Notice of Determination

Delta, B.C. –March 17, 2022– The Vancouver Fraser Port Authority has determined that the proposed Westshore Terminals Berth 2 Mooring Dolphin Upgrades – Extension to Expiry Date located at 1 Roberts Bank, Delta is not likely to cause significant adverse environmental effects.

This determination was based on a consideration of the following factors:

  • Impacts on rights of Indigenous peoples
  • Indigenous knowledge
  • Community knowledge
  • Comments received from the public
  • Technically and economically feasible mitigation measures

Mitigation measures taken into account for this determination are:

  • Mitigation measures that were part of the project and environmental review of Project Permit PER No. 19-187

The Vancouver Fraser Port Authority is satisfied that the carrying out of the project is not likely to cause significant adverse environmental effects.

Therefore, the Vancouver Fraser Port Authority may carry out the project, exercise any power, perform any duty or function, or provide financial assistance to enable the project to be carried out in whole or in part.

For up-to-date information on the project, visit our website.

Document reference number: 4