: 519-396-3468 | Fax: 519-396-8288 kincardine.ca June 25, 2025 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd Floor Ottawa, Ontario K1A 0H3 RE: Municipality of Kincardine comments on the Bruce C draft Permitting Plan To Whom it May Concern: Please accept this submission from the Municipality of Kincardine on the draft Permitting Plan for the Bruce C Nuclear Project. These comments have been endorsed by the Council for the Corporation of the Municipality of Kincardine at the July 9, 2025 meeting. We request that these comments be reflected in the final Permitting Plan and if they are not included, we request a written response with the detailed rational. The Municipality of Kincardine is the host community to the Bruce Nuclear Generating Station, the Ontario Power Generation (OPG) Western Waste Management Facility and the ...
  • Attachment Included
  • The Municipality of Kincardine 1475 Concession 5, R.R. #5, Kincardine, ON N2Z 2X6 Phone: 519-396-3468 | Fax: 519-396-8288 kincardine.ca July 9, 2025 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd Floor Ottawa, Ontario K1A 0H3 RE: Municipality of Kincardine comments on the draft Integrated Tailored Impact Statement Guidelines and input on the Summary of Potential Federal Incidental Activities To Whom it May Concern: Please accept this submission as initial comments from the Municipality of Kincardine on the draft Integrated Tailored Impact Statement Guidelines (herein referred to as the draft Integrated Guidelines) for the Bruce C Nuclear Project and input on the Summary of Potential Federal Incidental Activities. Please note that with the limited time available for public review, these comments are not comprehensive and there may be items in the future that the host community may wish to bring forward to the ...
  • Attachment Included
  • The Municipality of Kincardine 1475 Concession 5, R.R. #5, Kincardine, ON N2Z 2X6 Phone: 519-396-3468 | Fax: 519-396-8288 kincardine.ca June 25, 2025 Bruce C Nuclear Project Impact Assessment Agency of Canada 160 Elgin Street, 22nd Floor Ottawa, Ontario K1A 0H3 RE: Municipality of Kincardine comments on the Bruce C draft Cooperation Plan To Whom it May Concern: Please accept the comments below from the Municipality of Kincardine on the draft Cooperation Plan for the Bruce C Nuclear Project. This submission was endorsed by the Council for the Corporation of the Municipality of Kincardine at the July 9, 2025, meeting. The Municipality of Kincardine is the host Municipality to Bruce Power, Ontario Power Generation’s Western Waste Management Facility and the Douglas Point Nuclear Generating Station. Combined, our Municipality is host to one of the world’s largest nuclear facilities. The Municipality’s expectation is that there will be a ...

Report

Attachment Bruce County Submission to IAAC and CNSC for the Bruce C Nuclear Project Draft TISG and Public Participation Plan

  • Bruce C Nuclear Project
  • Author: Corporation of the County of Bruce
  • Reference Number: 210
  • Submitted: 2025-07-11 - 1:57 PM
  • Project Phase: Planning
  • Participation Notice: Public notice - Public comments Invited and Information Sessions on the Draft Integrated Tailored Impact Statement Guidelines and Draft Public Participation Plan
  • Please find attached the submission for the Bruce C Nuclear Project.
  • Attachment Included
  • Corporation of the County of Bruce 30 Park Street, P.O. Box 70, Walkerton, ON, N0G 2V0 brucecounty.on.ca July 10, 2025 Bruce C Nuclear Project Impact Assessment Agency of Canada 22nd floor, 160 Elgin Street Ottawa, Ontario K1A 0H3 Via email: Bruce@iaac-aeic.gc.ca Dear Sir/Madam, Please find attached Bruce County’s formal submission on the Draft Tailored Impact Statement Guidelines (TISG) and Public Participation Plan for the Bruce C Nuclear Project, as endorsed by County Council on July 10, 2025. As the upper-tier municipality for eight lower-tier (local) municipalities, Bruce County is responsible for delivering a range of infrastructure and services that are expected to be directly impacted by this project— including emergency response, transportation, housing, and workforce development. Our submission reflects support for the need for municipal readiness and community well-being as the Bruce C Nuclear Project moves forward in the Impact Assessment ...

Report
Date modified: