Public Safety Canada Federal Authority Advice Record - Tilbury Phase 2 LNG Expansion Project

Numéro de référence
20
Texte

Hello,

The  interpretation of the Public Safety Canada, Pacific Regional Office is that we do not have a direct role in the subject areas and assessment for the Tilbury Phase 2 Expansion. The assessment is expected to to be focused at the regulatory and legislative levels, and presumably any emergency preparedness or mitigative activities during project development would be prescribed by regulations to be commented on by the specific regulatory provincial and federal departments.

A role that Public Safety could have, should there be a major emergency related to the site or project in the future, would be to facilitate federal and federal/provincial coordination during emergency response. Note that this would be for a major incident exceeding the routine response mechanisms for involved departments. I have attached the link to the Federal Emergency Response Plan (FERP) which describes this role.

https://www.publicsafety.gc.ca/cnt/rsrcs/pblctns/mrgnc-rspns-pln/index-en.aspx

While we do have an interest in disaster risk reduction, which can include any measures to reduce the likelihood of an emergency and environmental or community impacts, again I suspect this is out of scope as it comes from a broader policy lens, and likely specific requirements to prevent or mitigate incidents related to this project will be prescribed by sector-specific regulations.

Please advise if you require anything further at this time.

Thank you,

Andrew J. Hannan

Regional Director
Public Safety Canada, Pacific Region

Présenté par
Administrateur de la part de Public Safety Canada
Phase
S.O.
Avis public
Avis public - Période de consultation publique et portes ouvertes virtuelles
Pièce(s) jointe(s)
  • PS-SP-#3586079-1-PS PRO Response - Federal Authority Advice Record - Tilbury 2 LNG Impact Assessment - June 3 2020.pdf (283,8 Ko)
  • Date et heure de soumission
    2020-06-03