September 14, 2020 – A new project has been proposed and before proceeding, the Montreal Port Authority (MPA) must decide whether the proposed project is likely to cause significant adverse environmental effects.

 

In order to make an informed decision, the MPA invites the public to comment on this determination. All comments received will be considered public [and may be posted online]. For more information, individuals should consult the Privacy Notice on the Registry website.

 

Written comments must be submitted by September 14, 2020 to:

 

Port of Montreal

2100, Pierre-Dupuy avenue, Wing 1

Montréal, QC, H3C 3R5

Telephone: 514-283-7050

Email: communications@port-montreal.com

 

The Proposed Project

The approximate 116-year old concrete culvert arch structure has not been used for process water discharge for many years. The concrete structure is reaching the end of its service life and should be decommissioning to ensure safety users of the culvert, CN and Neighbouring companies. The culvert is located at the rear east side of the ADM facility situated at 950 Mil Street, Montreal, Quebec and at the south-west corner of the Windmill-Point Basin.

Document Reference Number: 1