Document Notice of time limit suspension with reasons

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 56
  • Document Date: 2026-03-13
  • Document: 165391E.html
  • Relevance: 395.68
  • Notice of time limit suspension with reasons Ottawa — March 13, 2026 — On March 11, 2026, the Impact Assessment Agency of Canada (IAAC) suspended the 180-day time limit for the planning phase under the Impact Assessment Act for the Salt Springs Natural Gas Power Generation Facility Project proposed by IESO Nova Scotia, the province's Independent Energy System Operator (the proponent). IAAC has taken this action in consideration of a written request from the proponent that the time limit be ...
1 alternate format found
French HTML
  • Relevance: 344.68
  • Avis de suspension de délai avec motifs Ottawa — 13 mars 2026 — Le 11 mars 2026, l'Agence d'évaluation d'impact du Canada (AEIC) a suspendu le délai de 180 jours pour l'étape préparatoire en vertu de la Loi sur l'évaluation d'impact pour le projet de centrale électrique au gaz naturel Salt Springs, proposé par IESO Nova Scotia, l'exploitant indépendant du système d'énergie de la province (le promoteur). L'AEIC a pris cette mesure à la suite d'une demande écrite du promoteur (anglais ...

Document Summary of Issues

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 53
  • Document Date: 2026-02-19
  • Document: 165066E.pdf
  • Relevance: 393.31
  • 1 Summary of Issues Salt Springs Natural Gas Power Generation Facility Project The Summary of Issues outlines the key issues that the Impact Assessment Agency of Canada (IAAC) considers relevant for the federal impact assessment process for the Salt Springs Natural Gas Power Generation Facility Project (the project). The proponent’s response to the Summary of Issues will support decision-making by IAAC on whether further assessment is required under section 16 of the Impact ...
1 alternate format found
French PDF
  • Relevance: 342.31
  • 1 Sommaire des questions Projet de centrale électrique au gaz naturel Salt Springs Le sommaire des questions décrit les enjeux clés que l'Agence d'évaluation d’impact du Canada (AEIC) juge pertinents pour le processus fédéral d'évaluation d’impact pour le projet de centrale électrique au gaz naturel Salt Springs (le projet). La réponse du promoteur au sommaire des questions permettra d’éclairer la décision de l'AEIC quant à savoir si une évaluation d’impact approfondie est equise en ...

Document Fisheries and Oceans Canada - Federal Authority Advice Record

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 33
  • Document Date: 2026-02-03
  • Document: 164927E.pdf
  • Relevance: 391.59
  • Unclassified - Non-Classifié Federal Authority Advice Record (FAAR) FAAR Response must be submitted by January 28, 2026 Salt Springs Natural Gas Power Generation Facility Project – Independent Energy System Operator – Nova Scotia. Registry File: 90114 Department/Agency Fisheries and Oceans Canada Lead Contact Hayley Doyle Full Address Bedford Institute of Oceanography 1 Challenger Drive P.O. Box 1006, Station 500 Dartmouth, Nova Scotia, B2Y 4A2 Email ...
1 alternate format found
French PDF
  • Relevance: 340.59
  • Unclassified - Non-Classifié Fiche d’information de l’autorité fédérale (FIAF) La réponse au FIAF doit être soumise avant le 28 janvier, 2026 Projet de centrale électrique au gaz naturel Salt Springs – Independent Energy System Operator – Nova Scotia. Numéro de dossier du Registre : 90114 Ministère ou organisme Pêches et Océans Canada Contact principal Hayley Doyle Adresse complète Institut océanographique de Bedford 1, promenade Challenger, C.P. 1006, Station 500 ...

Document Health Canada - Federal Authority Advice Record

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 55
  • Document Date: 2026-01-28
  • Document: 165141E.pdf
  • Relevance: 390.95
  • 1 Refer to the Memoranda of Understanding with IAAC. 1 An issue is material to decision making if its analysis is anticipated to affect the conclusions on (1) whether adverse effects within federal jurisdiction or direct and incidental adverse effects (collectively adverse federal effects) are likely not significant, or of low, medium or high significance; (2) appropriate mitigation measures for significant adverse federal effects; or (3) justification in the public interest. ...
1 alternate format found
French PDF
  • Relevance: 339.95
  • Unclassified / Non classifié Fiche d’information des autorités fédérales (FIAF) La FIAF doit être soumise avant le 28 janvier 2026 (l’original) Projet de centrale électrique au gaz naturel Salt Springs – Exploitant indépendant du réseau énergétique (IESO) – Nouvelle-Écosse Numéro de dossier du registre : 90114 Ministère ou organisme Santé Canada Contact principal Jérémie Allain Adresse complète 101 boulevard Roland-Therrien, Longueuil QC J4H 4B9, Canada Place ...

Document Environment and Climate Change Canada - Federal Authority Advice Record

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 54
  • Document Date: 2026-01-28
  • Document: 165132E.pdf
  • Relevance: 390.95
  • UNCLASSIFIED - NON CLASSIFIÉ Federal Authority Advice Record (FAAR) FAAR Response must be submitted by January 28, 2026 Salt Springs Natural Gas Power Generation Facility Project – Independent Energy System Operator – Nova Scotia. Registry File: 90114 Department/Agency Environment and Climate Change Canada Lead Contact Stephen Zwicker Full Address 16th Floor Queen Square 45 Alderney Drive, Dartmouth NS B2Y2N6 Email stephen.zwicker@ec.gc.ca Telephone (902)402-7145 ...
1 alternate format found
French PDF
  • Relevance: 339.95
  • Fiche d’information de l’autorité fédérale (DCAF) La réponse au FIAF doit être soumise avant le 28 janvier 2026 Projet de l'installation de production d'électricité au gaz naturel de Salt Springs – Système énergétique indépendant Opérateur – Nouvelle-Écosse. Dossier du registre : 90114 Ministère ou organisme Environnement et Changement climatique Canada Contact principal Stephen Zwicker Adresse complète 45, promenade Alderney, 16e étage, immeuble Queen ...

Document Indigenous Services Canada - Federal Authority Advice Record

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 52
  • Document Date: 2026-01-28
  • Document: 165013E.pdf
  • Relevance: 390.95
  • UNCLASSIFIED - NON CLASSIFIÉ Federal Authority Advice Record (FAAR) FAAR Response must be submitted by January 28, 2026 Salt Springs Natural Gas Power Generation Facility Project – Independent Energy System Operator – Nova Scotia. Registry File: 90114 Department/Agency Indigenous Services Canada Lead Contact Norah Kielland Full Address 10 Rue Wellington Gatineau, QC Email Norah.kielland@sac-isc.gc.ca Telephone Alternate Contact ...
1 alternate format found
French PDF
  • Relevance: 339.95
  • Fiche d’information de l’autorité fédérale (FIAF) La réponse au FIAF doit être soumise avant le 28 janvier, 2026 Projet de centrale électrique au gaz naturel Salt Springs – Independent Energy System Operator – Nova Scotia. Numéro de dossier du Registre : 90114 Ministère ou organisme Services aux Autochtones Canada Contact principal Norah Kielland Adresse complète 10, rue Wellington, Gatineau (Québec) Adresse courriel Norah.kielland@sac-isc.gc.ca Téléphone Autre contact ...

Document Natural Resources Canada - Federal Authority Advice Record

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 34
  • Document Date: 2026-01-26
  • Document: 164928E.pdf
  • Relevance: 390.74
  • Andy Walter Project Manager, Atlantic Region Impact Assessment Agency of Canada Submitted by email: SaltSprings@iaac-aeic.gc.ca 28 January, 2026 Subject: NRCan Federal Authority Advice Record for the Salt Springs Natural Gas Power Facility Project On January 5, 2026 Natural Resources Canada (NRCan) received your request to review the Initial Project Description (IPD) and to submit a completed Federal Authority Advice Record form (FAAR) for the Salt Springs Natural Gas Power ...
1 alternate format found
French PDF
  • Relevance: 339.74
  • Andy Walter Chef de projet, région de l’Atlantique Agence d’évaluation d’impact du Canada Soumis par email: SaltSprings@iaac-aeic.gc.ca 28 janvier 2026 Objet : Fiche d’information des autorités fédérales de RNCan concernant le projet de centrale électrique au gaz naturel de Marshdale Le 5 janvier 2026, Ressources naturelles Canada (RNCan) a reçu votre demande d’examen de la description initiale du projet (DIP) et de soumission d’une Fiche d’information des autorités fédérales ...

Document Public notice - Comments invited on the summaries of the Initial Project Descriptions and funding available

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 4
  • Document Date: 2026-01-05
  • Document: 164362E.html
  • Relevance: 388.5
  • Public notice Comments invited on the summaries of the Initial Project Descriptions and funding available January 5, 2026 — Ottawa, Ontario The Impact Assessment Agency of Canda (IAAC) has accepted IESO Nova Scotia's initial project descriptions for two separate natural gas power generation facility projects to be developed in Pictou County, Nova Scotia. One project would be located in Marshdale and the other in Salt Springs. As proposed, each project would generate up to 300 megawatts ...
1 alternate format found
French HTML
  • Relevance: 337.5
  • Avis public Période de consultation publique sur les résumés des descriptions initiales de deux projet et possibilité d'aide financière Le 5 janvier 2026 - Ottawa (Ontario) L'Agence d'évaluation d'impact du Canada (AEIC) a accepté les descriptions initiales des projets d'IESO Nova Scotia pour deux projets distincts de centrales électriques au gaz naturel qui seront développés dans le comté de Pictou, en Nouvelle-Écosse. L'un des projets serait situé à Marshdale et l'autre à Salt Springs. ...

Document Supporting Geospatial Data - Initial Project Description

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: Geospatial data files
  • Reference Number: 3
  • Document Date: 2025-12-15
  • Document: 164363E.html
  • Relevance: 386.28
  • Supporting geospatial data – Initial Project Description  Independent Energy System Operator – Nova Scotia has provided, on December 15, 2025, electronic geospatial data files related to the Salt Springs Natural Gas Power Generation Facility Project. The dataset contains the following three layers for maps provided in the Initial Project Description. These data files are available to the public under the terms of the Open Government Licence – Canada. Layer name Page number Salt Springs ...
1 alternate format found
French HTML
  • Relevance: 335.28
  • Données géospatiales connexes – Description initiale du projet Independent Energy System Operator – Nova Scotia a fourni des fichiers électroniques de données géospatiales le 15 décembre 2025 liées au Projet de centrale électrique au gaz naturel Salt Springs. L'ensemble de données contient trois couches pour les cartes fournies dans la description initiale du projet (anglais seulement). Ces fichiers de données sont mis à la disposition du public selon les termes de la Licence du gouvernement ...

Document Summary of the Initial Project Description of a Designated Project

  • Project Salt Springs Natural Gas Power Generation Facility Project
  • Document Category: For Public Participation
  • Reference Number: 2
  • Document Date: 2025-12-15
  • Document: 164300E.pdf
  • Relevance: 386.28
  • December 2025 ENVIRONMENTAL ASSESSMENT REGISTRATION DOCUMENT & INITIAL PROJECT DESCRIPTION Plain Language Summary Fast Acting Natural Gas Power Generation Facility – Salt Springs (IAAC Project Title: Salt Springs Natural Gas Power Generation Facility) Prepared for: IESO Nova Scotia Environmental Assessment Registration Document & Initial Project Description December 15, 2025 Plain Language Summary Fast Acting Natural Gas ...
1 alternate format found
French PDF
  • Relevance: 335.28
  • Décembre 2025 DOCUMENT D'ENREGISTREMENT À L'ÉVALUATION ENVIRONNEMENTALE & DESCRIPTION INITIALE DU PROJET Résumé en langage simple Installation de production d'électricité au gaz naturel à action rapide – Salt Springs (Titre du projet IAAC : Installation de production d'électricité au gaz naturel de Salt Springs) Préparé pour: IESO Nouvelle-Écosse Document d'enregistrement de l'évaluation environnementale et description initiale du ...